Thursday, 14, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Nilakantan & Sons Private Limited vs Union Of India
2024 Latest Caselaw 20592 Mad

Citation : 2024 Latest Caselaw 20592 Mad
Judgement Date : 30 October, 2024

Madras High Court

M/S.Nilakantan & Sons Private Limited vs Union Of India on 30 October, 2024

Author: Krishnan Ramasamy

Bench: Krishnan Ramasamy

                                                                  Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023



                                   IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                         Reserved on                   02.08.2024
                                       Pronounced on                   30.10.2024

                                                        CORAM

                                  THE HON'BLE Mr. JUSTICE KRISHNAN RAMASAMY

                                       Arb.O.P (Com.Div.) Nos.74 and 287 of 2023

                     M/s.Nilakantan & Sons Private Limited
                     rep. by its Managing Director,
                     Mr.N.Jayachandran                                   ... Petitioner in
                                                                 Arb.O.P(Com.Div.)No.74 of 2023
                                                                                  and
                                                                         ... Respondent in
                                                                Arb.O.P(Com.Div.) No.287 of 2023

                                                       Versus

                     Union of India,
                     rep.by the Chief Engineer (Construction),
                     Office of the CAO/Construction,
                     Southern Railway, Egmore,
                     Chennai-600 008.                                  ... Petitioner in
                                                              Arb.O.P(Com.Div.)No.287 of 2023
                                                                                and
                                                                       ... Respondent in
                                                               Arb.O.P(Com.Div.) No.74 of 2023




                     Page No.1/28


https://www.mhc.tn.gov.in/judis
                                                                   Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

                     Prayer in Arb.O.P(Com.Div.)No.74 of 2023:

                                   Arbitration Original Petition filed under Section 34(2) of the
                     Arbitration and Conciliation Act, 1996, seeking to set aside the Arbitral
                     Award dated 29.09.2022 pertaining to the findings in relation to Claim
                     Nos.1,2,3,5,7 and 8 which have been delivered to the parties on 30.09.2022.


                     Prayer in Arb.O.P(Com.Div.)No.287 of 2023:


                                  Arbitration Original Petition filed under Section 34(2) of the
                     Arbitration and Conciliation Act, 1996 seeking to set aside the Arbitration
                     Award passed by the Sole Arbitrator, dated 20.09.2022 and to direct the
                     respondent to pay the costs.


                                         For Petitioner in
                                   Arb.O.P.(Com.Div.)No.74 of 2023
                                              and                   ... Mr.Anirudh Krishnan
                                         Respondent in
                                   Arb.O.P(Com.Div.) No.287 of 2023


                                        For Petitioner in
                                   Arb.O.P.(Com.Div.)No.287 of 2023
                                              and                   ... Mr.M.Karthikeyan, SPC
                                         Respondent in
                                   Arb.O.P.(Com.Div.) No.74 of 2023

                                                            ****



                     Page No.2/28


https://www.mhc.tn.gov.in/judis
                                                                        Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

                                                       COMMON ORDER

These Arbitration Original Petitions arise out of the same Arbitral

Award dated 20.09.2022 passed by the Sole Arbitrator.

2. The petitioner in Arb.O.P.No.74 of 2023 has challenged the

findings of the Sole Arbitrator in respect of rejection of their claim

Nos.1,2,3,5,7 and 8. However, the petitioner/Southern Railway in Arb

O.P.No.287 of 2023 has challenged the Award in toto.

3. For the sake of convenience, the claimant, who is the petitioner in

Arb.O.P.No.74 of 2023 will be hereinafter referred to as 'the petitioner' while

the petitioner/Southern Railway in Arb O.P.No.287 of 2023 will be

hereinafter referred to as 'the respondent'.

4. The brief facts, which led to the filing of the present petitions, are

as follows:

4.1 The respondent floated a Tender on 25.10.2022 for proposed

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

construction of the work of Construction of Road Over Bridge Clear Span of

2 X 35.00 m Clear Span PSC Box Girder, at Km 354/32-33, in lieu of

existing level Crossing No.116, in Magudanchavadi Yard, Jolarpettai

Section. After negotiation, the contract was awarded to the petitioner vide

Letter of Acceptance dated 17.04.2003 for a total value of Rs. 1,14,04,289/-

with a period of completion of 12 months i.e., to complete the works on or

before 16/04/2004. Thereafter, both the parties have entered into an

Agreement on 08.09.2003, which is subject to the General Conditions of

Contract (in short, 'GCC”) of the respondent. The award of contract

comprised into 4 components, viz., Annexure-A: First Component for

Rs.23,57,539/- comprising of Excavation work, CC, RCC etc., Annexure- B

- Second Component for Rs.1,05,750/- relating to removing of the existing

lifting barriers and restoration of Track etc., Annexure -C- Rs.56,00,000/-

comprising of Design and Construction of Pre-stressed Concrete

Superstructure (Box Type), Parapet walls, including Casting in position etc.,

conforming to Railways General Arrangement Drawings No.CN/332-

2000/1 and to Contractors' Design and Detailed Drawings, duly satisfying

the provisions in various IRC Codes and approval by the Railways; and

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

Annexure D-Rs.33,41,000/- relating to supply of Cement and Steel.

4.2 The petitioner has also furnished Security Deposit of

Rs.3,00,000/- after adjustment of EMD of Rs.50,000/- and balance

Rs.2,50,000/- in the form of Bank Guarantee.

4.3 While so, the dispute arises between the parties, which according

to the learned counsel for the petitioner is as follows:

4.4 The petitioner sent a letter dated 02/05/2003 to the Respondent

seeking Drawings for RCC details of Raft Foundation, Column, Trestle

Beam etc., along with GAD, for execution of the ROB Work. The petitioner

had submitted Design of PSC Box Girder Superstructure given by their

Consultant i.e., M/s.Jayshila Consultants, to the respondent on 09/07/2003.

Thereafter, the petitioner, vide letter dated 10.07.2003, in order to

commence the work of Foundation and Sub-Structure, requested the

respondent to furnish Drawings. However, the respondent informed on

09/07/2003 that the minor changes in the already approved Drawings will

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

be at capping Beam level and all the Structures can be cased up to that level

and that alignment marking was yet to be finalized with the Highways

Department.

4.5 The petitioner, vide letter dated 15/09/2003, having mobilized

Men and Machinery at site, requested the respondent to furnish Working

Drawings from to commence the work. But the respondent, only on

14/10/2003 only, the respondent sent the Drawings showing the detail of

Substructure for the ROB work. However, the petitioner, vide letter dated

31.10.2003 pointed out that an impediment had to be removed at the Third

Foundation location and once again requested the respondent to expedite the

approval for Superstructure Designs and Drawings.

4.6 According to the petitioner, nearly eight month period has been

lost in carrying out the Sub-structure work itself and still the Design and

Drawings for the Superstructure Box Girder furnished by the petitioner on

09/07/2003, had not been approved by the Respondent. Also considering the

steep increase in the Steel and Sand Prices and difficulty in procuring the

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

same, the petitioner requested for their First Extension to the Currency of the

Contract by 16/12/2004. The petitioner, vide letter dated 27.4.2004, pointed

out to the respondent that for want of approval for extension of time, the

work of foundation for Pier 1, ready for concreting with reinforcement and

progress in Column in Pier 2, got held up. The petitioner also brought to the

notice of the respondent the inconvenience that they confronted vide letter

dated 21.05.2004, mainly on account of change of Officers, holdup of

execution work for want of extension of currency, losses on account of idling

of establishment infrastructure and labour, very high rates of the market

price of Reinforcement Steel and not even getting the First Payment for the

work done so far etc.,

4.7 The petitioner vide letter dated 30/06/2004 addressed to the

Respondent stating that they submitted the Design and Drawing for the

Staging Arrangements for the ROB, after completing the Foundation and

Sub-structure work in anticipation of the approval for Superstructure.

Further, the petitioner also vide letter date 31/07/2004, informed the

respondent that the interference of the Highways Engineers to reduce the

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

depth of the Box Girder in the Railway's Portion and the Claimants

inclination of not adducing to that, on account of the Detailed Designs

already submitted to the Respondent more than a year back, has not been

approved yet. Any reduction will require redesigning and checking, causing

further delay and increased quantities of pre-stressed cables and other

materials etc., have also been brought out in that communication.

4.8 The petitioner, vide letter dated 07/09/2004, sought clearance

from the Respondent seeking change in level of the Trestle Beam and

mentioned that the Final lift concreting of Column for the work had been

kept pending. In reply to that the petitioner mentioned that the respondent

served on them a Seven Days' Notice on 20/09/2004, as per Clause 62 of the

GCC accusing them for not adhering to the programme charted, despite

extension of currency upto 30/09/2004, under Clause 17 (2) of the GCC.

4.9 The petitioner, vide letter dated 22.09.2004 mentioned various

reasons caused the delay in the completion of works such as, the Highways

Department sought Realignment of the Bridge alignment and these changes

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

were made by Railways warranting redoing the work, receipt of request for

reducing the Road Level etc., The petitioner also mentioned that due to that

the Trestle Beam Levels are proposed for change and the Revised levels had

not been fixed and the last lift of Column could not be concreted. The

position of non-approval of Box Girder Design and Staging Arrangement

Drawings were also part of that communication. However, the Claimant

requested for extending the period of contract upto 28/03/2005.

4.10 According to the petitioner, they have suitably replied the

Respondent, as to what were the problems faced by them while executing

the work after the receipt of LOA, attributable on the part of the Respondent

and the Highways Department, including delay in the payment of their CC

Bills, and requested them to refrain from taking any stringent action. Based

on that the Respondent vide his communication dated 15/10/2004 under the

same Clause 17(2) of the GCC, extended the time for completion of work

from 01/10/2004 to 28/03/2005.

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

4.11 The petitioner vide letter 24.07.2005, pointed that due to non-

submission of Design and Drawings for Superstructure for Staging works as

per GCC, having awarded the work on 17/04/2003, the entire delay was on

account of the Respondent only. The petitioner brought to the notice of the

respondent vide letter dated 10.08.2005 the reasons for the hold up of work

i.e., for want of approval of Drawings for the Staging arrangements and

Superstructure Design and Drawings, having submitted to the Respondents

on 30/06/04 and 09/07/2003 respectively and the losses on account of Idle

Machinery and Overheads and also brought out that if the Costs of

Construction with interest @ 21%, not compensated, which necessitated the

petitioner to take steps to resolve them through Arbitration process.

4.12 The petitioner, vide letter dated 19.09.2005 informed the

respondent detailing all the events that had taken place right from the

beginning of execution of work and the reasons for the delay and seeking

extension(s) of time and requested to withdraw the 48 Hours' Notice served

on them by the Respondent on 16/09/2005 and refer to their claims for

damages, to an independent and impartial Tribunal on mutual consent.

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

5. However, after expiry of the 48 Hours' Notice period, the

respondent vide Termination Notice, dated 14.11.2005, terminated the

contract in terms of Clause 62 of the GCC.

6. On the other hand, the learned Senior Panel Counsel appearing for

the respondent, would submit the following:

6.1. The respondent, vide communication dated 09.07.2003, advised

the petitioner to start the work since the foundation and substructure

Drawing had been issued to the petitioner.

6.2 As regards shortcomings in the execution of Foundation work on

the Third Location pointed out by the petitioner, the respondent vide

communication dated 03.11.2003, duly advised the petitioner to remove the

debris and commence the work on the Two Pier locations. The Respondent,

vide letter dated 31/07/2003 informed the petitioner that the progress of

work was not up to the required rates expected, as observed during the

Inspection at the Site, and to make up the deficiency by increasing men and

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

machinery, so as to complete the work within the currency period, failing

which, they would proceed against the petitioner for the poor progress of the

work and advised them to restart and speed up the progress of work.

Further, vide letters dated 19/02/04 and 05/06/2004 also, the respondent

informed the petitioner that the progress of work was very poor, citing

various reasons and wanted the petitioner to increase the ,en and machinery

for achieving the execution of Pier works and complete the Bridge work

within the currency period granted.

6.3 However, since the petitioner has not been adhering to the target

dates and also having failed to seek extension of time beyond 28/03/2005,

the respondent served on the petitioner a Seven Days' Notice on 18/03/2005

and advised the petitioner to make good the defaults and carry on the work,

to the entire satisfaction of the Engineer-in-charge. Thereafter, the Claimant

was also served again a Seven Days' Notice on 03/08/2005 inasmuch as the

work was not progressing as per the programme and not adhering to the

target dates.

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

6.4 Therefore, followed by Seven Days' Notice, the respondent has

served 48 Hours' Notice on the petitioner on 16.09.2005 as there was no

progress of work at the site.

6.5 The petitioner, vide communication dated 26/09/2005 has

mentioned that after completion of sub-structure, the work was stopped, as

the Staging Design and Drawing have not been approved. In reply tho this,

the Respondent also mentioned that based on the advice from

Dy.CE/Design/MS vide his letter dated 22/05/2005, the petitioner was

advised to rectify the defects vide letter dated 24/08/2005 and the same not

received and the petitioner had also not asked for further extension of

currency. As the currency was expiring on 30/11/2005, the respondent

terminated the Contract by invoking Clause 62 of GCC.

7. The petitioner has approached this Court by way of filing

O.P.No.13 of 2021, seeking for appointment of Sole Arbitrator to adjudicate

the dispute between the parties. This Court, vide order dated 13.08.2021,

appointed one Thiru V.Murali Mohan as Sole Arbitrator.

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

8. On consideration of both Statement of claims and counter statement

filed by both parties vis-a-vis documentary evidence and arguments

advanced, the learned Sole Arbitrator has passed the Award dated

29.09.2022.

9. Challenging the same, both the parties have come forward with the

present Original Petition.

10. Heard the learned counsel for the petitioner and the learned Senior

Panel Counsel for the respondent and perused the entire materials available

on record.

11. In the case on hand, 8 claims and 4 counter claims were filed

before the Arbitral Tribunal by the claimant and the respondent respectively.

Out of those claims, Claim Nos. 4 & 6 were awarded in entirety, Claim

Nos.2 & 7 were awarded partially and the Claim Nos.1, 3, 5 & 8 were

rejected. Further, the Tribunal has arrived at a conclusion that the contract

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

was illegally terminated by the respondents and hence, all the 4 counter

claims filed by the respondent were rejected by the Tribunal.

12. CLAIM No.1:

12.1 Claim No.1 is pertaining to the “Loss of profit due to reduced

turnover of work” and the amount claimed under this head is a sum of

Rs.13,46,097/-. The Arbitral Tribunal had rejected this claim in entirety.

12.2 While rejecting this claim, the Tribunal has stated that the

claimant was able to complete the work only to the tune of a sum of

Rs.24,43,543.45 out of the total value of contract i.e., a sum of

Rs.1,14,04,289/-, that too, the said work was completed with a lapse of 23

months from the date of LOA, which works out to a value of Rs.1,06,444/-

per month.

12.3 According to the petitioner, the said lapse has occurred only due

to the delay on the part of the respondent in approving the drawings and

realignments and hence, the said lapse is only attributable to the respondent.

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

However, without considering this aspect, the Tribunal had rejected this

claim of the petitioner in entirety.

12.4 On the other hand, according to the respondent, the Arbitral

Tribunal had considered all the aspects in a proper perspective and decided

the matter based on the available facts. Hence, there is no requirement for

this Court to interfere either on the aspect of illegality or on the aspect of

public policy.

12.5 Upon perusal of award, it appears that the Tribunal had applied

Clause 60(2) of General Conditions of Contract – “Determination of

Contract”, wherein it has been stated that the Contractor shall have no claim

to any payment of compensation or otherwise, howsoever on account of any

profit or advantage which he might have derived from the execution of the

work in full, but which he did not derive in consequence of determination of

the contract.

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

12.6 In this case, even after the expiry of Contract period, i.e., after a

lapse of 23 months, the claimant was only able to complete the work to the

tune of Rs.24,44,223/- out of total contract value of Rs.1,14,04,289/-.

Further, the claimant was in agreement for extending the contract from time

to time. In such case, without completing the work, that too, when the

claimant was not inclined to continue the work, they cannot expect any

amount towards this head. On the other hand, if the work was duly

completed by the petitioner, all these issues would have been considered in

an affirmative way by the Arbitral Tribunal. However, the claim under the

head Loss of profit due to reduced turnover of work would not arise for

partial completion of work. All these aspects were well considered by the

Tribunal.

12.7 Further, the Tribunal had considered and awarded the

compensation under the other heads viz., i) loss due to extended use of

materials, machineries and equipment, ii) damages due to non-

payment/delay on various claims, iii) loss due to increased cost of carrying

out the work, iv) overhead for the extended period. In view of the provisions

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

of GCC and based on the available facts and circumstances of this case, the

Tribunal had rightly considered the claim and passed the award. Therefore,

this Court does not find any error in rejecting the claim under the head Loss

of profit due to reduced turnover of work as the claimant was compensated

appropriately under the other heads.

13. CLAIM No.2:

13.1 The Claim No.2 is pertaining to “Losses due to extended use of

Materials, Machineries and Equipment” and the amount claimed under this

head is a sum of Rs.30,12,355/-. This claim was partially awarded by the

Tribunal to the extent of a sum of Rs.15,06,178/-.

13.2 The grievance of the claimant is that though the Tribunal had

considered this claim in favour of the claimant, all of a sudden, the

compensation under this head was reduced to the extent of 50% by the

Tribunal without assigning any reason.

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

13.3 In reply, it was contended by the respondent that as per the

terms of Clause 17 of GCC, no claim can be made for the extended period

under the present head. However, even without any bill with regard to the

additional work for extended use of materials, machineries and equipment,

the Tribunal had awarded 50% of the claim and hence, the same is liable to

be set aside.

13.4 Upon perusal of award, it appears that 50% of the claim amount

was awarded by the Tribunal under this head. It is an admitted fact that the

work was delayed for a period of 23 months, despite which, the work was

not completed by the claimant and they have not made any attempt to extend

for further period to carry on and complete the work. At this juncture, the

contract was illegally terminated by the respondent. Hence, the Tribunal

arrived at a conclusion that 50% of the loss under this head is attributable to

the respondent and they are liable to pay the same. On the other hand, if any

attempt was made by the claimant to continue and complete the work, the

Tribunal would have considered this claim and awarded the compensation to

the full extent.

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

13.5 All the above aspects were well considered by the Tribunal and

hence, the question of violation of basic notion of justice would not arise.

Further, this Court does not find any error in awarding this claim partially.

Therefore, the same stands confirmed.

14. CLAIM No.3

14.1 The Claim No.3 is pertaining to “Payment towards work done:

Design of Superstructure” and the claim amount is a sum of Rs.2,80,000/-.

This claim was rejected by the Tribunal.

14.2 According to the claimant, they have provided the Design of

Superstructure and hence, they are entitled fees for the same. However, no

amount was awarded by the Tribunal under this head. On the other hand, as

per the contention of the respondent, the claimant had only submitted a

rough drawing of Superstructure on 09.07.2003, however, the same was not

approved by the respondent. Further, the claimant had neither provided the

original drawing of Superstructure nor cooperated with the respondent for

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

further process. Hence, according to the respondent, the Tribunal has rightly

rejected the claim.

14.3 A perusal of award and documents available on record makes in

clear that only the rough drawing of Superstructure was provided by the

claimant and the originals of those drawings were not provided. Further, it

was stated by the Tribunal that there was no cooperation from the claimant

for taking joint final measurements after the termination of Contract and the

same was recorded as 'ex-parte'. Hence, the question of violation of basic

notion of justice would not arise and therefore, this Court is of the view that

the Tribunal had rightly rejected the claim.

15. CLAIM No.4:

15.1 The Claim No.4 is pertaining to the “Increased costs of

carrying out the work” and the amount claimed under this head is a sum of

Rs.5,60,528/-. This claim was awarded by the Tribunal in its entirety.

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

15.2 An objection was raised by the respondent in allowing this claim.

According to the respondent, due to the violation on the part of the claimant

in executing the work, this claim should have been rejected by the Tribunal.

However, in non-application of mind, this claim was awarded by the

Tribunal in its entirety.

15.3 In this case, the Contract was prolonged for a period of 23

months, even beyond the period, which was determined by the parties

concerned. Naturally, based on the market conditions, the cost of work and

labour would have increased. In such case, this Court is of the view that the

Tribunal has rightly considered all these aspects and awarded the

compensation and hence, it stands confirmed.

16. CLAIM No.5

16.1 The Claim No.5 is pertaining to “Losses due to Labour” and the

claim amount is a sum of Rs.4,48,699/-. This Claim was rejected by the

Tribunal.

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

16.2 Upon perusal of award, it is clear that the Tribunal has already

awarded compensation under the heads, viz., i) loss due to extended use of

materials, machineries and equipment, ii) damages due to non-

payment/delay on various claims, iii) loss due to increased cost of carrying

out the work, iv) overhead for the extended period. In such case, certainly,

the Tribunal cannot award separate compensation under this head. The loss

claimed under this head was already covered under different heads and

hence, if any compensation was awarded under this head, it will amount to

double entries.

16.3 In view of the above, this Court does not find any error in

rejecting the claim under this head. Hence, the same stands confirmed.

17. CLAIM No.6

17.1 The Claim No.6 is pertaining to the “Overheads for extended

period” and the amount claimed is a sum of Rs.27,01,970/-. This claim was

awarded by the Tribunal at its entirety.

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

17.2 The Tribunal has arrived at a conclusion that the contract was

illegally terminated by the respondent. That apart, there was a delay of 23

months in execution of partial work by the claimant. In such case, the

claimant was supposed to maintain Office with minimum staffs, materials,

etc and hence, the overheads would have occurred. Taking all these aspects

into consideration, the Tribunal has awarded the claim under this head in its

entirety.

17.3 In view of the above, this Court is of the view that there is no

merits in the objections made by the learned counsel for the respondent.

Accordingly, the compensation awarded by the Tribunal under this head

stands confirmed.

18. CLAIM No.7:

18.1 The Claim No.7 is pertaining to “Damages due to non-

payment/Delay on the various claims @18% per annum from 10.08.2005”.

The claim amount was not quantified by the claimant, however, the Tribunal

has quantified and awarded a sum of Rs.16,19,573/-.

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

18.2 In this claim, the Tribunal has awarded interest at the rate of

18% per annum, for the compensation awarded in Claim No.4, from the date

of filing of claim till the date of award. i.e., for a period of 5859 days.

According to the claimant, the awarding of interest by the Tribunal is

improper and in contravention to Clause 64.5 of GCC.

18.3 The Claim No.4 is with regard to the “Increased costs of carrying

out the work” and hence, the Tribunal felt that it would be appropriate to

award interest only for those type claims, etc. That apart, while awarding

damages, the Tribunal has applied its mind and felt that the quantified

amount would be sufficient. The said decision arrived at by the Tribunal is

not against the fundamental policy of Indian Law. Therefore, this Court is

not inclined to interfere with the decision of the Arbitral Tribunal.

Accordingly, the same stands confirmed.

19. CLAIM No.8:

19.1 The Claim No.8 is pertaining to the “Cost of Arbitration” and

the same was rejected by the Arbitral Tribunal. Though this claim was

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

raised before this Court, it was not pressed during the argument and hence,

the rejection of this claim stands confirmed.

20. COUNTER CLAIMS 1 to 4:

20.1 As far as rejection of counter claims is concerned, this Court is of

the view that once the Tribunal has arrived at a conclusion that the Contract

was illegally terminated by the respondent, the awarding of compensation

for the heads pertaining to counter claims would not arise.

20.2 In this case, the Tribunal had already traced out the fault on the

part of the respondent. When such being the case, this Court is of the view

that the Tribunal has rightly rejected the counter claims filed by the

respondent.

21. Both the learned counsel had referred various judgments. The law

laid down by the Hon'ble Apex Court is settled law. However, in view of the

decision arrived at by this Court, the aforesaid judgments referred by both

the learned counsel have not been considered by this Court.

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

22. For all the reasons stated above, this Court does not find any

merits in both the original petitions and hence, the same are liable to be

dismissed. Accordingly, these Arbitration Original Petitions are dismissed.

No cost.

30.10.2024

Speaking order : Yes Index : Yes Neutral Citation: Yes suk/nsa

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.74 and 287 of 2023

KRISHNAN RAMASAMY.J.,

suk/nsa

Arb.O.P (Com.Div.) Nos.74 and 287 of 2023

30.10.2024

https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter