Wednesday, 06, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Project Director vs Jsr Constructions Pvt. Ltd
2021 Latest Caselaw 18319 Mad

Citation : 2021 Latest Caselaw 18319 Mad
Judgement Date : 7 September, 2021

Madras High Court
The Project Director vs Jsr Constructions Pvt. Ltd on 7 September, 2021
                                                                               O.S.A.No.212 of 2019



                                    IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                  DATED: 07.09.2021

                                                        CORAM :

                                   THE HON'BLE MR.SANJIB BANERJEE, CHIEF JUSTICE
                                                          AND
                                     THE HON'BLE MR.JUSTICE P.D.AUDIKESAVALU


                                                  O.S.A.No.212 of 2019

                     The Project Director
                     Tamil Nadu Road Sector Project
                     TNMB Complex-I Floor
                     171, South Kesavaperumalpuram
                     Off Greenways Road
                     R.A.Puram, Chennai – 600 028.                       ...   Appellant

                                                          Vs.

                     JSR Constructions Pvt. Ltd, Bangalore
                     rep. by Power of Attorney Holder
                     R.Paneerselvam
                     114-G1, Green House Apartments
                     Mc Donalds Road
                     Cantonment, Trichy – 620 001.                       ...   Respondent


                     Prayer: Appeal under Order XXXVI Rule 1 of the Original Side Rules
                     read with Clause 15 of the Letters Patent against the judgment dated
                     30.4.2019 passed by the learned Single Judge on O.P.No.228 of 2014.




                                    For the Appellant       : Mr.R.Shunmugasundaram

                     ____________
                     Page 1 of 11


https://www.mhc.tn.gov.in/judis/
                                                                             O.S.A.No.212 of 2019



                                                              Advocate-General
                                                              assisted by
                                                              Mr.P.Muthukumar
                                                              State Government Pleader

                                    For the Respondent      : Mr.D.Balaraman

                                                      JUDGMENT

(Delivered by the Hon'ble Chief Justice)

The appeal is directed against an order dated April 30, 2019

passed under Section 34 of the Arbitration and Conciliation Act, 1996,

rejecting the challenge to an arbitral award dated November 23, 2013.

2. The matter pertains to a project undertaken and completed in

or about the year 2008 for the construction of two segments of the

Ramanathapuram Bypass road adding up to slightly over 10 kilometre.

The respondent contractor initiated the arbitral reference upon

claiming, inter alia, the wrongful withholding of performance security,

money payable under the bills raised by the contractor, loss of profit

on account of delay and the like. The arbitral tribunal consisted of

three members. It is the majority view which was assailed as such

majority view found a substantial amount, in excess of Rs.9.44 crore

together with interest, to be due and owing from the appellant herein.

____________

https://www.mhc.tn.gov.in/judis/ O.S.A.No.212 of 2019

The original contract was valued at a little over Rs.35 crore.

3. The appellant questions the award made under two heads of

claim: the wrongful withholding of payment to the tune of

Rs.84,55,380/- and the loss assessed due to overhead and profit to

the extent of Rs.3,90,99,700/-. These two items are covered by the

first head of claim of award and the first item under the fifth head,

respectively.

4. It is recorded that no challenge has been thrown in the

present appeal in respect of the three other heads on which sums in

excess of Rs.4.62 crore, Rs.75,000/- and Rs.5.68 lakh were awarded

by the arbitral tribunal on account of release of performance security,

revised rate for box culvert and refund of recovered interest on

mobilisation advance, respectively.

5. It appears from the judgment and order impugned that a

rather general challenge was fashioned in the proceedings under

Section 34 of the Act and the court found that the matters had been

appropriately dealt with by the arbitral tribunal. The arbitration court

____________

https://www.mhc.tn.gov.in/judis/ O.S.A.No.212 of 2019

found that it was a techno commercial arbitration, since various

technical aspects went into the consideration of the matter, particularly

engineering and design defects complained of and the assessment

thereof.

6. As to the first head of claim pertaining to the withholding of

the sum in excess of Rs.84 lakh, the appellant says that it was on

account of the defective work on a section of the stretch pertaining to

a bridge. Certain cracks or other defects may have been noticed and it

is the appellant's case that despite the contractor being obliged to

remove the defect within a period of one year of it being pointed out,

as envisaged in the contract, no endeavour was made by the

contractor here to address the defect or attempt to rectify the same.

The appellant says that since the appellant had to take steps, inter

alia, by engaging another contractor to take care of the defective

workmanship of this contractor, considerable sums were expended and

there was no basis to the arbitral tribunal absolving the contractor of

the liability on such count.

7. The discussion on such aspect is found in paragraph 9.3 and

____________

https://www.mhc.tn.gov.in/judis/ O.S.A.No.212 of 2019

thereafter in the majority award. The substance of the dispute was

that the contractor claimed that it was an anomaly in the design of the

bridge that led to what the employer perceived to be a fault and the

contractor was required to make the construction in accordance with

the design supplied by the employer. The correspondence in such

regard have been noticed and re-produced in the award and it appears

that upon the disputes arising between the parties herein, expert

opinion was sought from the Indian Institute of Technology, Chennai.

The report of the IIT has been copiously referred to in the award and,

on the expert assessment of the specialised arbitral tribunal, it

appeared that the fault lay in the design and not in the workmanship.

Several pages have been expended in discussing the matter and the

arbitral tribunal found that the contractor was not liable for the

perceived defect.

8. In the face of such categorical finding rendered by the arbitral

tribunal on the basis of an expert opinion obtained from a recognised

institution as the IIT, there was little room for the arbitration court to

interfere with such aspect of the matter, particularly within the limited

ambit of authority available under Section 34 of the Act.

____________

https://www.mhc.tn.gov.in/judis/ O.S.A.No.212 of 2019

9. Accordingly, there does not appear to be any merit in the first

count of challenge pertaining to the award of a sum in excess of Rs.84

lakh for the wrongful withholding by the appellant herein of the bills

due and payable to the contractor in terms of the relevant contract.

10. Apropos the other ground of challenge pertaining to the first

item under the fifth head of the claim, on account of overhead and loss

of profit, the appellant draws the court's attention to when the papers

in support of such claim may have been filed before the arbitral

tribunal. The appellant refers to recording in the award as to the dates

of hearing and suggests that it was only after the hearing was

substantially completed that the primary evidence in support of such

head of claim was produced before the arbitral tribunal.

11. It is the appellant's underlying suggestion that pleadings and

evidence should precede the hearing and the hearing is taken up at a

stage after the cross-examination and if the material in support of the

claim was produced in course of the hearing, the appellant was

deprived the opportunity of cross-examining the representatives of the

____________

https://www.mhc.tn.gov.in/judis/ O.S.A.No.212 of 2019

contractor in respect of the evidence produced in such regard.

12. For a start, there does not appear to be any specific ground

taken in the petition under Section 34 of the Act complaining of any

lack of opportunity on the part of the appellant herein to cross-

examine any representative or witness called by the contractor.

Indeed, it does not appear, on a reading of the judgment and order

impugned, that an issue was raised as to the late filing of papers

pertaining to such head of claim. At any rate, the arbitral tribunal is

the master of the procedure and the award was rendered several

months after the evidence in respect of the impugned head of claim

was furnished. It does not appear that the appellant herein was

deprived from dealing with the evidence or making any submission in

such regard. At any rate, no minutes of any proceedings before the

arbitral tribunal has been produced to demonstrate that the cross-

examination was sought by the appellant and it was declined by the

tribunal, no letter of protest issued to the arbitral tribunal by the

appellant in course of the proceedings has also been disclosed in such

regard.

13. When it comes to the loss of profit or cost overrun due to the

____________

https://www.mhc.tn.gov.in/judis/ O.S.A.No.212 of 2019

delay in the completion of the work upon the employer being

responsible for the delay, there is no doubt that the assessment that is

made is not arithmetically accurate and there are certain guidelines to

go by. This was an engineering contract and the use of Hudson's

formula in engineering contracts is almost universal and is judicially

recognised in this country. Of the several judgments, including those

rendered by the Supreme Court and which recognise the applicability

of Hudson's formula in engineering contracts, two of the more

prominent may be referred to – (2015) 3 SCC 49 (Associate Builders

v. Delhi Development Authority) and (2006) 11 SCC 181 (McDermott

International Inc. v. Burn Standard Company Limited).

14. Further, authoritative pronouncements of the Supreme Court

instruct that when it comes to loss of profit, a rough and ready

estimate can be made. Approximation to the extent of 15% of the

contract price is permissible in terms of such judgments. In the

present case, upon applying Hudson's formula, about 18% of the value

of the original contract has been assessed to be the quantum of loss of

profit for the period of delay and the figure arrived at upon applying

Hudson's formula has been toned down in the majority view to about

____________

https://www.mhc.tn.gov.in/judis/ O.S.A.No.212 of 2019

Rs.3.91 crore.

15. Considering that the value of the contract was in excess of

Rs.35 crore, the quantum awarded on account of loss of profit by

applying the Hudson's formula does not shock the conscience of the

court or otherwise appear to be patently erroneous or manifestly

arbitrary. At any rate, the challenge on this head does not appear to

have been fashioned as being opposed to public policy since the law in

this country recognises the entitlement of a contractor to

compensation on account of loss of profit for the delay occasioned at

the behest of the employer.

16. In the impugned judgment and order, the arbitration court

refers to certain salutary principles which ought always to be

remembered in this jurisdiction. Apart from the arbitral tribunal being

the master of the procedure, the arbitral tribunal also has the final say

as to the quality and the quantum of evidence before it. In exercise of

the limited authority under Section 34 of the Act, the Court cannot re-

assess the evidence before the Arbitrator or supplant its view for that

expressed by the arbitrator, even if the other view appears more

____________

https://www.mhc.tn.gov.in/judis/ O.S.A.No.212 of 2019

plausible to the court.

17. There does not appear any infirmity in the judgment and

order impugned in it refusing to interfere with the arbitral award in this

case. The specific challenge launched by the appellant herein to the

two heads of claim do not meet the exalted tests required to be

discharged in this jurisdiction.

18. Accordingly, O.S.A.No.212 of 2019 fails and the same is

dismissed. C.M.P.No.19435 of 2019 is closed.

There will, however, be no order as to costs.

                                                                   (S.B., CJ.)          (P.D.A., J.)
                                                                                 07.09.2021
                     Index : No
                     bbr

                     To:

                     The Sub Assistant Registrar
                     Original Side
                     High Court, Madras.



                     ____________



https://www.mhc.tn.gov.in/judis/
                                              O.S.A.No.212 of 2019



                                     THE HON'BLE CHIEF JUSTICE
                                                  AND
                                          P.D.AUDIKESAVALU, J.

                                                              bbr




                                           O.S.A.No.212 of 2019




                                                     07.09.2021




                     ____________



https://www.mhc.tn.gov.in/judis/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter