Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Ranjit Buildcon Limited vs Rail Vikas Nigam Limited
2021 Latest Caselaw 405 Mad

Citation : 2021 Latest Caselaw 405 Mad
Judgement Date : 6 January, 2021

Madras High Court
Ranjit Buildcon Limited vs Rail Vikas Nigam Limited on 6 January, 2021
                                                                       W.P.No.17888 of 2020

                                   IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                 DATED: 06.01.2021

                                                      CORAM

                            THE HONOURABLE Mrs. JUSTICE PUSHPA SATHYANARAYANA

                                               W.P.No.17888 of 2020
                                                       and
                                         W.M.P. Nos.22172 & 24091 of 2020

                     Ranjit Buildcon Limited
                     Represented by its Authorised Signatory
                     Mr.Maheshkumar Narottamdas Patel
                     'Ranjit House'
                     Opp. Sun Residency
                     B/h.Bhagwat Bungalows
                     Rt. Side Road to Gora Maharaj Madir
                     Thatlej-Shilaj Road
                     Tatlej, Ahmedabad - 380059                             .. Petitioner

                                                        Vs.

                     Rail Vikas Nigam Limited
                     Represented by its Chief Project Manager
                     Thirumailai Railway Station Building
                     Mylapore, Chennai - 600 004                            .. Respondent


                     PRAYER : Writ Petition filed Under Article 226 of the Constitution of
                     India praying to issue a Writ of Mandamus, forbearing the
                     respondent from awarding the de-scoped portion of work of the
                     petitioner to any third party without following due process of law in
                     awarding the works by issue of a public open tender in a
                     transparent manner.
                                     For Petitioner     : Mr.Vijaynarayan, Sr.Counsel
                                                          for Mr.K.Harishankar
                                     For Respondent     : Mr.R.Sankaranarayanan
                                                          Additional Solicitor General
                                                          of India
                                                          Assisted by Mr.V.G.Suresh Kumar
https://www.mhc.tn.gov.in/judis/
                                                      Page 1/21
                                                                         W.P.No.17888 of 2020

                                                        ORDER

The petitioner has sought for a Writ of Mandamus, forbearing

the respondent from awarding the de-scoped portion of work of the

petitioner to any third party, without following due process of law in

awarding the works by issue of a public open tender in a

transparent manner.

2. The petitioner is the contractor, who was awarded with the

contract of construction of Pamban Bridge, parallel to the existing

bridge No.346 at Km.655/000 - 657/200, including vertical lift span

between Mandapam and Pamban Railway stations in Madurai

Division of Southern Railway.

3. The Letter of Acceptance was given on 02.08.2019. Now,

the challenge is to the unilaterally de-scoped part of the works as

per the Letter of Acceptance. The petitioner is a contractor, who is

specialised in construction of Rail Over Bridges/Bridges/Fly-overs

and road works including water supply projects.

4. The respondent had issued a Notice Inviting Tender on

02.01.2019 for the re-construction of the famous Pamban Bridge,

which was originally built in the year 1914. The present bridge is a

https://www.mhc.tn.gov.in/judis/ Page 2/21 W.P.No.17888 of 2020

parallel one to the existing bridge. The earlier tender was in two

folds, namely technical and financial and the petitioner bagged the

contract work involving construction of 3.36 Km long railway bridge

over Pamban river that has the Bay of Bengal on one side. On

receipt of the Letter of Acceptance, a bank guarantee towards

Performance Security was furnished and a contract agreement was

executed on 06.03.2020. The petitioner blames the respondent for

certain deficiencies from the beginning. It is alleged that the

respondent did not provide the critical details for carrying out the

works or had provided details misguiding the petitioner. In addition

to the above allegation, the petitioner also had blamed the

respondent for:

(i) Failing to clarify the date of commencement;

(ii) The petitioner was required to take up the work from both

the approach ends of the project i.e. from Mandapam end and the

Pamban end, as per the contract provisions;

(iii) The petitioner proceeded with the work only from

Mandapam end for which the respondent declined to provide facility

to cross the railway track;

(iv) The petitioner had to wait for removal of hindrance and

encroachment for enabling movement of heavy and massive

mechanical equipments to reach the actual work site;

https://www.mhc.tn.gov.in/judis/ Page 3/21 W.P.No.17888 of 2020

(v) The geo-technical details furnished by the respondent did

not match as shown in the tender documents. The respondent was

also not ready with the design and drawing for the retaining wall at

the Mandapam end.

(vi) The start and end points were unavailable;

(vii) The information regarding the depth of the sea is false

and vague and the petitioner had to commence piling works despite

there being various deviations, mismatch etc. The depth of the pile

was actually different from what was indicated in the work drawing,

as the pile has to rest on the rock, the petitioner had to conduct SPT

test for the same pile at various depths to decide upon the pile

termination. The date of commencement was also not clear and it

was contrary to the bid provisions.

5. It is further stated by the petitioner that several details,

such as change in the location, access to site, change in

geography/depth of the sea water available etc. were at variance

from what was given at the time of tender and that there was a

delay in furnishing the same. In addition to the above, the nation-

wide lock-down due to COVID-19, brought the work to a standstill.

The petitioner had been informing the respondent about the

difficulties faced by it, by various letters. Despite pointing out the

https://www.mhc.tn.gov.in/judis/ Page 4/21 W.P.No.17888 of 2020

above difficulties and the unforeseen circumstances like COVID-19

Pandemic situation, the respondent had issued a Notice to Correct

on 08.10.2020. A reply was sent by the petitioner on 19.10.2020

reiterating the issues faced due to the respondent's lack of clarity

and inertness in the tender.

6. While so, on 30.10.2020, the respondent had issued a

Notice of Part Termination of the contract thereby unilaterally de-

scoped the part of the works awarded as per the Letter of

Acceptance dated 02.08.2019. Not stopping with that, the

respondent is attempting to award the de-scoped works, to satisfy

the third parties by having private negotiations with them.

According to the petitioner, all those deficiencies that were pointed

out by the petitioner with regard to the technical details, have now

been rectified making the job easier for the third party. The

petitioner still is willing to continue with the contract and expressed

hope to finish the same before August 2021, the deadline given as

per the contract.

7. It is also pointed out that the de-scoped work, as per

petitioner's contract was only around Rs.60.00 Crores, whereas now

the same has been estimated around Rs.135.00 Crores, which is

https://www.mhc.tn.gov.in/judis/ Page 5/21 W.P.No.17888 of 2020

more than the double the value of the work. Such high value of the

work should be awarded only by public open tender and not by

private negotiations. Therefore, the petitioner is seeking a

mandamus forbearing the respondent from awarding the de-scoped

work of the petitioner, to any third party, without following the due

process.

8. The respondent, namely Rail Vikas Nigam Limited, raised

certain preliminary objections on the maintainability of the writ

petition itself. The respondent is a Special Purpose Vehicle that

undertakes project development for creating rail transport capacity

on behalf of Ministry of Railways, Government of India. It is stated

that the work was proposed on a out of turn basis considering the

condition of the existing bridge, which has outlived its life. The

proposed bridge also has to serve the nation for at least 100 years.

9. The work was entrusted to the petitioner under the Letter

of Acceptance being the lowest among the five bidders, who

participated. The period of completion of the work was 24 months

i.e. the work has to be completed on or before 01.08.2021.

However, no work was started for more than seven months i.e. up

to March 2020 and whatever the mutual arrangements that were

https://www.mhc.tn.gov.in/judis/ Page 6/21 W.P.No.17888 of 2020

made also came to a grinding halt, after the spread of COVID-19

Pandemic followed by nation-wide lock down. Even after the State

Government had relaxed the safety protocol, the petitioner did not

show any urgency in completing the task entrusted to them. Even

after the expiry of 14 months, the progress of the work entrusted to

the petitioner was far from satisfactory. Hence it was decided to

terminate the part of the subject contract work from the scope of

the petitioner and allow the petitioner to continue with the other

works. Accordingly, a "Notice to Correct" was issued on 30.10.2020.

10. As per clause 15.2 of the general conditions of the

contract, the employer's election to terminate the contract, shall not

prejudice any other rights of the employer, under the contract or

otherwise. In accordance with the same, the respondent is taking

necessary steps to engage another agency to complete the work to

prevent the work from the scope of the petitioner. As the petitioner

had already taken substantial time without any progress, the

respondent had to take steps in finalising a new agency for

executing the de-scoped work from the petitioner.

11. As the completion of the project is utmost important for

running trains to Rameswaram, the bids were finalised after

https://www.mhc.tn.gov.in/judis/ Page 7/21 W.P.No.17888 of 2020

following the due process, as stipulated, for calling and acceptance

of Special Limited Tender (SLT). Besides, when it is a alleged breach

of contract, according to the petitioner, its remedy is elsewhere and

not before this court invoking Article 226 of the Constitution of

India. As the writ petition itself is not maintainable, the respondent

has sought for dismissal of the same.

12. Heard Mr.Vijayanarayan, learned senior counsel appearing

for Mr.K.Harishankar and Mr.R.Sankaranarayanan, learned

Additional Solicitor General of India, assisted by Mr.V.G.Suresh

Kumar. The materials available in the form of typed set, were also

perused.

13. The scope of the writ petition is very limited, as the

petitioner is only seeking a mandamus forbearing the respondent

from awarding the de-scoped part of the work of the petitioner to

any other third party. The undisputed facts are as follows:

14. Notice inviting Tender was on 02.01.2019. The letter of

acceptance was given to the petitioner on 02.08.2019. The contract

period was 24 months from the date of commencement of work as

per clause 8.1 and the defect liability period is 180 days from the

https://www.mhc.tn.gov.in/judis/ Page 8/21 W.P.No.17888 of 2020

date of taking over of the whole work. The value of the agreement

is Rs.220,97,51,604/- and the due date of completion is 01.08.2021

plus 180 days of defect liability period. It is an admitted fact that

the work was delayed. Hence the respondent had issued Notice to

Correct on 08.10.2020. Thereafter, within 20 days, Notice of part

termination of the contract, was issued on 30.10.2020, wherein de-

scoping part of the works awarded as per Letter of Acceptance

dated 02.08.2019, was issued. Now the termination of the part of

the contract done by the respondent is based on various grounds.

15. It is not out of place to mention that the said termination

notice dated 30.10.2020 is not challenged by the petitioner. The

petitioner is only seeking a mandamus not to award the de-scoped

work to any other third party. Clause 15.2 of the general conditions

of the contract provides for termination of the employer. The said

condition specifically empowers the employer to terminate the

contract with immediate effect and the employer's election to

prevent the contract shall not prejudice any other rights of the

employer under the contract or otherwise. It further provides that,

after termination, the employer may complete the works and/or

arrange for any other entities to do so. The employer and these

entities may then use any Goods Contractor's documents and other

https://www.mhc.tn.gov.in/judis/ Page 9/21 W.P.No.17888 of 2020

design documents made by or on behalf of the contractor for

completing the work.

16. The existing bridge is more than 100 years old and there

was a dire urgency in completing the new Pile bridge parallel to the

existing bridge and the same was to be raised in a time bound

manner. The delay in completion of the work would be detrimental

to the running of the train services. Thus the project is of national

importance and the work is public oriented. Once the project is

completed, it would attract tourists from within the country and also

from outside. The inordinate delay caused by the petitioner had

forced the respondent to de-scope the work under the conditions of

the contract mutually agreed upon and taking steps to finalise the

new agency for doing the rest of the work. Though the learned

senior counsel argued and pointed out several reasons for the

admitted delay in the execution of the contract, the termination of

the same is not challenged. Therefore, the correctness of the

termination of the contract, cannot be gone into this writ petition.

17. Clause 20.3 of the general conditions of the contract

provides for arbitration. The said clause stipulates that in case the

cumulative amount of claims in the contract is not exceeding 20%

https://www.mhc.tn.gov.in/judis/ Page 10/21 W.P.No.17888 of 2020

of the contract price, arbitration clause will not be applicable.

Therefore, where the claim, if any, that may be made by the

petitioner would exceed 20% of the contract price or not, has to be

decided and the arbitration clause can be invoked. Even presuming

that the respondent had committed breach of contract, the part

termination is not challenged by the petitioner. If the termination of

the contract is arbitrary, it is open to the petitioner to take recourse

under common law remedy. Therefore, when the general conditions

of the contract clause 15.2 specifically provides for completion of

the work through any other entity, the petitioner cannot challenge

the same, much less, ask for not awarding the contract to any third

party.

18. In support of his contention, the learned senior counsel

appearing for the petitioner placed reliance on the decision of the

Hon'ble Supreme Court in Sterling Computers Ltd. v. M&N

Publications Ltd. reported in (1993) 1 SCC 445, wherein at

paragraphs 12, 25 and 28, the Hon'ble Supreme Court held as

follows:

12. At times it is said that public authorities must have the same liberty as they have in framing the policies, even while entering into contracts because many contracts amount to implementation or projection of policies of the Government. But it cannot

https://www.mhc.tn.gov.in/judis/ Page 11/21 W.P.No.17888 of 2020

be overlooked that unlike policies, contracts are legally binding commitments and they commit the authority which may be held to be a State within the meaning of Article 12 of the Constitution in many cases for years. That is why the courts have impressed that even in contractual matters the public authority should not have unfettered discretion. In contracts having commercial element, some more discretion has to be conceded to the authorities so that they may enter into contracts with persons, keeping an eye on the augmentation of the revenue. But even in such matters they have to follow the norms recognised by courts while dealing with public property. It is not possible for courts to question and adjudicate every decision taken by an authority, because many of the Government Undertakings which in due course have acquired the monopolist position in matters of sale and purchase of products and with so many ventures in hand, they can come out with a plea that it is not always possible to act like a quasi-judicial authority while awarding contracts. Under some special circumstances a discretion has to be conceded to the authorities who have to enter into contract giving them liberty to assess the overall situation for purpose of taking a decision as to whom the contract be awarded and at what terms. If the decisions have been taken in bona fide manner although not strictly following the norms laid down by the courts, such decisions are upheld on the principle laid down by Justice Holmes, that courts while judging the constitutional validity of executive decisions must grant certain measure of freedom of “play in the joints” to the executive.

https://www.mhc.tn.gov.in/judis/ Page 12/21 W.P.No.17888 of 2020

25. The cases aforesaid on which reliance was placed on behalf of the appellants, have also reiterated that once the State decides to grant any right or privilege to others, then there is no escape from the rigour of Article 14; the executive does not have an absolute discretion, certain precepts and principles have to be followed, the public interest being the paramount consideration. It has also been pointed out that for securing the public interest one of the methods recognised is to invite tenders affording opportunity to submit offers for consideration in an objective manner. However, there may be cases where in the special facts and circumstances and due to compelling reasons which must stand the test on Article 14 of the Constitution, departure of the aforesaid rule can be made. This Court while upholding the contracts by negotiation in the cases referred to above has impressed as to how in the facts and circumstances of those cases the decisions taken by the State and the authorities concerned were reasonable, rational and in the public interest. The decisions taken in those cases by the authorities concerned, on judicial scrutiny were held to be free from bias, discrimination and under the exigencies of the situation then existing to be just and proper. On the basis of those judgments it cannot be urged that this Court has left to the option of the authorities concerned whether to invite tenders or not according to their own discretion and to award contracts ignoring the procedures which are basic in nature, taking into account factors which are not only irrelevant but detrimental to the public interest.

https://www.mhc.tn.gov.in/judis/ Page 13/21 W.P.No.17888 of 2020

28. Philanthropy is no part of the management of an undertaking, while dealing with a contractor entrusted with the execution of a contract. The supply of the directories to public in time, was a public service which was being affected by the liberal attitude of the MTNL and due to the condonation of delay on the part of the UIP/UDI. There was no justification on the part of the MTNL to become benevolent by entering into the supplemental agreement with no apparent benefit to the MTNL, without inviting fresh tenders from intending persons to perform the same job for the next five years. Public authorities are essentially different from those of private persons. Even while taking decision in respect of commercial transactions a public authority must be guided by relevant considerations and not by irrelevant ones. If such decision is influenced by extraneous considerations which it ought not to have taken into account the ultimate decision is bound to be vitiated, even if it is established that such decision had been taken without bias. The contract awarded for the publication of the directories had not only a commercial object but had a public element at the same time i.e. to supply the directories to lakhs of subscribers of telephones in Delhi and Bombay, every year within the stipulated time free of cost. In such a situation MTNL could not exercise an unfettered discretion after the repeated breaches committed by UIP/UDI, by entering into a supplemental agreement with the Sterling for a fresh period of more than five years on terms which were only beneficial to UIP/UDI/Sterling with corresponding no benefit to MTNL, which they have realised only after the High Court went into the matter in detail in its judgment under appeal.

https://www.mhc.tn.gov.in/judis/ Page 14/21 W.P.No.17888 of 2020

19. Per contra, the learned Additional Solicitor General of

India appearing for the respondent, relied on the decision of the

Hon'ble Supreme Court in Joshi Technologies International Inc.

v. Union of India and others reported in (2015) 7 SCC 728. In

the said judgment, the law was exhaustively considered and at

paragraph Nos.69 and 70, the Hon'ble Supreme Court, held as

follows:

69. The position thus summarised in the aforesaid principles has to be understood in the context of discussion that preceded which we have pointed out above. As per this, no doubt, there is no absolute bar to the maintainability of the writ petition even in contractual matters or where there are disputed questions of fact or even when monetary claim is raised. At the same time, discretion lies with the High Court which under certain circumstances, it can refuse to exercise. It also follows that under the following circumstances, “normally”, the Court would not exercise such a discretion:

69.1. The Court may not examine the issue unless the action has some public law character attached to it.

69.2. Whenever a particular mode of settlement of dispute is provided in the contract, the High Court would refuse to exercise its discretion under Article 226 of the Constitution and relegate the party to the said mode of settlement, particularly when settlement of disputes is to be resorted to through the means of arbitration.

https://www.mhc.tn.gov.in/judis/ Page 15/21 W.P.No.17888 of 2020

69.3. If there are very serious disputed questions of fact which are of complex nature and require oral evidence for their determination.

69.4. Money claims per se particularly arising out of contractual obligations are normally not to be entertained except in exceptional circumstances.

70. Further, the legal position which emerges from various judgments of this Court dealing with different situations/aspects relating to contracts entered into by the State/public authority with private parties, can be summarised as under:

70.1. At the stage of entering into a contract, the State acts purely in its executive capacity and is bound by the obligations of fairness.

70.2. State in its executive capacity, even in the contractual field, is under obligation to act fairly and cannot practise some discriminations.

70.3. Even in cases where question is of choice or consideration of competing claims before entering into the field of contract, facts have to be investigated and found before the question of a violation of Article 14 only be tested satisfactorily by taking detailed evidence, involving examination and cross-examination of witnesses, the case could not be conveniently or satisfactorily decided in proceedings under Article 226 of the Constitution. In such cases the Court can direct the aggrieved party to resort to alternate remedy of civil suit, etc. 70.4. Writ jurisdiction of the High Court under Article 226 of the Constitution was not intended to facilitate avoidance of obligation voluntarily incurred.

70.5. Writ petition was not maintainable to avoid contractual obligation. Occurrence of commercial difficulty, inconvenience or hardship in performance of https://www.mhc.tn.gov.in/judis/ Page 16/21 W.P.No.17888 of 2020

the conditions agreed to in the contract can provide no justification in not complying with the terms of contract which the parties had accepted with open eyes. It cannot ever be that a licensee can work out the licence if he finds it profitable to do so: and he can challenge the conditions under which he agreed to take the licence, if he finds it commercially inexpedient to conduct his business.

70.6. Ordinarily, where a breach of contract is complained of, the party complaining of such breach may sue for specific performance of the contract, if contract is capable of being specifically performed. Otherwise, the party may sue for damages.

70.7. Writ can be issued where there is executive action unsupported by law or even in respect of a corporation there is denial of equality before law or equal protection of law or if it can be shown that action of the public authorities was without giving any hearing and violation of principles of natural justice after holding that action could not have been taken without observing principles of natural justice.

70.8. If the contract between private party and the State/instrumentality and/or agency of the State is under the realm of a private law and there is no element of public law, the normal course for the aggrieved party, is to invoke the remedies provided under ordinary civil law rather than approaching the High Court under Article 226 of the Constitution of India and invoking its extraordinary jurisdiction.

70.9. The distinction between public law and private law element in the contract with the State is getting blurred. However, it has not been totally obliterated and where the matter falls purely in private field of contract, this Court has maintained the position https://www.mhc.tn.gov.in/judis/ Page 17/21 W.P.No.17888 of 2020

that writ petition is not maintainable. The dichotomy between public law and private law rights and remedies would depend on the factual matrix of each case and the distinction between the public law remedies and private law field, cannot be demarcated with precision. In fact, each case has to be examined, on its facts whether the contractual relations between the parties bear insignia of public element. Once on the facts of a particular case it is found that nature of the activity or controversy involves public law element, then the matter can be examined by the High Court in writ petitions under Article 226 of the Constitution of India to see whether action of the State and/or instrumentality or agency of the State is fair, just and equitable or that relevant factors are taken into consideration and irrelevant factors have not gone into the decision- making process or that the decision is not arbitrary.

70.10. Mere reasonable or legitimate expectation of a citizen, in such a situation, may not by itself be a distinct enforceable right, but failure to consider and give due weight to it may render the decision arbitrary, and this is how the requirements of due consideration of a legitimate expectation forms part of the principle of non-arbitrariness.

70.11. The scope of judicial review in respect of disputes falling within the domain of contractual obligations may be more limited and in doubtful cases the parties may be relegated to adjudication of their rights by resort to remedies provided for adjudication of purely contractual disputes.

20. Following the judgment in Joshi Technologies, a Full Bench https://www.mhc.tn.gov.in/judis/ Page 18/21 W.P.No.17888 of 2020

of the Supreme Court in State of U.P. vs. Sudhir Kumar Singh

and others reported in (2020) 8 MLC 359(SC), at paragraph

No.22 of the judgment, held as under:

22. In Rishi Kiran Logistics v. Board of Trustees of Kandla Port and Others reported in (2015) 13 SCC 233, this court held that a writ petition under Article 226, being a public law remedy, a "public law element" should be present on facts before Article 226 can be invoked. The law on this subject has been laid down exhaustively in Joshi Technologies Inc. v.

Union of India and others reported in (2015) 7 SCC

21. Judged by the touchstone of these tests, this court is of

the view that the general conditions of the contract has cautiously

provided for the de-scope of the work and continue the same with

the new entity for the completion of the balance work. Therefore,

reading the contract, as per its express terms, it is open to the

respondent to award a contract to a third party to the extent the

work that has been de-scoped from the petitioner. Hence the

petitioner does not have any right to stop the respondent from

proceeding further with the work much less when it involves a

public interest.

https://www.mhc.tn.gov.in/judis/ Page 19/21 W.P.No.17888 of 2020

22. In view of the discussions and the decisions quoted supra,

the writ petition fails and the same is dismissed. However, there

shall be no order as to costs. Consequently, the connected writ

miscellaneous petitions are closed.



                                                                               06.01.2021

                     Index          : Yes / No
                     Internet       : Yes / No

                     Asr

                     To

                     Rail Vikas Nigam Limited

Represented by its Chief Project Manager Thirumailai Railway Station Building Mylapore, Chennai - 600 004

Note:

Registry is directed to upload the order copy on or before 07.01.2021.

https://www.mhc.tn.gov.in/judis/ Page 20/21 W.P.No.17888 of 2020

PUSHPA SATHYANARAYANA, J.

Asr

W.P.No.17888 of 2020

Date : 06.01.2021

https://www.mhc.tn.gov.in/judis/ Page 21/21

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter