Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The State Of Tamil Nadu vs M/S.Rao Constructions
2023 Latest Caselaw 1266 Mad

Citation : 2023 Latest Caselaw 1266 Mad
Judgement Date : 1 February, 2023

Madras High Court
The State Of Tamil Nadu vs M/S.Rao Constructions on 1 February, 2023
                                                                      C.M.A(MD)Nos.824 to 829 of 2002

                             BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT

                                              DATED : 01.02.2023

                                                    CORAM:

                                  THE HONOURABLE DR.JUSTICE G.JAYACHANDRAN
                                                      AND
                                     THE HON'BLE MR JUSTICE SUNDER MOHAN

                                        C.M.A(MD)Nos.824 to 829 of 2002

                 C.M.A(MD)No.824 of 2002

                 The State of Tamil Nadu,
                 represented by
                 The Superintending Engineer(WRO),
                 Periyar Vaigai Basin Circle,
                 Public Works Department,
                 Madurai -1.                                ... Second Respondent/Appellant

                                                     .Vs.

                 1.M/s.Rao Constructions,
                   represented by Managing Director,
                   Thiru.C.P.Rao,
                   Office at M.P.2/2,
                   P.T.A.Buildings,
                   Pannarahatta Road,
                   Bangalore – 560 076.                     ...Ist Respondent/Respondent

                 2.K.Thirunavukkarasu                ... Petitioner/Arbitrator/Respondent


                 PRAYER in C.M.A(MD)No.824 of 2002: Civil Miscellaneous Appeal filed
                 under Section 39 of the Arbitration Act against the parent and           decretal
                 order made in Arbitration O.P.No.36 of 1997, dated 30.4.2001, on the file
                 of the Principal Subordinate Judge, Madurai.

                 1/10

https://www.mhc.tn.gov.in/judis
                                                                         C.M.A(MD)Nos.824 to 829 of 2002

                 C.M.A(MD)Nos.824 to 829 of 2002


                                   For Appellant        : Mr.R.Baskaran
                                                          Addl.Advocate General
                                                          assisted by
                                                          Mr.C.Baskaran,
                                                          Government Advocate

                                   For Respondent-1      :Mr.Anand Chandrasekar
                                                          for M/s.Sarvabhauman Associates

                                   For Respondent-2      :Arbitrator
                                                          (No appearance)


                                               COMMON JUDGMENT

                 DR.G.JAYACHANDRAN,J.

AND SUNDER MOHAN,J.

Against the award passed by the Arbitrator under the Arbitration Act,

1940 and confirmed by the Sub-Court, Madurai, the State, represented by

the Superintending Engineer(WRO), Periyar-Vaigai Basin Circle, Public Works

Department, Madurai-1, has preferred these batch of Civil Miscellaneous

Appeals.

2.A perusal of the records indicate that against the Arbitration award,

dated 14.07.1997, the State had preferred three Arbitration OPs' to set

https://www.mhc.tn.gov.in/judis C.M.A(MD)Nos.824 to 829 of 2002

aside the award,whereas, the claimant has filed three Arbitration O.Ps' to

confirm the award. The said six Arbitration O.P.Nos.35,36,37, 47,48 and 49

of 1997 were taken up together for consideration by the Subordinate Court,

Madurai and passed a common order confirming the award and dismissing

the Petition filed to set aside the award. Aggrieved by the

same,C.M.A(MD)Nos.824 to 829 of 2002 are filed and these appeals

pending for the past two decades, for final disposal.

3.Though several adjournments were granted for the appellant to

argue the matter, under some pretext or other, they have successfully got

adjournemnts. From the records, it is seen that on 11.02.2014, for the non-

appearance of the appellant, the Division Bench of this Court, had dismissed

all these Civil Miscellaneous Appeals, but later, it was restored to file, in

order to give an opportunity to the appellant to purforth the case. The said

restoration order is dated 12.7.2016.It was an unconditional order of

restoration with the fond hope that the appellant will be ready to argue the

appeals within a reasonable time. Unfortunately, that never happened

which again prompted this Court to impose cost of Rs.30,000/-(Rs.5000/-

for six cases), when adjournment was sought. This order was passed on

23.11.2016.Thereafter, the appellant is not ready and nearly 15

https://www.mhc.tn.gov.in/judis C.M.A(MD)Nos.824 to 829 of 2002

adjournments have been granted in all these years.

4.On change of roster, this Bench took up the matter on 16.12.2022

and at the request of the appellant, the appeals were again adjourned to

20.1.2023 and then to 27.01.2023 and finally to 01.02.2023.

5.Today, when the matter is taken up for hearing, the learned

Additional Advocate General appearing for the appellant submitted that the

first respondent is a construction company which entered into a construction

agreement with the State/Public Works Department for laying down link

canal/parallel canal from Vaigai to Anaikudi in connection with Periyar Vaigai

Irrigation Scheme. Dispute arose regarding settlement of contract

amount and the matter was referred to the Arbitrator.The Arbitrator, after

considering the claim, passed an award on 31.3.1993 in respect of three

contracts relating to link Canal Km 4 to 8, Link Canal Km 8 to 11 and Link

Canal 18 to 22 and a sum of Rs.68,08,820/-, Rs.77,62,516/- and Rs.

52,88,352/- respectively in respect of three claims werre awarded with

interest. Aggrieved by the same, appeals were filed before the High Court

and the matter was remanded back for reconsideration by the Arbitrator.

The appeals in A.A.O.Nos.1230 to 1232 came to be disposed of with a

https://www.mhc.tn.gov.in/judis C.M.A(MD)Nos.824 to 829 of 2002

direction on 9.4.1996. Thereafter, the Arbitrator considered the matter

afresh and passed fresh award on 14.7.1997 in all the three claims for a

sum of Rs.65,16,471/- in total with interest at the rate of 15% p.a.The said

award was confirmed by the Sub-Court, Madurai and at the same time, the

applications filed by the Public Works Department for setting aside the

award was dismissed. In the said circumstances, aggreived by the order if

the Sub-Court in the batch of Arbitration O.Ps referred to above, the present

Civil Miscellaneous Appeals are filed.

6.In the appeals, it is contended that price adjustments as laid in

clause 54 of the Contract will not compensate the escalation of costs, when

the contract itself is a self contained one and provides for all contingency.

Further, it is submitted that the Arbitraror has misconducted himself while

passing the award. Also submitted that the entire award amount with

interest been already deposited and withdrawn by the claimant later by

way of an interim order, the claimant was directed to repay the difference

amount of Rs.41,28,471 and the same was repaid by the claimant after

nearly two years.

7.As far as the allegation of misconduct against the arbitrator is

https://www.mhc.tn.gov.in/judis C.M.A(MD)Nos.824 to 829 of 2002

concerned, this Court finds no material evidence at all. Regarding the

application of Clause 54 of the Contract, it reads as below:

''54(1)Price Adjustment:- The amounts paid to the Contractor for the work done shall be adjusted for increase or decrease in the rates of labour or materials excepting those materials supplied by the Government as per the schedule.

54(2)Price adjustment clause shall be applicable only for the work that is carried out in the stipulated time and extended thereof due to the reason as are not attributable to the Contractors.''

8.We find that after remand, the Arbitrator has gone into the reason

for fixing differental cost by applying the price adjustment as contemplated

under Clause 54 of the Contract. From the materials placed before this

Court, it is seen that the contract was completed within the time extended

for completion and on the part of the Contractor, there was no fault. While

Clause 54 provides for adjustment of money for increase or decrease in the

labour or materials, except those materials supplied by the Government.

As per the schedule, specific formula has been provided for such increase

https://www.mhc.tn.gov.in/judis C.M.A(MD)Nos.824 to 829 of 2002

or decrease in the award. This Court finds that the said formula has been

adopted by the Arbitrator to arrive at the conclusion.The reasonableness of

the reasoning given by the Arbitrator cannot be questioned by the Court, in

an appeal under this Act and therefore decline to entertain these appeals.

It is also pertinent to note that reduced award amount after remand by this

Court has not been challenged by the Contractor and has accepted the

award. Hence this Court finds no reason to interfere with the award which is

impugned in these batch of appeals.

9.The learned Additional Advocate General appearing for the appellant

would submit that for the difference in the award amount which was repaid

by the first respondent/Contractor, after nearly 2 ½ years of enjoyment, it

should bear some interest to the State. Since along with the award,

interest was also paid to the Contractor, the same has to be reciprocated

when the award was modified and reduced. The learned Additional Advocate

General would further submit that pursuant to the first award, which was

later remanded, the award of Rs.1,06,44,942/- was withdrawn by the

claimant on 17.02.1995.Thereafter, pursuant to the modified award, dated

14.7.1997, followed by the interim order passed by this Court to return the

difference amount, the Contractor has repaid the money to the Public Works

https://www.mhc.tn.gov.in/judis C.M.A(MD)Nos.824 to 829 of 2002

Department on 14.07.1997 san interest.

10.This Court finds some force in the submission and therefore, while

confirming the award, dated 14.07.1997, all these Civil Miscellaneous

Appeals are dismissed. The first respondent/Contractor is directed to pay

interest for a sum of Rs.41,28,471/- at the rate of 15% pa. for the period

between 17.02.1995 to 14.07.1997 and the same is directed to be paid

within a period of three months from the date of receipt of a copy of this

judgment. No Costs.



                                                                   [G.J.,J.]   [S.M.,J.]
                                                                         01.02.2023

                 Index            : Yes / No

                 Internet : Yes / No

                 NCC              :Yes/No

                 vsn

                 To

                 The Principal Subordinate Judge,
                 Madurai.






https://www.mhc.tn.gov.in/judis
                                                         C.M.A(MD)Nos.824 to 829 of 2002

                 Copy to

                 1.The Record Keeper,
                   Vernacular Section,
                   Madurai Bench of Madras High Court,
                   Madurai.






https://www.mhc.tn.gov.in/judis
                                        C.M.A(MD)Nos.824 to 829 of 2002

                                     DR.G.JAYACHANDRAN, J.
                                                      and
                                           SUNDER MOHAN,J.


                                                                  vsn




                                  COMMON JUDGMENT MADE IN

                                        C.M.A(MD)Nos.824 to
                                                829 of 2002




                                                      01.02.2023






https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter