Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Praj Industries Limited vs M/S.Veerapandi Common Effluent ...
2024 Latest Caselaw 20589 Mad

Citation : 2024 Latest Caselaw 20589 Mad
Judgement Date : 30 October, 2024

Madras High Court

M/S.Praj Industries Limited vs M/S.Veerapandi Common Effluent ... on 30 October, 2024

Author: Krishnan Ramasamy

Bench: Krishnan Ramasamy

                                                                    Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

                                   IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                            Reserved on                 01.08.2024
                                           Pronounced on                30.10.2024

                                                           CORAM

                                  THE HON'BLE Mr. JUSTICE KRISHNAN RAMASAMY

                                       Arb.O.P (Com.Div.) Nos.534 and 634 of 2022

                     M/s.Praj Industries Limited
                     represented by its authorized Signatory,
                     Venugopalan Nair                                       ... Petitioner in
                                                                   Arb.O.P(Com.Div.)No.534 of 2022
                                                                                      and
                                                                            ... Respondent in
                                                                   Arb.O.P(Com.Div.) No.634 of 2022

                                                          Versus

                     M/s.Veerapandi Common Effluent Treatment Plant Limited,
                     No.548/1, Karuppa Gounden Palayam,
                     Cotton Market Post,
                     Tirupur-641 604.                              ... Petitioner in
                                                         Arb.O.P(Com.Div.) No.634 of 2023
                                                                             and
                                                                   ... Respondent in
                                                         Arb.O.P(Com.Div.) No.534 of 2023

                     Prayer in Arb.O.P(Com.Div.)No.534 of 2022:

                                  Arbitration Original Petition filed under Section 34(2) of the
                     Arbitration and Conciliation Act, 1996, seeking to set aside the Arbitral

                     Page No.1/26


https://www.mhc.tn.gov.in/judis
                                                                     Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

                     Award dated 05.04.2022 partly passed by the learned Arbitral Tribunal.


                     Prayer in Arb.O.P(Com.Div.) No.634 of 2022:


                                  Arbitration Original Petition filed under Section 34(2) of the
                     Arbitration and Conciliation Act, 1996 seeking to set aside the Arbitral
                     Award, dated 05.04.2022 passed by the learned Arbitral Tribunal.


                                         For Petitioner in
                                   Arb.O.P.(Com.Div.)No.534 of 2022
                                              and                   ... Mr.Srinath Sridevan,
                                         Respondent in                  Senior Counsel for
                                   Arb.O.P(Com.Div.) No.634 of 2022 M/s.Ramya Subramaniam

                                        For Petitioner in
                                   Arb.O.P.(Com.Div.) No.634 of 2022
                                              and                    ... Mr.R.Vidhya Shankar
                                         Respondent in
                                   Arb.O.P.(Com.Div.) No.534 of 2023

                                                              ****

                                                      COMMON ORDER

These Arbitration Original Petitions arise out of the same Arbitral

Award dated 05.04.2022 passed by the learned Arbitral Tribunal.

2. The petitioner in Arb.O.P.No.534 of 2022 has challenged the

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

findings of the Tribunal in respect of rejection of their claim Nos.2, 3, 4 and

their counter claim, while the petitioner in Arb O.P.No.634 of 2022 has

challenged the entire Award.

3. For the sake of convenience, the claimant, M/s.Veerapandi

Common Effluent Treatment Plant Pvt.Ltd, who is the petitioner in

Arb.O.P.No.634 of 2022 will be hereinafter referred to as 'the petitioner'

while the petitioner in Arb O.P.No.534 of 2022, viz., M/s.Praj Industries

Limited, will be hereinafter referred to as 'the respondent'.

4. The brief facts, which led to the filing of the present petitions, are

as follows:

4.1 The petitioner approached the Arbitral Tribunal, by way of a

claim petition, seeking to pass an award for a sum of Rs.29,10,00,000/-

payable by the respondent. The brief facts of the claim petition, are as

follows:

4.2. The petitioner is the Limited Company, formed to meet the

requirements of dying units at Tirupur, who are the Members / Shareholders

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

of the petitioner company, to comply with the statutory guidelines of the

Government of Tamil Nadu to meet the Zero Liquid Discharge (ZLD). The

petitioner Company invited tenders in October, 2012 for the works of

installing, commissioning and operational maintenance of mechanical

evaporator.

5. The Respondent Company approached the petitioner Company and

assured that they are having the requisite expertise, experience, design,

engineering, project management, R&D etc., and they can provide the turn

key solution to the petitioner in achieving Zero Liquid Discharge. The

petitioner Company relied upon the representation made by the Respondent

herein, entered into an Agreement on 28.03.2013 for design, engineering,

sale, supply, erection, and commissioning of mechanical evaporator plant.

The entire work was to be completed within eight months and timely

completion is one of the key criteria of the contract. The total value of the

work was fixed Rs.11,50,00,000/- and the petitioner Company has paid 60%

of the amount i.e., 7.31 crores in full as per the terms of the Agreement.

Consequently, the Respondent Company executed a corporate guarantee on

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

19.04.2013 giving guarantee for performance of their applications under the

Agreement.

6. According to the petitioner, right from the beginning, the

respondent committed inordinate delay and installed machines at a belated

stage. Though the machines have been installed and purportedly attempted

to commission, there was negligible Glauber's Salt recovery. The entire

system was getting chocked within 15 minutes of the operation of the

common effluent treatment plant during trial runs. Even though the

Respondent Company promised to rectify all the defects, they failed not do

so. Ultimately, they attempted making certain modifications in the design

but yet recovery Glauber salt was not satisfactory. The petitioner addressed

repeated letters to the Respondent including the mail dated 31.10.2014 to

which the Respondent replied on 01.11.2014 assuring that performance runs

would be conducted at the earliest after completing necessary pre-

commissioning works. But the commissioning was not completed and this

resulted in a several warnings from the Department of Handloms and

Textiles and Tamil Nadu Pollution Control Board for closure of the

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

petitioner concern for not achieving ZLD even after sanction and release of

Interest Free loan by the Tamil Nadu Government..

7. The petitioner pointed out various defects in the commissioning of

the plants by the mail dated 14.11.2014. The petitioner also conveyed to the

Respondent that there was a serious risk of closure by the Tamil Nadu

Pollution Control Board since ZLD was not achieved for full capacity. To

get over the said problem, the Respondent suggested in their email dated

20.11.2014 that recovery of Mixed Salts can be attempted in the Chiller

Section instead of Glauber Salt, just so that Tamil Nadu Pollution Control

Board may be pacified.

8. At the joint meeting held on 25.11.2014 between the parties, the

Respondent accepted that the plant was a failure, there was no salt recovery

and the Respondent would take steps for rectification so as to achieve at

least 40% within a month, after which, the plant can run with 100% capacity

by end of January 2015. Even after such undertaking also, the Respondent

did not take any steps for the successful completion of the project. The

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

petitioner sent a mail dated 03.12.2014 requesting the Respondent to furnish

the schedule of plan of action to which the Respondent by their mail dated

11.12.2014 agreed to complete modifications and take up the plant run and

further promised that if the plant does not run satisfactorily despite

modifications and alterations, options may be discussed. In the meeting held

on 09.01.2015, the Respondent accepted that the plant was in the trial run

stage was upto 20% capacity/flow only and attempts were being made to

run it at least 40% of its capacity. Till December 2015, as the Respondent

persistently defaulting in completing the commissioning, the petitioner

finally requested the Respondent to submit a comprehensive plan of action

as to how they are intend to reach 100% performance. During the discussion

held on 05.03.2015 the Respondent agreed that the plant was working only

to 25% of the design capacity. Thereafter, the Respondent committed that

by17.04.2015 the full plant will be in operation for full capacity. However,

the Respondent did not take any steps to fulfill the undertaking except again

repeatedly asking for extension.

9. According to the petitioner, they had made all the payments in

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

terms of the Agreement. The plant installed by the Respondent is working

upto a maximum of 15% capacity only. The petitioner herein has forced to

use another evaporator from local supplier and this only helped the

petitioner to meet further 25% capacity. Consequently, the petitioner's

member units are running only with maximum of 40% of their individual

capacity utilization resulting in continuous loss. The petitioner invested

crores of rupees with the Respondent only on the basis of promise that the

Respondent has the expertise assistance to fulfill the requirement of the

petitioner for achieving ZLD. However, the Respondent has abandoned the

project. Consequently, the petitioner had sustained heavy loss, i.e. to the

tune of Rs.29,10,00,000/-.

10. Consequently, the petitioner terminated the contract of the

Respondent by letter dated 19.10.2015. The petitioner also intimated the

Respondent that PMA M/s. Enkem Engineers, Chennai agreed to inspect

and submit the report on the performance of the plant on 03.11.2015 to

05.11.2015 and requested the Respondent to send their representative.

Ultimately, the said M/s. Emkem Engineers Private Limited, Chennai

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

submitted a report on the performance during 17.11.2015 to 20.11.2015 in

which they categorically mentioned the failure of the project. Based on the

said report, the petitioner quantified the loss suffer by the dying units and

garment sector at a sum of Rs.29,10,000/- and sent a notice dated

27.06.2015 calling upon the Respondent to pay the damages as mentioned

above and as the respondent failed to pay the same, the petitioner invoked

arbitration Clause 7 of the Agreement dated 28.03.2013 and filed the claim

petition before the learned Arbitral Tribunal.

11. The respondent company, resisting the claim petition, filed a

defence statement along with counter claim, wherein, at the outset, it is

denied denied that the entire work was to be completed within 8 months as

the timely completion was dependent on timely fulfilment of petitioner 's

several obligations as per the terms of the contract, mainly among others

supply of steam, completion of civil works and other utilities. The payments

made to the respondent was in tranches after an inordinate delay. The

balance price of the contract is still due.

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

12. It is further denied that there is negligible Glauber Salt recovery.

All the equipment were supplied by the respondent on the basis of the

equipment list provided by the petitioner in the tender.

13. On several occasion, the respondent brought to the notice of the

petitioner about process of modifications, addition of specific equipment,

taking into consideration the non-compatibility and non-suitability of the

petitioner given list of equipment for achieving ZLD and producing

Glauber Salt. The choking of the system was entirely due to the scheme of

design basis given by the petitioner in the tender and therefore the

respondent during the execution of the works and subsequent installation of

the equipment was calling upon the petitioner to do design modifications

and add additional equipment. There were no defects at all. On the contrary

the system and equipment was inadequate, for which, the respondent

suggested that the petitioner should carry out necessary design basis

modifications including the addition of equipment and the petitioner also

concurred with this.

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

14. The respondent had informed the petitioner that it is executing

two other projects for ZLD and producing Glauber salt and it is confident of

doing it successfully for petitioner 's project also if the petitioner accepts

for process modifications and addition of specific equipment as suggested

by the Respondent. The respondent denied that they attempted making

certain modifications in design but nothing of alleged modifications resulted

in unsatisfactory performance in recovery of Glauber salt and stated that it

is because of the petitioner not allowing the respondent to make

modifications and that the petitioner prematurely terminated the contract.

15. It is further stated that the petitioner having concurred that the

design basis of the plaint given by the petitioner in tender is not suitable and

compatible, for achieving ZLD, allowed the respondent to carry out

necessary experiments during execution of the project in order to enable the

respondent to suggest the suitable modifications and if required addition of

any equipment. The respondent was continuously doing analysis of the

problems faced by the equipment and its design suggested by the petitioner

in the tender and was doing a root cause analysis. According to the

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

respondent, in course of time through discussions and several meetings that

took place between the Respondent's technical team, the petitioner and its

consultant, the petitioner realized that the design basis for which the tender

was floated was inadequate in terms of capacity and process time and it

required modifications and additions of certain equipment so that the system

is capable of recovering salts and solids to achieve ZLD. Therefore, the

respondent kept on suggesting modifications by way of installing new

equipment so that the plant can achieve ZLD and recover Glauber salt of

desired quantity.

16. It is further stated that the tender document and the agreement do

not contemplate an obligation on their part to suggest modifications and the

heads of account and the basis of calculations are premature, wrongful and

exaggerated. Therefore it cannot be claimed either in equity/law/ contract or

otherwise. The petitioner had not suffered any loss. The calculations are in

the nature of penalty. There is no genuine pre-estimate of Liquidated

Damages. The termination of contract on 19.10.2015 is illegal. The

performance run and report relied upon by the petitioner cannot be accepted.

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

The petitioner has no legal right to reserve any claim to be agitated later on.

The plant in question consists of three parts. The first part being Shell and

Tube based evaporation System for concentration of the effluent. For this

purpose the required steam as specified in the Agreement was to be supplied

by the petitioner in order to achieve the concentration. According to the

respondent even as on today the evaporation which is required and

concentration of effluent which is expected in this equipment is being

carried on even as on today and the same is working as per specifications.

Glauber Salt and thereafter the residue after recovery of Glauber Salt is

inducted into Auxiliary Evaporator and used for further concentration of

effluent and ZLD is achieved. It is stated that the equipment for recovery of

Glauber salt is a bought out item as per the tender conditions. Even at the

time of entering into contract, the respondent informed the petitioner that

the above referred item is a bought out item and the same requires

modification for recovery of require quantity of Glauber salt and

accordingly a clause was incorporated in the Agreement that modifications

as may be required, can be made in the equipment. Therefore, according to

the respondent, after achievement of both the requirements, they discharged

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

their obligations.

17. It is stated that n the date of termination of the contract, the

petitioner has to pay a sum of Rs.4,45,21,294/- being the balance price for

all the supplies completed. This sum carries interest at 15% per annum.

Therefore, the respondent raised a counter claim for a sum of

Rs.6,18,66,302/- including the balance due with interest.

18. While pending the arbitral proceedings, the petitioner also filed an

amended claim statement on 09.08,2018, wherein, while reiterating the

averments made in the claim statement, the petitioner claimed a sum of

Rs.57,50,000/- as Liquidated Damages, refund of the amount paid by the

petitioner to the respondent and expenses incurred to rectify the breach and

to produce ZLD. Rs.7,33,17,179 is the amount paid under the contract to the

respondent and a sum of Rs.2,10,00,000/- in all totalling to Rs.9,43,17,179/-

and lastly Rs. 3,88,80,00,000/- as production loss for the period from

December 2013 to March 2018 until filing of the claim. The value of the

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

claim is totalled to Rs. 131,98,67,179/-.

19. Resisting the amended claim statement filed by the petitioner, the

respondent also filed a additional defence statement, wherein, while denying

the averments made in the additional claim statement, it is stated that all the

amended claims have been abandoned and waived by the petitioner and

therefore, the entire amended claim is liable to be rejected as devoid of

merits and barred by limitation.

20. On consideration of the claim and counter claim statements and

the evidence adduced by the parties, the learned Arbitral Tribunal, vide its

award dated 05.04.2022, dismissed both claim petition and counter claim

petition filed by the parties.

21. Challenging the same, both the parties have come forward with

the present Original Petition.

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

22. Heard the learned counsel for the petitioner and the learned

Senior counsel for the respondent and perused the entire materials available

on record.

23. Learned counsel for the petitioner, who is the claimant before the

Arbitral Tribunal, would submit that in the present case, the petitioner has

launched a claim for Rs.29,10,00,000/- towards liquidated damages for non-

recovery of Glauber Salt as per Clause 10.3 of the Agreement dated

28.03.2013. The said claim was rejected by the Tribunal on the ground that

there were no pleadings at all and no evidence was produced by the

petitioner to substantiate the same. However, the learned counsel would

submit that the pleadings in respect of the claim were made in para 9(g) of

the claim statement and also the calculations were given for the claim of a

sum of Rs.29,10,00,000/-. He would also submit that para 7.4 of the

Additional Claim Statement also talks about the basis of the forumla under

which, based on the performance, the petitioner is entitled for damages

towards non-recovery of Glauber salt. Clause 3 of the Contract pertains to

the performance guarantee, guaranteeing that recovery of Glauber salt for

different ranges of feed TDS will be as per Annexure V Mass Balance, but

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

the same was not considered by the Tribunal. He pointed out that the

Tribunal also ignored the Expert's Report of the PMA which was marked as

Ex.C60-C.V.3, which is crucial evidence to assess the shortfall in recovery

of Glauber salt. The respondent, in fact, guaranteed Glauber salt recovery

should be 5 tonns/hour or 120 tons per day, but there is a shortfall of 97

tonns per day. However, without considering all these aspects and

particularly, the documents produced by the claimant/petitioner, the

Tribunal came to a conclusion as if no document was produced to

substantiate the claim, by the petitioner and rejected the said claim. Hence,

the learned would submit that there is patent illegality committed by the

Tribunal on this aspect while rejecting the claim No.1. Therefore, the award

in respect of claim No.1 is liable to be set aside.

24. As regards claim Nos.2, 3 and 4 are concerned, the same are

pertaining to the additional claims and the Tribunal had rejected the same

on the ground that they were barred by limitation. The learned counsel

would point out that the learned Arbitral Tribunal arrived at the date of

breach as 30.08.2015, as such, the cause of action arose on 01.09.2015,

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

thereby, the claimant had time until 29.08.2018 for making claims and the

amended claim application was filed on 25.08.2018 as could be seen from

the affidavit filed in support of the amendment application filed for

additional claims, which was sworn to by the Chairman on 09.08.2018.

However, these additional claims were rejected by the Tribunal vide order

dated 13.10.2018 and the Tribunal has taken into consideration that the date

of ordering the additional claims as the date for making the additional

claims and thereby, held that they were barred by limitation. The learned

counsel for the petitioner would point out that the date on which, the

additional claims were actually made before the Tribunal should be taken

into consideration and not the date of rejecting them by the Tribunal. It is

not in dispute that the amendment application for additional claims was

filed on 25.08.2018 and as such, these additional claims cannot be held as

barred by Limitation. This vital aspect has not been considered by the

Tribunal and even the judgment in “State of Goa versus Praveen

Enterprises” reported in (2012) 12 SCC 581 was wrongly interpreted by the

Tribunal while deciding the additional claims.

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

25. The learned counsel would submit that the Tribunal held that

claimant/petitioner is entitled to Rs.7.33,17,179/- towards additional claim

No.3 along with interest at 18% p.a. from the date of breach till the date of

actual payment, however, rejected the additional claims as time barred,

which shows non-application of mind on the part of the Tribunal and as

such, the award passed by the lelarned Tribunal suffers from patent

illegality and also it is opposed to public policy of India and hence, the same

is liable to be set aside.

26. Per contra, learned Senior counsel appearing for the respondent

would submit that on the aspect of limitation, no interpretation is required

as the Tribunal has rightly rejected the claims made by the petitioner. As far

as the claim in respect non-recovery of Glauber salt is concerned, he would

submit that the Tribunal has held that no performance trial run was

conducted and rightly came to the conclusion that the petitioner is not

entitled to claim damages towards non-recovery of Glauber salt. As regards

the counter claim is concerned, the learned counsel would submit that

towards balance price, the respondent had incurred Rs.4,45,21,291/- and

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

hence, they are entitled to the same, but the Tribunal has not considered in

proper perspective and erroneously rejected, which is liable to be set aside.

He would submit that as regards the rejection of the claims made by the

petitioner, no interference is required by this Court, however, as regards the

rejection of the counter claim is concerned, he would submit that the

respondent is entitled to Rs.4,45,21,291/- and hence, to this extent, the

award has to be set aside.

27. Upon hearing the learned counsel for the parties and on going

through the entire materials placed on record, it reveals that both parties

have filed Original Petitions since the Tribunal has rejected claims made by

the petitioner as well as the counter claim made by the respondent. As far

as the claim No.1 is concerned, it is pertaining to the liquidated damages

towards non-recovery of Glauber salt to the extent of Rs.29,10,00,000/-.

The Tribunal has rejected this claim on the ground that there was no

pleading and documentary evidence produced by the petitioner and also

performance run has not been conducted, but except mechanical run, based

on which, recovery of Glauber salt could not be determined. The Tribunal

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

was of the view that after mechanical trial run, there was no Glauber salt

recovery, however, on a perusal of the terms and conditions as referred to by

the petitioner, it is clear that the respondent is supposed to recover Glauber

salt at each and every stage of mechanical trial run. To substantiate this, the

claimant/petitioner has filed various documents and also adduced evidence.

However, the Tribunal has completely failed to deal with those vital

documents and evidence, but only rejected on the ground that during

mechanical run, no Glauber salt recovery will be available but during the

performance run alone, there will be recovery of Glauber salt. This finding

of the Tribunal appears to be without considering the documentary

evidence. This Court finds that there is substance in the submissions made

by the learned counsel for the petitioner and for this reason, this Court is of

the view that the conclusion arrived at by the Tribunal in respect of Claim

No.1 is liable to be set aside.

28. As regards claim Nos.2, 3 and 4 are concerned, the same have

been been rejected by the Tribunal on the ground that they are barred by

limitation. The petitioner has made these claims by way of amendment

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

application as additional claims. While considering the claim No.3, the

Tribunal on merits, has reached at a conclusion that the claimant/petitioner

is entitled for a sum of Rs.7,33,17,179/- along with interest at 18% p.a. from

the date of breach till the date of actual payment, however rejected the other

additional claims on the ground that these claims are barred by limitation. It

is pertinent to note that even the Tribunal held that the respondent

committed the breach of contract on 31.08.2015 and therefore, any claim

should have been made on or before 31.08.2018. It is not in dispute that the

petitioner has filed amendment application seeking to add additional claims

on 25.08.2024. The Tribunal, vide order dated 13.10.2018, allowed the

amendment application. As such, the Tribunal has taken into consideration

that the date of ordering the additional claims as the date for making the

additional claims, i.e. 13.10.2018 and thereby, held that they were barred by

limitation. This view of the Tribunal is contrary to law and incorrect. Once

a claim statement is filed before the Tribunal on a particular day and the

same is taken on file on the same day, that would be the date to be

considered as the date of the claim made. In the event of allowing the

application on later date, it has to be considered that the date of claim is on

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

the date of filing the application before the Tribunal and not the date of

passing the order. In the present case, admittedly, the additional claims

were filed by way of amendment application on 25.08.2018 by the petitioner

and though the Tribunal has ordered the application on 31.10.2018, the

claims have to be given effect to from the date of filing, i.e. on 25.08.20218

only. Therefore, this Court is of the view that the additional claims made by

the claimant/petitioner are well within the time and the Tribunal has

committed patent illegality in rejecting these claims as barred by limitation.

Further, the judgment in “State of Goa versus Praveen Enterprises”

reported in (2012) 12 SCC 581 was wrongly interpreted by the Tribunal that

the date of amendment by which the claim was introduced will become the

relevant date for determining the limitation and as such, the Tribunal has

taken into consideration the date of passing the order allowing the

amendment application, i.e. 13.10.2018 as the date of additional claims

taken on file and thereby, erroneously rejected the additional claims as

barred by limitation and hence, this Court is of the view that the same is

liable to be set aside. It is also pertinent to note that even while rejecting

the counter claim, the Tribunal has come to the conclusion that there was a

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

breach of contract occurred. When such being the case, this Court is of the

view that the Tribunal has committed patent illegality and therefore, the

entire award is liable to be set aside.

29. As regards the counter claim is concerned, it pertains to a sum of

Rs.4,45,21,291/- made by the respondent towards balance price for the

supply of equipment as per the contract and the Tribunal arrived at the

conclusion that there was a breach occurred at the instance of the

respondent and therefore, rejected the counter claim. However, the Tribunal

has not taken into consideration the various documents and evidence placed

on record by the respondent to establish that the petitioner has terminated

the contract prematurely contrary to the terms of the contract. Therefore, on

this ground, the award of the Tribunal as regards the rejection of counter

claim, is liable to be set aside.

30. In the light of the above discussion, both the petitions filed by the

petitioner as well by the respondent are allowed and the entire award passed

by the learned Arbitral Tribunal, dated 05.04.2022 is set aside.

https://www.mhc.tn.gov.in/judis Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

31. Accordingly, both the Arbitration Original Petitions filed by the

parties are allowed. No costs.

32. However, it is made clear that since the entire award is set aside

by this Court, for the purpose of any future course of action proposed to be

initiated (if any) by the respective parties, by virtue of Section 43(4) of the

Arbitration and Conciliation Act, 1996, the period, i.e. from the date of

commencement of arbitral proceedings till the date of this order, shall be

excluded in computing the time prescribed by the Limitation Act, 1963.

                     suk                                                                       30.10.2024
                     Index: Yes/No
                     Internet: Yes/No







https://www.mhc.tn.gov.in/judis
                                     Arb.O.P.(Com.Div.) Nos.534 and 634 of 2022

                                        KRISHNAN RAMASAMY, J.

                                                                          suk




                                         Pre delivery Common Order in
                                          Arb.O.P (Com.Div.) Nos.534
                                                   and 634 of 2022




                                                                 30.10.2024







https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter