Wednesday, 06, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Trigyn Technologies Limited ... vs The Commissioner
2021 Latest Caselaw 1888 Mad

Citation : 2021 Latest Caselaw 1888 Mad
Judgement Date : 29 January, 2021

Madras High Court
M/S.Trigyn Technologies Limited ... vs The Commissioner on 29 January, 2021
                                                       1/45

                                   IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                              Reserved on :23.2.2021

                                              Delivered on : 24.3.2021

                                                      CORAM

                                      THE HON'BLE MR.JUSTICE B.PUGALENDHI

                                                W.P.No.3447 of 2021
                                                        and
                                          W.M.P.Nos.3949 and 4998 of 2021

                     M/s.Trigyn Technologies Limited 27,
                     rep. by its Company Secretary,
                     Mukesh Tank,
                     SDF-I, SEEPZ-SEZ,
                     Andheri East,
                     Mumbai 400 096.                                        Petitioner

                                    vs.

                     1. The Commissioner,
                        Erode City Municipal Corporation,
                        894 Brough Road, Erode 638 001.

                     2. The Chief Engineer,
                        Erode City Municipal Corporation,
                        894 Brough Road, Erode 638 001.

                     3. Assistant Executive Engineer,
                        Erode City Municipal Corporation,
                        Zone-2, 894 Brough Road,
                        Erode 638 001.

                     4. City Engineer,
                        Erode City Municipal Corporation,
                        894 Brough Road, Erode 638 001.




https://www.mhc.tn.gov.in/judis/
                                                          2/45

                     5. Erode Smart City Limited,
                        Registered office: Erode Corporation Building,
                        246, Meenachi Sundaranar Salai,
                        Erode 638 001.

                     6. M/s.Bharat Electronics Ltd.,
                        Kotdwara 246 149.
                        Uttarkhand.

                     7. M/s.SS Tech Commercials (P) Ltd.,
                        14, Arulmigu Sugavenswara
                           Kovil Complex, Cherry Road,
                        Salem 636 001.

                     8. M/s.Lantra Soft Pvt. Ltd.,
                        998, J.M.Building,
                        Avanashi Road,
                        Coimbatore 641 018.

                     9. M/s.Lookman Electroplast Industries,
                        15, Old No.9, First Floor,
                        II Street Extension,
                        III Main Road, CIT Nagar,
                        Nandanam, Chennai 600 035.                             Respondents


                               Writ Petition filed under Article 226 of the Constitution of India
                     seeking issuance of a writ of certiorarified mandamus calling for the
                     records relating to the impugned Minutes of the meeting held on
                     29.1.2021 at 3.30 pm on Conference Hall of the Erode City Municipal
                     Corporation rejecting the petitioner's bid as non responsive and not
                     eligible for further evaluation, digitally signed by the third respondent
                     on behalf of the first respondent, Tender Inviting and Tender Accepting
                     Authority, quash the same as illegal, incompetent and unconstitutional
                     and further pass an order directing the respondents to restart the
                     tender process.




https://www.mhc.tn.gov.in/judis/
                                                           3/45


                               For Petitioner     : Mr.Kumarpal Chopra

                               For R1 to R5       : Mr.S.R.Rajagopal,
                                                    Additional Advocate General assisted by
                                                    Mr.Raja Mathivanan, Standing Counsel



                                                          ORDER

This petition has been filed challenging the impugned Minutes of

the Meeting of the respondent Corporation dated 29.1.2021 rejecting

the petitioner's bid as non responsive and not eligible for evaluation.

2. The Erode City has been selected as one of the cities under

the Government of India Smart City Mission 2015. As a part of Smart

City Initiative, the respondent Corporation intended to set up an

Integrated Command Control Centre to bring all necessary data under

one roof. For the said purpose, the respondent Corporation invited

tenders from System Integrators to design, supply, Operate and

manage the said Integrated Command Control Centre in Erode City.

3. The petitioner, a Public Limited Company submitted its Tender

in consortium with M/s.Kerala State Electronics Development

Corporation Limited. the petitioner has also enclosed Earnest Money

Deposit amount in the form of a Demand Draft for a sum of

Rs.10,25,000/-. The technical bids were opened on 29.1.2021 and the

https://www.mhc.tn.gov.in/judis/

Technical Evaluation Committee disqualified the petitioner company

that they failed to meet the qualification criteria for technical bid on

two counts that the Power of Attorney of the lead bidder (Trigyn)

signed by the Consortium Member (KELTRON) does not contain the

date or signature of the Lead bidder and as per the Tender condition

No.4, the documentary proof of consortium agreement on the roles

and responsibilities of each Member, the responsibility of the lead

bidder and the maximum stake held by the lead bidder were not

mentioned in the Agreement and therefore, the petitioner’s bid was

rejected as not satisfactory. The said Minutes of the Meeting of the

Technical Evaluation Committee dated 29.1.2021 is under challenge in

this writ petition.

4. Mr.Kumarpal Chopra, learned counsel appearing for the

petitioner submits that the defects which have been pointed out by

the Technical Evaluation Committee are small clerical errors that were

crept in due to inadvertence which can easily be rectified and they

cannot be treated as technical errors for rejection of the bid itself and

defining the role and responsibilities for the lead and consumption

partner in consortium agreement is not a term of instructions to the

bidders and it is not an essential condition. He would further submit

https://www.mhc.tn.gov.in/judis/

that the condition No.2 of the Tender document requires a submission

of a letter of authorization authorizing the tender signatory and such a

condition is only an ancillary condition and it is not an essential

condition and the respondent has disqualified the petitioner's bid in a

partisan manner where as another bidder, who has not complied with

the same condition on the mentioning of the stake of the lead bidder in

the consortium agreement has been qualified and therefore, the

rejection of the petitioner's bid has been made intentionally to

eliminate the petitioner and it is a pure act of bias when they have

taken a stand otherwise in respect of M/s.SS Tech Commercials (P) Ltd

on the same mistake. According to the learned counsel for the

petitioner, the reasoning given for rejecting the petitioner's bid is a

hostile discrimination and unfavorable treatment and it is unjust and

unfair and therefore the entire tender process raises a serious doubt

on the evaluation and rejection and therefore, it warrants interference

of this court.

5. The learned counsel for the petitioner has also relied upon the

following judgments in support of his contentions:-

(i) Poddar Steel Corporation v. Ganesh Engineering Works

and Others [( 1991) 3 SCC 273]

https://www.mhc.tn.gov.in/judis/

(ii) Bakshi Security and Personnel Services Pvt. Ltd. v.

Devkishan Computed Pvt. Ltd. and Ors., (2016) 8 SCC 446

(iii) B.S.N. Joshi & Sons Ltd. v. Nair Coal Services Ltd.

[B.S.N. Joshi & Sons Ltd. v. Nair Coal Services Ltd., (2006) 11

SCC 548]

(iv) Om Prakash Sharma vs Ramesh Chand Prashar & Ors

(Civil Appeal No.5101 of 2016 dated 13.5.2016)

(v) Kanhaiyalal Agarwal v. Union of India & Ors. [(2002)

6 SCC 315

(vi) W.B. State Electricity Board vs. Patel Engineering Co.

(2001 (2) SCC 451)

(vii) G.J. Fernandez v. State of Karnataka and Others

[(1990) 2 SCC 488]

(viii) lvrcl Infrastructures & Projects vs NHAI in WP (C)

No.235 of 2011

(ix) Ramunia Fabricators SDN BHD & Ors. Vs. Oil and

Natural Gas Corpn. Ltd. & Ors., 150 (2008) DLT 1

(x) Kapsch Metro JV Vs. Union of India & Anr., 140 (2007)

https://www.mhc.tn.gov.in/judis/

DLT 378.

6. Mr S.R.Rajagopal, learned Additional Advocate General

assisted by Mr.Rajamathivanan, learned Standing Counsel appearing

for Respondents 1 to 5 would submit that the Technical Evaluation

Committee has made their evaluation as per class 3.2 of and 3.5 of the

Request For Proposal (RFP) and the verification of document is part of

the work assigned to the Technical Evaluation Committee and the

selection process for bidders is mentioned in clause 3 of the Tender

document as processing of Earnest Money Deposit (EMD), Technical

Bid and (c) Commercial Bid. The Technical Evaluation Committee is

expected to examine the bids by determining whether they are

complete, whether the documents are properly signed and whether

the bids are in order. As per clause 3.2, the petitioner's Tender

document was submitted without the letter of authorization (Power of

Attorney). The bidders can participate either as a sole bidder or by

consortium. If it is a consortium bid, the lead bidder shall be a

registered entity and they must enclose a documentary proof such as

Incorporation Certificate and the Consortium Agreement and must

state (i) Roles and responsibilities of each member. (ii) The Lead

https://www.mhc.tn.gov.in/judis/

Bidder shall have maximum Stake in the consortium. (iii) The Lead

Bidder shall be responsible and jointly & severally liable under this

RfP.

7. The petitioner has filed with the power of attorney unsigned

and without any attestation on each page. The petitioner has also

admitted the same as a clerical error inadvertently made. Similarly,

the petitioner has not furnished the details as to the roles and

responsibilities of the members of consortium and the maximum stake

held by the lead bidder as per class 3.5 of the Tender document and

therefore the Technical Evaluation Committee has rightly rejected the

petitioner’s bid. The learned Additional Advocate General would

further submit that in fact another Company by name S.S.Tech, Salem

which also applied on consortium did not mention the stake of the

lead bidder in the tender document, however it was annexed along

with the bid document though it was not mentioned in the agreement

and therefore, the bid document of S.S. Tech, Salem was treated as

satisfactory on its evaluation, but the bid was not allotted to the said

S.S.Tech, Salem. According to the learned Additional Advocate

General, the work was awarded in favor of the 8th respondent

https://www.mhc.tn.gov.in/judis/

M/s.Lantra Soft Pvt. Ltd. and the letter of acceptance has been issued

to the 8th respondent in Roc.E1/3945/2020 dated 16.2.2021 and the

work order has also been issued on 17.2.2021. It is further submitted

that the 8th respondent has also commenced the execution of the

work.

8. The learned Additional Advocate General submits that the

Rules and procedures contemplated under the Tamil Nadu

Transparency in Tenders Acts and Rules were strictly adhered to and

there is no violation of the Acts and Rules and the petitioner has not

pointed out any procedural lapse in his pleadings. Further, no mala fide

is pleaded by the petitioner as against the respondent. The letter of

authorisation and consortium agreement are essential conditions and

the petitioner has not stated the roles and responsibilities of each

Member and that of the lead bidder. The petitioner cannot interpret

that it is not an essential condition and if any relaxation is provided to

the petitioner, then it would amount to bias and favouritism. He would

further submit that the delay in execution of the work would cause

great prejudice to the general public and it would be against the public

interest and requested to dismiss the writ petition.

9. The learned Additional Advocate General has also relied upon

https://www.mhc.tn.gov.in/judis/

the following decisions in support of his contention:-

(i) Jagadish Mandal v. State of Orissa (2007 (14) SCC 517

(ii) Silppi Constructions Contractors v. Union of India,

(2019 SCC OnLine SC 1133)

(iii) Michigan Rubber India Limited v. State of Karnataka

and others (2012 (8) SCC 216)

(iv) Afcons Infastructure Limited v. Nagpur Metro Rail

Corporation Limited and another (2016 (16) SCC 818)

(v) Municipal Corpn, Ujjain v. BVG India Ltd., (2018) 5 SCC

462].

10. This court paid its anxious consideration to the rival

submissions made and also perused the materials placed on record.

11. The respondent Corporation invited tenders for selection of

System Integrators to design, supply, implement, operate and manage

the Integrated Command and Control Centre in Erode City under the

Erode Smart City Scheme. The Tender Notification was published in

newspapers both in vernacular and also in the State Tender Bulletin

dated 3.12.2020. Along with the petitioner, five other companies have

submitted their Request For Proposal (RFP). The petitioner Company

M/s.Trigyn Technologies Limited submitted its bid in consortium with

https://www.mhc.tn.gov.in/judis/

M/s.Kerala State Electronics Development Corporation Limited. The

selection process is of verification of EMD, Technical Bid and

Commercial Bid. The technical bids were opened in the presence of all

the representatives of the petitioners by the Technical Evaluation

Committee on 22.12.2020. The Technical Evaluation Committee

declared the petitioners bid as non responsive since the petitioner did

not satisfy class 3.2 of the RFP and for non furnishing of the required

data as per clause 3.5 of RFP.

12. Clause 3.2 of the RFP is extracted hereunder:-

"3.2 Preliminary Examination of Bids

ERODE CITY CORPORATION/ ERODE SMART CITY

LIMITED shall examine the bids to determine

whether they are complete, whether the documents

have been properly signed and whether the bids are

generally in order. Any bids found to be

nonresponsive for any reason or not meeting any

criteria specified in the RfP, shall be rejected by

ERODE CITY CORPORATION/ ERODE SMART CITY

LIMITED and shall not be included for further

consideration.

https://www.mhc.tn.gov.in/judis/

Initial Bid scrutiny shall be held and bids will

be treated as non-responsive, it bids are:

a. Not submitted in format as specified in the RfP

document.

b. Received without the Letter of Authorization

(Power of Attorney).

c. With incomplete information, subjective,

conditional offers and partial otters submitted.

d. Submitted without the documents requested.

e. Non-compliant to any of the clauses mentioned in

the RfP.

f. With lesser validity period

g. Signature of Authorized personnel on all pages

both on Hard & Copy of the bid."

13. As per the terms of RFP, the initial bid scrutiny shall be made

as per clause 3.2 and if any bid is found to be incomplete not properly

signed and not in order be treated as non responsive and will be

rejected as per the said clause. The letter of authorization (power of

attorney) is one of the clauses mentioned as requirement as per clause

3.2.

https://www.mhc.tn.gov.in/judis/

14. In this case, the petitioner is said to have submitted a letter

of authorization (power of attorney) whereas it has been signed by the

consortium member and not by the lead bidder. Further, in the

consortium agreement the roles and responsibilities of the lead bidder

and consortium member was not mentioned and the maximum stake

held by the lead bidder was also not mentioned.

15. The petitioner has not denied the same and in fact he has

mentioned that it is only a clerical error inadvertently made which can

be easily rectifiable and according to the petitioner, it is not an

essential condition and it is a curable one.

16. In clause 3.5, the eligibility criteria is mentioned in the case

of consortium bid as under:-

"For Consortium bids :

Consortium Agreement clearly stating the

i. Roles and responsibilities of each member.

ii. The Lead Bidder shall have maximum Stake in

the consortium.

iii. The Lead Bidder shall be responsible and jointly

& severally liable under this RfP."

https://www.mhc.tn.gov.in/judis/

17. Therefore, on the basis of the conditions of RFP, the

Technical Evaluation Committee, in its Minutes of meeting dated

29.1.2021, declared the petitioner's bid as non responsive.

18. The relevant portions of the decisions relied upon by the

learned counsel appearing for the petitioner are extracted hereunder:-

(i) In Poddar Steel Corporation v. Ganesh Engineering

Works and Others [( 1991) 3 SCC 273] it was held thus:

"6. It is true that in submitting its tender accompanied

by a cheque of the Union Bank of India and not of the

State Bank clause 6 of the tender notice was not

obeyed literally, but the question is as to whether the

said non-compliance deprived the Diesel Locomotive

Works of the authority to accept the bid. As a matter

of general proposition, it cannot be held that an

authority inviting tenders is bound to give effect to

every term mentioned in the notice in meticulous

detail, and is not entitled to waive even a technical

irregularity of little or no significance; The

https://www.mhc.tn.gov.in/judis/

requirements in a tender notice can be classified into

two categories those which lay down the essential

conditions of eligibility and the others which are

merely ancillary or subsidiary with the main object to

be achieved by the condition. In the erst case the

authority issuing the tender may be required to

enforce them rigidly. In the other cases it must be

open to the authority to deviate from and not to insist

upon the strict literal compliance of the condition in

appropriate cases."

(ii) In Bakshi Security and Personnel Services Pvt. Ltd. v.

Devkishan Computed Pvt. Ltd. and Ors., (2016) 8 SCC 446, this

Court held:

“14. The law is settled that an essential condition of a

tender has to be strictly complied with. In Poddar

Steel Corpn. v Ganesh Engg. Works (1991) 3 SCC

273] this Court held as under: (SCC p. 276, para 6)

“6. ... The requirements in a tender notice

can be classified into two categories-those

https://www.mhc.tn.gov.in/judis/

which lay down the essential conditions of

eligibility and the others which are merely

ancillary or subsidiary with the main object

to be achieved by the condition. In the first

case the authority issuing the tender may

be required to enforce them rigidly. In the

other cases it must be open to the authority

to deviate from and not to insist upon the

strict literal compliance of the condition in

appropriate cases.

.... .... ....

16. We also agree with the contention of

Shri.Raval that the writ jurisdiction cannot be utilised

to make a fresh bargain between parties.”

(iii) In B.S.N. Joshi & Sons Ltd. v. Nair Coal Services Ltd.

[B.S.N. Joshi & Sons Ltd. v. Nair Coal Services Ltd., (2006) 11

SCC 548] this Court held as under: (SCC pp. 571-72, para 66)

“(i) if there are essential conditions, the same must

https://www.mhc.tn.gov.in/judis/

be adhered to;

(ii) if there is no power of general relaxation,

ordinarily the same shall not be exercised and the

principle of strict compliance would be applied where

it is possible for all the parties to comply with all such

conditions fully;

(iii) if, however, a deviation is made in relation to all

the parties in regard to any of such conditions,

ordinarily again a power of relaxation may be held to

be existing;

(iv) the parties who have taken the benefit of such

relaxation should not ordinarily be allowed to take a

different stand in relation to compliance with another

part of tender contract, particularly when he was also

not in a position to comply with all the conditions of

tender fully, unless the court otherwise finds

relaxation of a condition which being essential in

nature could not be relaxed and thus the same was

wholly illegal and without jurisdiction;

(v) when a decision is taken by the appropriate

https://www.mhc.tn.gov.in/judis/

authority upon due consideration of the tender

document submitted by all the tenderers on their own

merits and if it is ultimately found that successful

bidders had in fact substantially complied with the

purport and object for which essential conditions were

laid down, the same may not ordinarily be interfered

with;...”

(iv) The Apex Court in Om Prakash Sharma vs Ramesh

Chand Prashar & Ors (Civil Appeal No.5101 of 2016 dated

13.5.2016) reiterating Poddar Steel Corpn. v Ganesh Engg. Work

held thus

“In the Present case the site in question was to be

sold on outright sale basis. The advertisement or the

stipulations therein did not contemplate creation and

or continuation of any relationship between the

parties calling for continued existence of any

particular level of financial parameters on part of the

bidder except the ability to Pay the price as per his

bid. The Condition was not an essential Condition at

all but was merely ancillary to achieve the main

https://www.mhc.tn.gov.in/judis/

object that was to ensure that the bid amount was

paid Promptly. The advertisement contemplated

payment of bid amount whereafter the Sale Deed

would be executed and not a relationship which would

have continued for considerable period warranting an

assurance of continued ability on part of the bidder to

fulfil his obligations under the arrangement. Nor was

this condition aimed at ensuring a particular level of

financial ability on part of the bidder, for example in

cases where the benefit is designed to be given to a

person coming from a particular financial segment, in

which case the condition could well be termed

essential. The idea was pure and clear sale

simplicitor. As a matter of fact, the appellant did pay

the entire bid amount within the prescribed period

and the Sale Deed was also executed in his favor. In

the circumstances the relevant condition in the

advertisement would not fall in the first category of

cases as dealt with by this Court in Poddar Steel

Corporation (supra). The authorities could therefore

https://www.mhc.tn.gov.in/judis/

validly deviate from and not insist upon strict literal

compliance. The discretion so exercised by the

authorities could not have therefore been faulted.

Thus, the assessment made by the High Court that

the condition in question was an essential condition

for non-compliance of which, the bid furnished by the

appellant was required to be rejected, in our view was

not correct."

(v) The Apex Court once again in the case of Kanhaiyalal

Agarwal v. Union of India & Ors. [(2002) 6 SCC 315 held that if

the bid submitted by the bidder substantially complies with the purport

and object for which the essential conditions were laid down in the

tender document, such bid should not be rejected or disqualified for

non-compliance/ a deviation with regard to a non-essential and / or

ancillary condition.

(vi) In W.B. State Electricity Board vs. Patel Engineering

Co. (2001 (2) SCC 451) it has been held as under:-

”23. The mistakes/errors in question, it is stated,

https://www.mhc.tn.gov.in/judis/

are unintentional and occurred due to the fault of

computer termed as "a repetitive systematic

computer typographical transmission failure". It is

difficult to accept this contention. A mistake may

be unilateral or mutual but it is always

unintentional. If it is intentional it ceases to be a

mistake. Here the mistakes may be unintentional

but it was not beyond the control of respondents 1

to 4 to correct the same before submission of the

bid. Had they been vigilant in checking the bid

documents before their submission, the mistakes

would have been avoided. Further correction of

such mistakes after one-and-a-half months of

opening of the bids will also be violative of clauses

24.1, 24.3 and 29.1 of the ITB."

(vii) This aspect was examined by this Court in G.J. Fernandez

v. State of Karnataka a case dealing with tenders. Although not in

an entirely identical situation as the present one, the observations in

the judgment support our view. In G.J. Fernandez v. State of

https://www.mhc.tn.gov.in/judis/

Karnataka and Others [(1990) 2 SCC 488] wherein this Court

observed :

"15. Thirdly, the conditions and stipulations in a

tender notice like this have two types of

consequences, The first is that the party issuing

the tender has the right to punctiliously and

rigidly enforce them. Thus, if a party does not

strictly comply with the requirements of para III,

V or VI of the NIT, it is open to the KPC to decline

to consider the party for the contract and if a

party comes to court saying that the KPC should

be stopped from doing so, the court will decline

relief. The second consequence, indicated by this

Court in earlier decisions, is not that the KPC

cannot deviate from these guidelines at all in any

situation but that any deviation, if made, should

not result in arbitrariness or discrimination. It

comes in for application where the nonconformity

with, or relaxation from, the prescribed standards

results in some substantial prejudice or injustice

https://www.mhc.tn.gov.in/judis/

to any of the parties involved or to public interest

in general. For example, in this very case, the

KPC made some changes in the time frame

originally prescribed. These changes affected all

intending applicants alike and were not

objectionable. In the same way, changes or

relaxations in other directions would be

unobjectionable unless the benefit of those

changes or relaxations were extended to some

but denied to others. The fact that a document

was belatedly entertained from one of the

applicants will cause substantial prejudice to

another party who wanted, likewise, an extension

of time for filing a similar certificate or document

but was declined the benefit. It may perhaps be

said to cause prejudice also to a party which can

show that it had refrained from applying for the

tender documents only because it thought it

would not be able to produce the document by

the time stipulated but would have applied had it

https://www.mhc.tn.gov.in/judis/

known that the rule was likely to be relaxed."

(viii) In lvrcl Infrastructures & Projects vs NHAI in WP (C)

No.235 of 2011 it has been held as under:-

“30. There is no doubt about the proposition that the

terms & conditions of a tender document must be

strictly adhered to. However, the legal position in

this behalf is enunciated in Poddar Steel

Corporation Vs. Ganesh Engineering Works

&Ors. (1991) 3 SCC 273. It was held that

deviations from non-essential or ancillary /

subsidiary requirement being a minor technical

irregularity can be waived. The issue, thus, arises

whether the discrepancy in the present case can be

stated to be of such minor technical nature.”

(ix) In Ramunia Fabricators SDN BHD &

Ors. Vs. Oil and Natural Gas Corpn. Ltd. & Ors.,

150 (2008) DLT 1, the distinction between

essential and non-essential conditions in a contract

https://www.mhc.tn.gov.in/judis/

was emphasized. In the facts of the case, the bids

were submitted by a subsidiary on the basis of the

documents purchased by another subsidiary of a

single parent company. The bid submitted by the

petitioner was held to be perfectly in tune with the

terms of the bid; The Hon’ble Court observed that

whether or not a condition is an essential would

depend upon the fact situation of each case and the

nature of the conditions while relying upon the

judgment in Poddar Steel Corporation"s case

(supra).

(x) In Kapsch Metro JV Vs. Union of India

& Anr., 140 (2007) DLT 378, it was emphasized

that public interest requires a wider participation of

bidders to ensure healthy competition especially

keeping in mind the dictum laid down in Poddar

Steel Corporation's case (supra). The deficiency of

17 days' period in the EMD of 180 days' validity

period which too was subsequently altered in order

https://www.mhc.tn.gov.in/judis/

to conform to the prescribed requirement was held

to be a technical irregularity of little significance and

worthy of being waived.

19. On the other hand, the learned Additional Advocate

General has relied upon the following judgments of the honourable

Supreme Court and submit that the Tender conditions in question are

essential conditions:-

(i) In Jagadish Mandal v. State of Orissa (2007 (14) SCC

517, the Hon'ble Supreme Court has held as under:

"22. Judicial review of administrative action is

intended to prevent arbitrariness, irrationality,

unreasonableness, bias and mala fides. Its purpose is

to check whether choice or decision is made 'lawfully'

and not to check whether choice or decision is 'sound'.

When the power of judicial review is invoked in

matters relating to tenders or award of contracts,

certain special features should be borne in mind. A

contract is a commercial transaction. Evaluating

tenders and awarding contracts are essentially

https://www.mhc.tn.gov.in/judis/

commercial functions. Principles of equity and natural

justice stay at a distance. If the decision relating to

award of contract is bona fide and is in public interest,

courts will not, in exercise of power of judicial review,

interfere even if a procedural aberration or error in

assessment or prejudice to a tenderer, is made out.

The power of judicial review will not be permitted to

be invoked to protect private interest at the cost of

public interest, or to decide contractual disputes. The

tenderer or contractor with a grievance can always

seek damages in a civil court. Attempts by

unsuccessful tenderers with imaginary grievances,

wounded pride and business rivalry, to make

mountains out of molehills of some

technical/procedural violation or some prejudice to

self, and persuade courts to interfere by exercising

power of judicial review, should be resisted. Such

interferences, either interim or final, may hold up

public works for years, or delay relief and succour to

thousands and millions and may increase the project

https://www.mhc.tn.gov.in/judis/

cost manifold. Therefore, a court before interfering in

tender or contractual matters in exercise of power of

judicial review, should pose to itself the following

questions :

i) Whether the process adopted or decision

made by the authority is mala fide or intended to

favour someone or

Whether the process adopted or decision made

is so arbitrary and irrational that the court can say

"the decision is such that no responsible authority

acting reasonably and in accordance with relevant law

could have reached".

ii) Whether public interest is affected.

If the answers are in the negative, there should be no

interference under Article 226. Cases involving black-

listing or imposition of penal consequences on a

tenderer/contractor or distribution of state largesse

(allotment of sites/shops, grant of licences,

dealerships and franchises) stand on a different

footing as they may require a higher degree of

https://www.mhc.tn.gov.in/judis/

fairness in action."

(ii) In Silppi Constructions Contractors v. Union of India,

(2019 SCC OnLine SC 1133) the Apex Court has held as under:-

"19. This Court being the guardian of fundamental

rights is duty bound to interfere when there is

arbitrariness, irrationality, mala fides and bias.

However, this Court in all the aforesaid decisions

has cautioned time and again that courts should

exercise a lot of restraint while exercising their

powers of judicial review in contractual or

commercial matters. This Court is normally loathe

to interfere in contractual matters unless a clear-cut

case of arbitrariness or mala fides or bias or

irrationality is made out. One must remember that

today many public sector undertakings compete

with the private industry. The contracts entered into

between private parties are not subject to scrutiny

under writ jurisdiction. No doubt, the bodies which

are State within the meaning of Article 12 of the

https://www.mhc.tn.gov.in/judis/

Constitution are bound to act fairly and are

amenable to the writ jurisdiction of superior courts

but this discretionary power must be exercised with

a great deal of restraint and caution. The Courts

must realise their limitations and the havoc which

needless interference in commercial matters can

cause. In contracts involving technical issues the

courts should be even more reluctant because most

of us in judges’ robes do not have the necessary

expertise to adjudicate upon technical issues

beyond our domain. As laid down in the judgments

cited above the courts should not use a magnifying

glass while scanning the tenders and make every

small mistake appear like a big blunder. In fact, the

courts must give “fair play in the joints” to the

government and public sector undertakings in

matters of contract. Courts must also not interfere

where such interference will cause unnecessary loss

to the public exchequer.

20. The essence of the law laid down in the

https://www.mhc.tn.gov.in/judis/

judgments referred to above is the exercise of

restraint and caution; the need for overwhelming

public interest to justify judicial intervention in

matters of contract involving the state

instrumentalities; the courts should give way to the

opinion of the experts unless the decision is totally

arbitrary or unreasonable; the court does not sit like

a court of appeal over the appropriate authority; the

court must realise that the authority floating the

tender is the best judge of its requirements and,

therefore, the court’s interference should be

minimal. The authority which floats the contract or

tender, and has authored the tender documents is

the best judge as to how the documents have to be

interpreted. If two interpretations are possible then

the interpretation of the author must be accepted.

The courts will only interfere to prevent

arbitrariness, irrationality, bias, mala fides or

perversity. With this approach in mind we shall deal

with the present case.

https://www.mhc.tn.gov.in/judis/

.... .... ....

25. That brings us to the most contentious

issue as to whether the learned single judge of the

High Court was right in holding that the appellate

orders were bad since they were without reasons.

We must remember that we are dealing with purely

administrative decisions. These are in the realm of

contract. While rejecting the tender the person or

authority inviting the tenders is not required to give

reasons even if it be a state within the meaning of

Article 12 of the Constitution. These decisions are

neither judicial nor quasi-judicial. If reasons are to

be given at every stage, then the commercial

activities of the State would come to a grinding halt.

The State must be given sufficient leeway in this

regard. The Respondent nos. 1 and 2 were entitled

to give reasons in the counter to the writ petition

which they have done."

(iii) In Michigan Rubber India Limited v. State of

https://www.mhc.tn.gov.in/judis/

Karnataka and others (2012 (8) SCC 216), the Hon'ble Supreme

Court has held as under:-

"23) From the above decisions, the following

principles emerge:

(a) the basic requirement of Article 14 is

fairness in action by the State, and non-

arbitrariness in essence and substance is the

heartbeat of fair play. These actions are amenable

to the judicial review only to the extent that the

State must act validly for a discernible reason and

not whimsically for any ulterior purpose. If the State

acts within the bounds of reasonableness, it would

be legitimate to take into consideration the national

priorities;

(b) fixation of a value of the tender is entirely

within the purview of the executive and courts

hardly have any role to play in this process except

for striking down such action of the executive as is

proved to be arbitrary or unreasonable. If the

Government acts in conformity with certain healthy

standards and norms such as awarding of contracts

https://www.mhc.tn.gov.in/judis/

by inviting tenders, in those circumstances, the

interference by Courts is very limited;

(c) In the matter of formulating conditions of

a tender document and awarding a contract, greater

latitude is required to be conceded to the State

authorities unless the action of tendering authority

is found to be malicious and a misuse of its

statutory powers, interference by Courts is not

warranted;

(d) Certain preconditions or qualifications for

tenders have to be laid down to ensure that the

contractor has the capacity and the resources to

successfully execute the work; and

(e) If the State or its instrumentalities act

reasonably, fairly and in public interest in awarding

contract, here again, interference by Court is very

restrictive since no person can claim fundamental

right to carry on business with the Government.

24) Therefore, a Court before interfering in

tender or contractual matters, in exercise of power

https://www.mhc.tn.gov.in/judis/

of judicial review, should pose to itself the following

questions:

(i) Whether the process adopted or decision

made by the authority is mala fide or intended to

favour someone; or whether the process adopted or

decision made is so arbitrary and irrational that the

court can say: “the decision is such that no

responsible authority acting reasonably and in

accordance with relevant law could have reached”;

and (ii) Whether the public interest is affected. If

the answers to the above questions are in negative,

then there should be no interference under Article

226."

(iv) In Afcons Infastructure Limited v. Nagpur Metro Rail

Corporation Limited and another (2016 (16) SCC 818), it has

been held as follows:-

"11. Recently, in Central Coalfields Ltd. v. SLL-

SML (Joint Venture Consortium) it was held by

this Court, relying on a host of decisions that the

https://www.mhc.tn.gov.in/judis/

decision making process of the employer or owner

of the project in accepting or rejecting the bid of a

tenderer should not be interfered with.

Interference is permissible only if the decision

making process is mala fide or is intended to

favour someone. Similarly, the decision should not

be interfered with unless the decision is so

arbitrary or irrational that the Court could say that

the decision is one which no responsible authority

acting reasonably and in accordance with law

could have reached. In other words, the decision

making process or the decision should be perverse

and not merely faulty or incorrect or erroneous.

No such extreme case was made out by GYT-TPL

JV in the High Court or before us.

12. In Dwarkadas Marfatia and Sons v.

Board of Trustees of the Port of Bombay it

was held that the constitutional Courts are

concerned with the decision making process. Tata

Cellular v. Union of India went a step further

https://www.mhc.tn.gov.in/judis/

and held that a decision if challenged (the decision

having been arrived at through a valid process),

the constitutional Courts can interfere if the

decision is perverse. However, the constitutional

Courts are expected to exercise restraint in

interfering with the administrative decision and

ought not to substitute its view for that of the

administrative authority. This was confirmed in

Jagdish Mandal v. State of Orissa as

mentioned in Central Coalfields.

13. In other words, a mere disagreement

with the decision making process or the decision

of the administrative authority is no reason for a

constitutional Court to interfere. The threshold of

mala fides, intention to favour someone or

arbitrariness, irrationality or perversity must be

met before the constitutional Court interferes with

the decision making process or the decision."

(v) In Municipal Corpn, Ujjain v. BVG India Ltd., (2018) 5

https://www.mhc.tn.gov.in/judis/

SCC 462], it has been held as under:-

"45. Evaluating tenders and awarding contracts

are essentially commercial transactions/contracts.

If the decision relating to award of contract is in

public interest, the Courts will not, in exercise of

the power of judicial review, interfere even if a

procedural aberration or error in awarding the

contract is made out. The power of judicial review

will not be permitted to be invoked to protect

private interest by ignoring public interest.

Attempts by unsuccessful bidders with an artificial

grievance and to get the purpose defeated by

approaching the Court on some technical and

procedural lapses, should be handled by Courts

with firmness. The exercise of the power of judicial

review should be avoided if there is no irrationality

or arbitrariness. In the matter on hand, we do not

find any illegality, arbitrariness, irrationality or

unreasonableness on the part of the expert body

while in action. So also, we do not find any bias or

https://www.mhc.tn.gov.in/judis/

mala fides either on the part of the corporation or

on the part of the technical expert while taking the

decision. Moreover, the decision is taken keeping

in mind the public interest and the work

experience of the successful bidder.

46. As held in Tata Cellular (supra), the

terms of the tender are not open to judicial

scrutiny as the invitation to tender is a matter of

contract. Decisions on the contract are made

qualitatively by experts. M/s Eco Save Systems

Private Limited [respondent no.2 in Civil Appeal

arising from SLP (C) No. 11967/2016] is a project

consultant and technical advisor of the Ujjain

Municipal Corporation. It provides technical

consultancy and advisory services. The documents

produced along with the counter affidavit filed by

respondent no.2 would show that respondent no.2

is an expert in municipal solid waste management.

It is brought to our notice that respondent no.2

has developed a Detailed Project Report (DPR)

https://www.mhc.tn.gov.in/judis/

cum Master Plan of Ujjain City for up-gradation,

systematization and abidance of the Municipal

Solid Waste Rules, 2000 for the period 2012 to

2042, and the Jawaharlal Nehru National Urban

Renewal Mission is stated to have sanctioned

35.88 crores for the purpose. There is no dispute

by any of the parties that respondent no.2 is an

expert in municipal solid waste management. We

also hasten to add that there are no allegations of

bias or mala fides against the technical committee,

though grounds are taken by BVG India Limited

before the High Court that the decision of the

expert committee is not proper.

... ... ....

64. Thus, the questions to be decided in this

appeal are answered as follows:

64.1 Under the scope of judicial review, the High

Court could not ordinarily interfere with the

judgment of the expert consultant on the issues of

technical qualifications of a bidder when the

https://www.mhc.tn.gov.in/judis/

consultant takes into consideration various factors

including the basis of non-performance of the

bidder;

64.2 A bidder who submits a bid expressly

declaring that it is submitting the same

independently and without any partners,

consortium or joint venture, cannot rely upon the

technical qualifications of any 3rd Party for its

qualification.

64.3 It is not open to the Court to independently

evaluate the technical bids and financial bids of

the parties as an appellate authority for coming to

its conclusion inasmuch as unless the thresholds of

mala fides, intention to favour someone or bias,

arbitrariness, irrationality or perversity are met,

where a decision is taken purely on public interest,

the Court ordinarily should exercise judicial

restraint.

65. In view of the above, the impugned

judgment and order of the High Court cannot be

https://www.mhc.tn.gov.in/judis/

sustained and the same is set aside."

20. In clause 3.2 of the RFP, it has been specifically mentioned

that the letter of authorization (power of attorney) is a required

document and if it is received without signature, it is a ground for

rejection treating it as non responsive. As per clause 3.2(g), the

signature of the authorized person on all pages on hard copy of the bid

is stated as a requirement for the preliminary examination and if the

documents are not properly signed if it is not in order, the RFP would

be rejected as non responsive. Similarly, for the consortium bid, the

consortium agreement is expected to state the roles and

responsibilities and admittedly these two conditions have not been

complied with and this cannot be treated as an essential requirement

when the tender document specifically mentioned that the

requirements as per the aforesaid clause are essential documents.

21. In view of the ratio laid down by the Hon'ble Supreme Court

cited supra, the defects as pointed out by the respondents are

essential conditions as per the tender document and this court is not

inclined to interfere with the impugned minutes of the rejection of the

https://www.mhc.tn.gov.in/judis/

petitioner’s bid. Accordingly, the writ petition is dismissed. No costs.

The connected Miscellaneous Petitions are also dismissed.

24.3.2021.

Index: Yes/No.

ssk.

To

1. The Commissioner, Erode City Municipal Corporation, 894 Brough Road, Erode 638 001.

2. The Chief Engineer, Erode City Municipal Corporation, 894 Brough Road, Erode 638 001.

3. Assistant Executive Engineer, Erode City Municipal Corporation, Zone-2, 894 Brough Road, Erode 638 001.

4. City Engineer, Erode City Municipal Corporation, 894 Brough Road, Erode 638 001.

5. Erode Smart City Limited, Registered office: Erode Corporation Building, 246, Meenachi Sundaranar Salai, Erode 638 001.

6. M/s.Bharat Electronics Ltd., Kotdwara 246 149.

Uttarkhand.

https://www.mhc.tn.gov.in/judis/

7. M/s.SS Tech Commercials (P) Ltd., 14, Arulmigu Sugavenswara Kovil Complex, Cherry Road, Salem 636 001.

8. M/s.Lantra Soft Pvt. Ltd., 998, J.M.Building, Avanashi Road, Coimbatore 641 018.

9. M/s.Lookman Electroplast Industries, 15, Old No.9, First Floor, II Street Extension, III Main Road, CIT Nagar, Nandanam, Chennai 600 035.

10. M/s.Trigyn Technologies Limited 27, rep. by its Company Secretary, Mukesh Tank, SDF-I, SEEPZ-SEZ, Andheri East, Mumbai 400 096.

https://www.mhc.tn.gov.in/judis/

B.PUGALENDHI, J.

Ssk.

P.D. Order in W.P.No.3447 of 2021

Delivered on 24.3.2021.

https://www.mhc.tn.gov.in/judis/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter