Friday, 15, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

K.P.Munisamy vs The Chief Engineer (Highways)
2021 Latest Caselaw 14848 Mad

Citation : 2021 Latest Caselaw 14848 Mad
Judgement Date : 26 July, 2021

Madras High Court
K.P.Munisamy vs The Chief Engineer (Highways) on 26 July, 2021
                                                                           W.A.(MD)No.1428 of 2021

                        BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT

                                             DATED : 26.07.2021

                                                   CORAM

                               THE HONOURABLE MR.JUSTICE T.S.SIVAGNANAM
                                                AND
                                 THE HONOURABLE MRS.JUSTICE S.ANANTHI

                                          W.A.(MD)No.1428 of 2021


                K.P.Munisamy                                          ... Appellant/Petitioner

                                                         Vs.


                1. The Chief Engineer (Highways),
                   Project Highways,
                   3rd Floor, Highways Research Centre,
                   Guindy, Chennai - 600 025.

                2. The Divisional Engineer (Highways),
                   Project Highways,
                   Thamarai Thotti Junction,
                   Alagar Kovil Road, Madurai.

                3. The Superintending Engineer (Highways),
                   Project Highways,
                   Thamarai Thotti Junction,
                   Alagar Kovil Road, Madurai.

                4. The Assistant Engineer (Highways),
                   Project Section, Dindigul District.                      ... Respondents/
                                                                                Respondents
                Prayer: Writ Appeal filed under Clause 15 of Letters Patent, against the order of
                this Court made in W.P.(MD) No.20251 of 2018, dated 02.02.2021.

https://www.mhc.tn.gov.in/judis/
                1/6
                                                                                    W.A.(MD)No.1428 of 2021

                                   For Appellant                : Mr.J.Lawrence

                                   For Respondents              : Mr.R.Baskaran,
                                                                  Standing Counsel for Government


                                                       JUDGMENT

[Judgment of the Court was delivered by T.S.SIVAGNANAM,J.]

We have heard Mr.J.Lawrence, learned counsel appearing for the

appellant and Mr.r.Baskaran, learned Government Counsel appearing for the

respondents.

2. This appeal is directed against the order dated 0202.2021 passed in

W.P(MD).No.20251 of 2018.

3. The said writ petition was filed by the appellant to direct the

respondents 2 and 3 to disburse a sum of Rs.6,31,582/- along with 20%

additional cash bill for the construction work performed by him by considering

his representation dated 07.09.2018.

4. The learned Single Bench dismissed the writ petition on the ground

that the matter is purely a contractual dispute and if the appellant has raised any

https://www.mhc.tn.gov.in/judis/

W.A.(MD)No.1428 of 2021

additional claim, then in terms of the Commercial Condition No.10 of the

agreement, he has to approach the competent civil Court.

5. In our considered view, the learned Single Bench was right in

observing that in such contractual matters, the Court should be very slow in

interfering, by exercising its jurisdiction under Article 226 of the Constitution

of India.

6. Mr.J.Lawrence, learned counsel appearing for the appellant would

contend that the respondents being the Governmental Authorities, though the

work assigned to the appellant is in a contractual field, yet they are bound to act

reasonably and fairly. There can be no quarrel on the aspect that the action of

the Government should be fair and reasonable. However, when the dispute

between the parties is in the private law field and not in the public law field,

then the Courts under Article 226 of the Constitution of India should seldom

interfere in such matters, more particularly, when the claims are disputed.

7. The grievance of the appellant is that though a communication was

sent by the appellant on 27.05.2016, by the Divisional Engineer to call for a

meeting with the appellant, so that the issue can be sorted out, thereafter, the

https://www.mhc.tn.gov.in/judis/

W.A.(MD)No.1428 of 2021

respondents have not even considered the appellant's representation dated

07.09.2018 and the request of the appellant is to examine his representation and

if the amount claimed by the appellant is not disputed, then the payment can be

released. In the counter-affidavit filed in the writ petition by the Divisional

Engineer, it is stated that a sum of Rs.32,62,597/- has been paid to the appellant

for the work which has been done after due verification by the Assistant

Engineer of the Department. The remaining amount has been stopped for not

complying with the agreement conditions and once the appellant ensures that

the specification and standards of work are completed in terms of the

agreement, the remaining amount would be released.

8. Further, it is stated that the additional claim to the tune of 20% is

the disputed issue and as per the Commercial Conditions No.10 in the

agreement, the appellant has to approach the civil Court, since the respondents

have stated that if the appellant ensures that the work has been completed as per

the specification and standards of work, the balance amount shall be released.

9. If such is the case, one opportunity can be granted to the appellant

to demonstrate that he has completed the works as per the specification and

standards and if the Department is satisfied, then the balance amount can be

https://www.mhc.tn.gov.in/judis/

W.A.(MD)No.1428 of 2021

released. If not, the Department can give a written reply to the appellant stating

as to why the amount cannot be released. So far as the additional claim of 20%

is concerned, the appellant has to necessarily approach the civil Court.

10. Therefore, we are inclined to grant a partial relief to the appellant

by directing the respondents to consider the petitioner's representation dated

07.09.2018, call upon the appellant to establish that he has complied with the

terms and conditions of the said agreement as per the specification and

standards and if the Department is satisfied, the balance amount can be released

or otherwise, the Department can intimate the appellant as to why the amount

cannot be released, therefore, it will enable the appellant to approach the civil

Court even for the said amount. As mentioned earlier, so far as the additional

claim of 20% is concerned, the appellant is at liberty to approach the civil Court

of competent jurisdiction.

11. With the above observations and directions, this Writ Petition

stands disposed of. No costs.

                Index    :Yes/No                                         (T.S.S.,J.)       (S.A.I.,J.)
                Internet :Yes/No                                                    26.07.2021
                pkn


https://www.mhc.tn.gov.in/judis/

                                                                              W.A.(MD)No.1428 of 2021



                                                                          T.S.SIVAGNANAM, J.
                                                                                         and
                                                                                 S.ANANTHI, J.

                                                                                                pkn

Note: In view of the present lock down owing to COVID-19 pandemic, a web copy of the order may be utilized for official purposes, but, ensuring that the copy of the order that is presented is the correct copy, shall be the responsibility of the advocate/litigant concerned. To:

1. The Chief Engineer (Highways), Project Highways, 3rd Floor, Highways Research Centre, Guindy, Chennai - 600 025.

2. The Divisional Engineer (Highways), Project Highways, Thamarai Thotti Junction, Alagar Kovil Road, Madurai.

3. The Superintending Engineer (Highways), Project Highways, Thamarai Thotti Junction, Alagar Kovil Road, Madurai.

4. The Assistant Engineer (Highways), Project Section, Dindigul District.

W.A.(MD)No.1428 of 2021

26.07.2021

https://www.mhc.tn.gov.in/judis/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter