Friday, 15, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Tarsun Steels India (P) Ltd vs The Chairman And Managing ...
2022 Latest Caselaw 16721 Mad

Citation : 2022 Latest Caselaw 16721 Mad
Judgement Date : 20 October, 2022

Madras High Court
M/S. Tarsun Steels India (P) Ltd vs The Chairman And Managing ... on 20 October, 2022
                                                                                     W.P.No.21686 of 2016

                                     IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                         Dated :   20.10.2022

                                                             CORAM

                                       THE HON'BLE MR.JUSTICE N.SATHISH KUMAR

                                              W.P.No.21686 of 2016 &
                                             W.M.P.No.18535 of 2016
                     M/s. Tarsun Steels India (P) Ltd.,
                     H.T.Sc.No.361, Palladam,
                     S.F.156/1B, Trichy Road,
                     Madhapur Village, Palladam,
                     Tiruppur – 641 664
                     rep. By its Managing Director,
                     S.Thangarajan                                                  ...Petitioner
                                                        Vs.

                     1. The Chairman and Managing Director,
                        Tamilnadu Generation and Distribution
                          Corporation Limited,
                        144, Anna Salai, Chennai – 600 002

                     2. The Superintending Engineer,
                        Tirupur Electricity Distribution Circle,
                        TANGEDCO, Tirupur.
                     ...Respondents

                                  Writ Petition filed under Article 226 of the Constitution of India for

                     issuance of a Writ of Certiorari by calling for the records of the 2nd

                     respondent            in    Lr.No.SE/TEDC/TRP/DFC/AO/HT/F.MRTREV/HTSC

                     361/D1038/16 dated Nil and quash the same as illegal,                arbitrary and

                     untenable under Law and against the provisions of Tamilnadu Electricity

                     1/17


https://www.mhc.tn.gov.in/judis
                                                                                 W.P.No.21686 of 2016

                     Supply Code 2004.

                                         For Petitioner          : Mr.AR.L.Sundaresan
                                                                   Senior Counsel assisted by
                                                                   Mr.A.R.Karthick Lakshmanan for
                                                                   Mr.K.Seshadri
                                                                   Counsel for the petitioner

                                         For Respondents         : Mr.L.Jaivenkatesh


                                                           ORDER

The present Writ Petition has been filed challenging the demand

notice issued by the 2nd respondent for the payment of short levy

consumption charges of Rs.4,90,62,768.67.

2. It is the case of the Writ Petitioner that the 1st respondent

sanctioned H.T.Service Connection in H.T.Sc/No.361 for sanctioned

demand 3600 K.V.A., to run said industry. The petitioner - Industry

provided with electronic L&T meter, which records Load Survey data, billing

data and tamper data, therefore, there would be no chance of defect and

furthermore, the meter is tamper proof meter. The respondents would take

meter reading on 26th of every month, after verifying the correctness of the

reading.

https://www.mhc.tn.gov.in/judis W.P.No.21686 of 2016

3. While the matter stood thus, on 19.01.2015, the officials from the

respondents' office inspected the petitioner-industry and checked the

function of the main meter located inside the factory and checked the meter

fixed outside the premises on the public road and found no defect in the

meter. Inspite of the fact that there was no defect in the meters, the 2nd

respondent compared the readings with the meter located in the sub-station,

which is 6.5 kms away from the petitioner-industry and based on the

readings in the meter located in sub-station, the bills for the period from

26.09.2013 to 19.01.2015 have been revised and claimed the said huge

amount, as short levy. It is the further contention that the 2nd respondent

has not given any opportunity to explain the petitioner's position before

issuing the impugned demand.

4. As there was power cut till 05.06.2015, the consumption was low

in the petitioner's industry. Based on the low consumption, the bills have

been revised under the impugned order. The 2nd respondent, revised the

bill, as if the meters were not recording the reading properly. If the meters

become defective, the authorities should have removed and sent the same

https://www.mhc.tn.gov.in/judis W.P.No.21686 of 2016

for testing by the acredited testing laboratory. No procedure were followed,

as contemplated under Supply Code, 2004, therefore, a Writ Petition has

been filed in W.P.No.26819 of 2015, whereas this Court, on the date of

admission, on 28.08.2015, was pleased to direct the petitioner to submit his

reply to the impugned demand notice treating it as show cause notice and

directed the 2nd respondent to pass orders within a period of two weeks

thereafter. Even after reply, the 2nd respondent without examining any

officers, direted the petitioner to furnish certain documents. Again on

28.01.2016, the 2nd respondent directed the petitioner to attend the enquiry

on 11.02.2016 and after attending the enquiry, the 2nd respondent has

issued impugned demand notice dated Nil (but it was signed on

04.06.2016) after a lapse of 9 months. Hence the same is challenged in the

present Writ Petition on the ground that none of the procedures

contemplated in the provisions available in the Supply Code is followed

before levying the amount, as short levy, without testing the meters.

5. In the counter, it is the contention of the respondents that the

petitioner purchased both main and check meters, due to non availability of

the meters at TANGEDCO. The same electronic L&T meters are provided

https://www.mhc.tn.gov.in/judis W.P.No.21686 of 2016

to the petitioner-industry, HT SC No.361. The L&T electronic TOD meters

are capable to record load survey data, billing data, tamper data, daily

energy and power off time (No supply). The energy quota fixed to the

petitioner was 13,50,000 unit per month and quota demand was 2592 KVA.

For the restriction and control period of October 2013 to May 2014 and

October 2014 to May 2015, the petitioner had not followed the power cut

instruction and violated the conditions of supply during the power cut period

for ten times and penalties were paid by the petitioner.

6. Further, it is the contention in the counter that on 19.01.2015,

during inspection, special tests were carried out in the existing main

metering and check metering arrangement, it was found that the energy

recorded in the main HT TOD meter (L&T Sl.No.13190786) and check HT

TOD Meter (L&T Sl.No.13190278) were 38.88% lower than the substation

meter installed for Alagumalai feeder, which feeds supply to this HT service

only. The CMRI data of main and check meters were analyzed from the date

of effecting service by MRT along with the representative of L&T meter

manufacturing company. It is found that there are data shifts from

September 2013 and also as it shows multiple power failures occurred in

https://www.mhc.tn.gov.in/judis W.P.No.21686 of 2016

the main and check meter, even though supply was continuously available

in the 33 KV Alagumalai feeder.

7. According to the respondents, in view of the above, the meter did

not record actual energy. The meter recorded 61.12% of energy only.

Petitioner's bills were revised for remaining 38.88% unrecorded energy of

83.227 Lakh units for the period from 01.09.2013 to 19.01.2015 for an

amount of Rs.4,90,62,769/- (Rupees Four Core Ninety Lakh Sixty Two

Thousand Seven Hundren and Sixty Nine Only).

8. Also, it is the contention of the respondents in the counter that the

revision of bills to the petitioner are based on the average consumption

from July 2015 to October 2015, as per Regulation 11 of Supply code, the

petitioner has not followed the Restriction and Control conditions and

exceeded the permitted demand and during the restriction and control

periods for ten times. The production statement given by the petitioner was

compared with the consumed energy on the day from CMRI downloaded

data from 01.09.2013 to 19.01.2015, hence opposed the Writ Petition.

https://www.mhc.tn.gov.in/judis W.P.No.21686 of 2016

9. The learned Senior Counsel for the petitioner would submit that the

petitioner provided with a main meter inside the premises and check meter

outside the premises. The officials of the respondents inspected on

19.01.2015, thereafter, demand notice was issued claiming huge amount

holding that during the inspection, it was found that energy recorded in the

main HT TOD meter (L&T Sl.No.13190786) and check HD TOD meter

(L&T Sl.No.13190278) were 38.88% lower than the substation meter

installed for Alagumalai feeder, which feeds supply HT Service only and

levied a sum of Rs.4,65,47,061/-.

10. It is the contention of the learned Senior Counsel for the petitioner

that there is a difference of percentage between the meters fixed in the

petition premises and the meter fixed in the sub-station of the respondents,

accordingly, the impugned order has been passed by levying such huge

amount. It is his contention that Installation of Meter is explained in

Regulation 7 of Tamilnadu Electricity Supply Code 2004. As per Regulation

7, the licensee shall ensure that such meter is of high quality, high precision

and accuracy and shall arrange to recalibrate the same at consumer cost.

https://www.mhc.tn.gov.in/judis W.P.No.21686 of 2016

11. Sub Regulation 9 of Regulation 7 states that if the consumer

considers that the meter is defective, the meter has to be tested by the

Third Party testing laboratory accredited by National Accreditation Board for

Testing and Calibration Laboratories (NABL). Till the Third Party Meter

Testing Arrangement is established, the licensee shall have the special test

conducted by the Chief Electrical Inspector to Government of Tamil Nadu.

12. The further contention of the learned Senior Counsel for the

petitioner is that Regulation 23 Chapter 4 of the Supply Code deals with

Tampering of Meters etc., According to him, in case of suspected theft of

tampering meter, such tampered meter shall be taken out and sealed at the

time of inspection, as prescribed in sub regulation (3), shall be sent to the

third party accredited meter testing laboratory, as arranged by the licensee

or supplier concerned, therefore, without following provisions to findout as

to whether there was any defective in the meters fixed in the petitioner-

Industry, the respondents merely on the basis of their inspection, came to

the conclusion that there was a difference in a reading recorded in the meter

fixed in the writ petitioner-Industry and sub station.

https://www.mhc.tn.gov.in/judis W.P.No.21686 of 2016

13. It is the further contention of the learned senior counsel for the

petitioner that it is admitted case of the respondents that at the time of

inspection, the meter fixed at the premises of the writ petitioner neither

found defective nor tampered, such being the case, merely because some

difference recording was shown in sub meter fixed at the sub station, which

is situated nearly 7 kms away, the respondents cannot term that the meter

reading recorded at the Industry of the writ petitioner is not correct. Hence it

is the contention of the learned senior counsel for the petitioner that the

entire demand raised in the impugned order is without any basis and not

following any procedure, as mandated in the Electricity Supply Code.

14. Whereas the learned counsel appearing for the respondents

would submit that on 19.01.2015 during inspection, they found that the

meter fixed at the writ petitioner-Industry is not according to the original

reading by comparing meter fixed at the sub-station. The levy has been

fixed from 01.09.2013 to 19.01.2015. The 2nd respondent revised the bills

from 01.09.2013 to 19.01.2015 based on the average consumption of

13,23,195 units per month for no restriction and control period including the

https://www.mhc.tn.gov.in/judis W.P.No.21686 of 2016

evening and night peak hours and 11,81,850 units per month for restriction

and control period excluding evening and night peak hours, therefore, it is

his contention that impugned order does not suffer from any irregularity,

hence pleaded to dismiss the present Writ Petition.

15. I have heard the contentions on either side and perused the entire

materials placed on record.

16. The impugned order has been passed by raising demand of

Rs.4,65,47,061/- mainly on the ground that main and check meters installed

at the writ petitioner-Industry found incorrect recording from 01.09.2013 to

19.01.2015, therefore, revised bills from 01.09.2013 to 19.01.2015, has

been passed based on the average consumption per month. The impugned

order itself would indicate that during the inspection, on 19.01.2015, the 2nd

respondent along with the Execution Engineer / Enforcement / Coimbatore

and Executive Engineer / O&M/ Palladam, has not noticed tampering or

defective in the meter, whereas, they have noticed only a change of energy

recorded in the main and check meters were 38.88% lower than the

substation meter installed for Alagumalai Feeder, which feeds supply to this

HT service only and it is not the case of the 2nd respondent that the meter

https://www.mhc.tn.gov.in/judis W.P.No.21686 of 2016

installed in the petitioner-Industry was found tampered or defective at the

time of inspection.

17. It is relevant to note that when the impugned order is passed

based on the allegation of incorrect recording of the meter, the proper

procedure to take a decision is to test the meter as per Law. The Sub

Regulation 3 of Regulation 7 of the Electricity Supply Code 2004 deals with

Installation of Meter where the consumer elects to purchase his own meter,

licensee shall ensure that such meter is of high quality, high precision and

accuracy and shall arrange to recalibrate the same at consumer cost.

18. Sub-Regulation 4 of Regulation 7 makes it mandatory that after

installation, the security seals shall be affixed in the presence of the

consumer or his representative on the meter box cover, current transformer

chamber, terminal cover of the meter, test block, cut outs, air-break switch

and gate and such other part of die (installation as the licensee may decide).

After such safety measures adopted by the licensee, then, it is the duty of

the consumer to see that the meter and the seals are not stolen, damaged

or tampered with. Only after then the consumer shall run his wiring from

such point of supply. Sub-Regulation 5 of Regulation 7 states that the

quantity of electricity recorded by such meter shall be taken as the quantity

https://www.mhc.tn.gov.in/judis W.P.No.21686 of 2016

actually supplied by the licensee.

19. It is not the case of the 2nd respondent that they have not taken

any safety measure while fixing the meter, at the initial stage, it is also not

their case that at time of inspection, on 19.01.2015, the meters were either

found defective or tampered. It is also relevant to note that if the consumer

considers that meter fixed is a defective or tampered, there is a special

mechanism under Sub-Regulation 9 of Regulation 7 in such a case,

licensee to have a special test carried out on the meter at any time and the

cost of such test shall be borne by the licensee or the consumer if the meter

is found defective or correct as a result of such a test. [The aforementioned

special test for the disputed energy meters including the

suspected/defective meters shall be carried out in the Third Party testing

laboratory accredited by National Accreditation Board for Testing and

Calibration Laboratories (NABL) and till such time the Third Party Meter

Testing Arrangement is established, the licensee shall have the special test

conducted by the Chief Electrical Inspector to Government of Tamil Nadu].

Therefore, the said Sub-Regulation 9 of Regulation 7 makes it clear that

whenever there is a complaint with regard to defective meters, proper test

https://www.mhc.tn.gov.in/judis W.P.No.21686 of 2016

has to be conducted by the licensee that too with the 3rd party testing

laboratory. Till such test is conducted by the 3rd party testing laboratory, the

licensee shall have the special test conducted by the Chief Electrical

Inspector to Government of Tamil Nadu.

20. Admittedly, in this case, it is not the case of the consumer that the

meters are defective, similarly, it is not the case of the respondents that they

have also found that the meters are incorrect or defective, but the impugned

order has been passed only on the ground that the meter fixed at the

premises of the petitioner are found recording incorrect energy, therefore

according to respondents, it is only the meter is over tampered and not

reflecting right energy supply, if such being the contention of the

respondents, on the date of inspection, on 19.01.2015, they ought to have

sealed meter, subjected the meter for analysis by the accredited laboratory.

21. Sub-Regulation 9 of Regulation 23 deals with the Tampered

Meters, in case of suspected theft through a tampered meter, such

tampered meter taken out and sealed at the time of inspection, as

prescribed in sub regulation (3), shall be sent to the third party accredited

https://www.mhc.tn.gov.in/judis W.P.No.21686 of 2016

meter testing laboratory as arranged by the licensee or supplier concerned

or to the Chief Electrical Inspector to the State Government till such time the

third party meter testing arrangement is established by the licensee or

supplier concerned, as the case may be. Only after testing in the

laboratory, where it is established that there is a case of any theft or

tampering, the procedure for assessment could be followed by the

respondents, as per Supply Code.

22. Though Regulation 23 made applicable to the Tampering,

Distress or Damage to the Electrical Plant, Meters etc., the same principle

is also applicable to the present case for the simple reason that levy has

been made only on the ground of defective recording in the meter, without

establishing defect found in the meter, merely on the basis of recording

shown in the meter of the licensee, namely, the 2nd respondent, which has

been fixed in their sub-station, which is admittedly at the distance of 6.5

kms from the petitioner-Industry, hence this Court is of the view that without

establishing the fact that the meter, in fact, is found defective or recording

incorrect details by subjecting meters to the laboratory, as contemplated in

the Regulations, the respondents cannot by mere inference on the basis of

their own recording sub-station, can come to the conclusion that there were

https://www.mhc.tn.gov.in/judis W.P.No.21686 of 2016

excess energy used by the petitioner.

23. It is also relevant to note that the distance between the sub-station

and the petitioner-Industry is 6.5 kms, as per the 2nd respondent. Therefore,

possibility of leakage or pilferage in the above distance is also cannot be

ruled out. Therefore, merely on the basis of their own recording in their sub-

station, the petitioner cannot be clothed with liability to pay huge amount on

the ground that the energy consumed is not been properly reflected in the

meter without establishing any tampering in their meter.

24. It is further to be noted that the meter has been installed only for

the purpose of calculating the energy used and supplied. While installing

the sub-station meter, the same should have been made in the presence of

consumer and the licensee have not installed the meter in the presence of

consumer and if at all the respondents intends to rely on recording of their

sub-station meter, the installation should have been made in the presence

of Writ Petitioner, which also not been done in this case.

25. In such view of the matter, the impugned order passed by revising

https://www.mhc.tn.gov.in/judis W.P.No.21686 of 2016

the bills based on their own calculations without examining the meter by

subjecting the same in a 3rd party test laboratory accredited by the National

Accreditation Board or by the Electricial Inspector of the Government of

Tamilnadu, revision made by the 2nd respondent cannot be sustained in the

eye of law. Further, it is also submitted on behalf of the petitioner that a

deposit is made pursuant to the earlier direction of this Court while admitting

the Writ Petition, if it is so, the same shall be adjusted in future bills.

Accordingly, the impugned order is setaside and the Writ Petition is

allowed. Consequently, connected miscellaneous petition is closed. No

costs.

20.10.2022

Index : Yes/No Internet : Yes/No Speaking /Non-Speaking Judgment ssd

N.SATHISH KUMAR, J.,

ssd

https://www.mhc.tn.gov.in/judis W.P.No.21686 of 2016

W.P.No.21686 of 2016 & W.M.P.No.18535 of 2016

20.10.2022

https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter