Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Concrete Products & ... vs Union Of India
2021 Latest Caselaw 23838 Mad

Citation : 2021 Latest Caselaw 23838 Mad
Judgement Date : 6 December, 2021

Madras High Court
M/S.Concrete Products & ... vs Union Of India on 6 December, 2021
                                                                                     O.P.No.185 of 2015


                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                             DATE D        :   06.12.2021

                                                    CORAM:

                         The Hon'ble Mr. Justice SENTHILKUMAR RAMAMOORTHY

                                                 O.P.No.185 of 2015
                                                        and
                                        Application Nos.2120 to 2123 of 2015


                M/s.Concrete Products & Construction Company
                Rep. by its Joint Managing Partner
                No.398, Poonamallee High Road,
                Kilpauk, Chennai – 600 010.                                 ... Petitioner

                                                      Vs

                1.Union of India
                  Owning Southern Railway,
                  Rep. by the Principal Chief Engineer,
                  Headquarters Office,
                  Works Branch, Chennai – 600 003.

                2.Mr.R.K.Dash
                  Chief Materials Manager/SGT,
                  East Coast Railway,
                  Rail Sadan, Chandrasekharpur,
                  Bhubaneswar,
                  Odissa – 751017.                                          ... Respondents




                _____________
https://www.mhc.tn.gov.in/judis
                Page No.1 of 18
                                                                                         O.P.No.185 of 2015


                PRAYER : This Petition has been filed under Section 34 of the Arbitration

                and Conciliation Act 1996 praying to set aside the Arbitration Award dated

                03.03.2014 passed by the second Respondent in the dispute between the

                Petitioner and the first Respondent.

                                            For Petitioner : Mr.Abishek Jenasenan
                                                             for Mr.A.Jenasenan

                                           For Respondents : Mr.C.V.Ramachandramurthy


                                                      ORDER

The claimant before the Arbitral Tribunal is the Petitioner herein.

An Arbitral Award dated 03.03.2014 (the Award) is assailed.

2. An agreement was entered into between the Respondents and

the Petitioner for supply of 2,94,400 numbers of pre-stressed mono block

concrete sleepers (PSC Sleepers) at a price of Rs.1194/- per unit exclusive

of taxes and with price variation. The original delivery period was two

years and 37 days, i.e. from 19.11.2009 to 25.12.2011 with a permissible

variation of + or – six months as regards time and + or – 30% as regards

quantity. According to the Petitioner, as regards the Ambattur Concrete

Sleepers Plant (the ABU Plant), the original monthly target was fixed at

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.185 of 2015

10,000 numbers. Such monthly target was reduced from time to time. For

instance, the Petitioner asserts that the monthly target was reduced to 3000

numbers by communication dated 26.07.2011 from the Respondents and to

nil by communication dated 10.11.2011. Consequently, it is contended that

it was not possible to meet the over all delivery schedule. In such

circumstances, a request was made to the Respondents to consent to the

assignment of the contract to a sister concern of the Petitioner. Such

request was declined. The Respondents, however, by communication of

03.02.2012, agreed to reduce the total quantity by 30%. Eventually, by

communication dated 02.11.2012, the Respondents terminated the contract

with effect from 20.10.2012 and proceeded to initiate action for the

forfeiture of the security deposit and for the imposition of liquidated

damages at 5% on the value of unsupplied and undelivered sleepers. The

Petitioner herein initiated arbitral proceedings in the above facts and

circumstances.

3. The Petitioner claimed a sum of Rs.4,49,90,340/- along with

interest thereon amounting to Rs.55,61,514/- up to 31.01.2013 by relying

upon Sections 15 to 17 of the Micro, Small and Medium Enterprises

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.185 of 2015

Development Act, 2006(the MSMED Act). In addition, the following relief

was prayed for: a declaration that the termination of the contract is void; for

refund of the security deposit of Rs.20,00,000/- with interest thereon at

18% per annum; a perpetual injunction restraining the Respondents from

recovering liquidated damages of Rs.71,42,445/- ; and refund of a sum of

Rs.16,84,809/- towards excess land licence fee collected by the

Respondents from the Petitioner.

4. The Respondents herein filed a counter along with a counter

claim. By way of such counter claim, forfeiture of the security deposit of

Rs.20,00,000/-; recovery of liquidated damages of Rs.68,16,977/-; and

arbitration costs were prayed for. By the Award, the Arbitral Tribunal

directed the Respondents to make the payment of Rs.4,49,90,340/- within a

period of 30 days. In the event of default, simple interest at 7% per annum

was directed to be paid. As regards termination, the Arbitral Tribunal

concluded that termination may be done only for the unsupplied quantity.

The forfeiture of the security deposit was upheld. As regards the claim for

liquidated damages, the Arbitral Tribunal concluded that liquidated

damages could be levied for delayed supply of supplied quantities, but not

for unsupplied quantities.

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.185 of 2015

5. The Petitioner assails the Award only insofar as it pertains to

the refusal to award interest as per the MSMED Act, the award of liquidated

damages as regards delayed supply of supplied quantities and the forfeiture

of the security deposit.

6. The refusal to grant interest at the rates specified in the

MSMED Act is assailed on the ground that the MSMED Act confers rights

on any enterprise which is registered under the said enactment to claim

interest at the rates specified therein if payments are not made within 45

days as specified therein. By drawing reference to Section 16 of the

MSMED Act, the Petitioner contends that the said provision opens with a

non-obstante clause and overrides contractual stipulations to the contrary.

By adverting to internal pages 10 and 11 of the Award, the Petitioner

contends that the sole reason assigned by the Arbitral Tribunal for rejecting

the claim for interest is that the relevant contract does not draw reference to

Sections 15 to 17 of the MSMED Act. According to the Petitioner, the said

conclusion is patently illegal. In addition, the Petitioner contends that such

conclusion is contrary to public policy inasmuch as the MSMED Act was

enacted to confer special benefits on MSMEs.

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.185 of 2015

7. As regards the award of liquidated damages, the Petitioner

contends that the counter claim of the Respondents was for recovery of

liquidated damages at 5% of the unsupplied quantity. Such claim was made

for a sum of Rs.68,16,977/-. The Arbitral Tribunal, at internal page 87,

rejected the claim for liquidated damages with regard to unsupplied

quantities by concluding that it would amount to a double penalty in view

of the termination of the contract. However, the Petitioner contends that the

Arbitral Tribunal committed a grave error in awarding liquidated damages

for the alleged belated supply of 25,945 numbers of PSC Sleepers. With

regard to the forfeiture of the security deposit, the Petitioner reiterates that

the Respondents did not plead or establish loss. The Petitioner also

contends that the principles pertaining to liquidated damages would apply

equally to the forfeiture of the security deposit. Therefore, the Petitioner

contends that the Award as regards forfeiture of security deposit is

unsustainable.

8. On this issue, the Petitioner relies upon the judgment of the

Hon'ble Supreme Court in Kailash Nath Associates v. DDA (2015) 4 SCC

136 (Kailash Nath) to the effect that even with regard to a claim for

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.185 of 2015

liquidated damages, it is necessary to establish the factum of loss and prove

loss unless such loss is established to be impossible or difficult to prove. In

the case at hand, the Petitioner contends that the Respondents did not plead

that the loss was impossible or even difficult to prove. Indeed, it is

submitted that even the factum of loss was not pleaded by the Respondents.

9. These contentions are refuted by the Respondents. By

referring to the written submissions, the Respondents contend that the bills

raised by the Petitioner could not be processed and paid on account of the

non-execution of a rider agreement to extend the terms of the agreement.

The next contention of the Respondents is that payment of interest is not

permissible in terms of IRS condition 2401. By relying upon IRS condition

2401, it is contended that the Respondents are entitled to and exercised a

lien over such amounts on account of the breach of contract by the

Petitioner and the amounts payable on such account to the Respondents.

10. With regard to the reliance on the MSMED Act, the

Respondents referred to earlier orders of this Court. By relying upon the

order in Union of India v. M/s.Nellai Concrete Products, O.P.No.1022 of

2017, it is contended that the MSMED Act and the provisions relating to

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.185 of 2015

interest as specified therein would apply only to a reference made before

the Facilitation Council constituted under the said Act. In addition, the

order of a learned Judge in O.P.Nos.143 and 525 of 2016, which was

affirmed in appeal by the Division Bench, is also relied upon.

11. By way of a short rejoinder, the Petitioner contends that the

delay in supply is irrelevant at this juncture. As regards the non-execution

of a rider agreement, the Petitioner points out that the Arbitral Tribunal

considered the said contention and rejected the same on the ground that

payment cannot be denied for non-execution of a rider agreement. As

regards the judgments cited by the Respondents, the Petitioner contends

that the judgment in O.P.Nos.143 and 525 of 2016 pertained to a security

deposit and to the 75% pre-deposit requirement under the MSMED Act.

Therefore, the said judgment has no bearing on the question of payment of

interest for supply of goods or services.

12. In view of the Petitioner confining the challenge to three

aspects of the Award, only the said aspects need to be discussed herein.

With regard to the payment of interest on unpaid invoices, the factual

position, as on date, is that the Respondents have paid the Petitioner a sum

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.185 of 2015

of Rs.4,10,01,358/- on 31.07.2014 and a further sum of Rs.13,64,979/- on

04.08.2014. While making such payments, the Respondents levied and

recovered a sum of Rs.24,03,208/- towards liquidated damages in terms of

the Award. Thus, any interest claim would be from the date the relevant

invoices became due until the above dates of payment thereof. This issue

should be examined by bearing in mind the above factual context. The

Arbitral Tribunal considered the question of payment of interest and

rejected the claim on two grounds. First, at internal page 10 of the Award,

the Arbitral Tribunal extracted IRS 2401. IRS 2401 is as under:

''IRS 2401 states that ''Whenever any claim or claims for payment of a sum of money arises out of or under the contract against the Contractor, the purchaser shall be entitled to withhold and also have a lien to retain such sum or sums in whole or in part from the security, if any, deposited by the Contractor and for the purpose aforesaid, the purchaser shall be entitled to withhold the said cash security deposit or the security, if any, furnished as the case may be and also have a lien over the same pending finalisation or adjudication of any such claim. In the event of the security being insufficient to cover the claimed amount or amounts or

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.185 of 2015

if no security has been taken from the Contractor, the purchaser shall be entitled to withhold and have lien to retain to the extent of the such claimed amount or amounts referred to supra, from any sum of sums found payable or which at any time thereafter may become payable to the Contractor under the same contract or any other contract with the Purchaser or the Government pending finalisation or adjudication of any such claim.

It is an agreed term of the contract that the sum of money or moneys so withheld or retained under the lien referred to above, by the Purchaser will be kept withheld or retained as such by the Purchaser till the claim arising out of or under the contract is determined by the Arbitrator(if the contract is governed by the arbitration clause) or by the competent court as prescribed under clause 2703 hereinafter provided, as the case may be, and that contractor will have no claim for interest or damages whatsoever on any account in respect of such withholding or retention under the lien referred to supra and duly notified as such to the Contractor.'' (emphasis added).

13. On perusal of IRS 2401, it is evident that a lien may be

exercised provided the exercise of lien is duly notified to the contractor.

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.185 of 2015

From the documentary evidence placed before the Arbitral Tribunal, it

appears that no such notification was made by the Respondents to the

Petitioner. This aspect was not discussed by the Arbitral Tribunal.

Secondly, the Arbitral Tribunal noticed that the relevant contract does not

refer to the MSMED Act, and, on such basis, a conclusion was drawn that

the MSMED Act is not applicable to the contract. Given the fact that the

MSMED Act is a statute, it is not necessary for such statute to be

incorporated by reference into the contract between the parties. While

there could be other reasons for not applying the MSMED Act to the

present dispute, the Arbitral Award does not discuss anything other than the

non-citing of the provisions of the MSMED Act in the relevant contract.

Therefore, the conclusion on this aspect is not sustainable and is liable to be

interfered with. A claim for interest is grounded in facts inasmuch as the

said claim would run from the date the relevant amount became payable and

extend up to the date when payment was made. Therefore, if a claim for

interest is to be made by the Petitioner herein, such claim would have to be

made in de novo proceedings for such purpose.

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.185 of 2015

14. Turning to the question of the grant of liquidated damages, a

claim for damages involves four elements: a breach of contract; the

occurrence of loss; the causal link between the breach and such loss; and

proof of the quantum of loss. In the context of liquidated damages, a minor

qualification is made with regard to proof of quantum of loss. Starting with

the judgment in Maula Bux v. Union of India, (1969) 2 SCC 554 and,

thereafter, in the more recent judgment in Kailash Nath, the Hon'ble

Supreme Court concluded that the person claiming liquidated damages

should discharge the burden of either proving actual loss or establishing

that such loss is impossible or difficult to prove given the nature of the

contract. After considering the line of judgments on this issue, in 3i

Infotech Limited v. Tamil Nadu e-Government Agency and another 2020 (4)

CTC 673, I had formulated the applicable principles in this regard in

paragraph 23, which reads as under:

'' 23.The following principles emerge upon consideration of the judgments on liquidated damages and penalty and from the foregoing analysis:

(i) Section 74 of the Contract Act provides for two categories of stipulated payments for breach: (a) a sum named in the contract as the amount to be paid in case of breach, which

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.185 of 2015

could be called stipulated compensation; and (b) stipulations by way of penalty.

(ii) The principal difference between English law and Indian law, in this regard, is that a stipulation by way of penalty is unenforceable under English law whereas it is enforceable under Indian law.

(iii) In both categories of stipulated payments under section 74, the sum stipulated operates as the maximum amount or ceiling. In this respect also, the two categories are similar.

(iv) The term or label used, namely, liquidated damages, penalty or even price reduction, in the relevant clause, is not conclusive or determinative. However, it cannot be disregarded and the person contending that the label or term used is not the correct term would be required to discharge the burden of establishing the said assertion.

(v) The primary test for identifying and distinguishing between liquidated damages and penalty clauses is whether, when tested as of contract formation, the stipulated sum bears a reasonable correlation to anticipated loss; if so, it would be construed as a liquidated damages clause and, if not, as a penalty clause. A stipulated sum that bears such reasonable correlation to anticipated loss is considered as a genuine pre- estimate of loss.

(vi) As regards enforcement, the two categories are treated differently. In case the court concludes that the stipulated payment is a genuine pre-estimate of anticipated loss in case of breach, the sum stipulated would be ordered to be paid if the court also concludes that it is difficult or impossible to prove loss in the facts and circumstances. Such pre-estimate is to be made at

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.185 of 2015

the time of contract formation although evidence thereof may be adduced when there is a dispute.

(vii) Even if the court concludes that the stipulated compensation is a genuine pre-estimate of loss, the party claiming such compensation is required to prove that loss was incurred as a consequence of breach and what is dispensed with is the obligation to prove the loss accurately by also proving quantum of loss as per the claim. To put it differently, even in such a situation, a claim cannot be sustained in an injuria sine damnum scenario.

(viii) If it is not difficult or impossible to prove loss, the person claiming liquidated damages is required to prove loss, including the quantum of loss, even if the sum stipulated is a genuine pre-estimate and, therefore, qualifies as a claim for liquidated damages. In contrast with the contract formation stage evidence with regard to genuine pre-estimate, needless to say, actual loss would be required to be proved with reference to the breach and the direct consequences flowing therefrom.

(ix) Given the fact that a party claiming liquidated damages cannot claim more than the stipulated sum, once such party establishes that the stipulated compensation is a genuine pre-estimate, a high standard of proof would not be insisted upon to prove difficulty or impossibility of proving loss. In other words, the court would bear in mind that parties negotiated and concluded the contract on the basis of risk allocation, whereby the party claiming liquidated damages forecloses the possibility of claiming an amount higher than the sum stipulated, by way of proving higher actual loss, so as to enjoy the benefit of the relative ease and certainty of establishing a claim for liquidated

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.185 of 2015

damages as opposed to a claim for unliquidated damages.

(x) On the contrary, if it is concluded that the stipulation is by way of penalty, the person claiming such penalty would be required to prove loss accurately, including the quantum of loss, and claim reasonable compensation on that basis.''

15. The Respondents herein did not plead that they suffered loss

in their counter statement cum counter claim before the Arbitral Tribunal,

and no evidence of loss was adduced. Needless to say, the Respondents did

not plead that the loss was impossible or difficult to prove in light of the

nature of the contract.

16. The conclusions of the Arbitral Tribunal should be examined

in the above factual context. At internal page 12 of the Award, the Arbitral

Tribunal recorded its conclusion that liquidated damages are leviable for

25,945 numbers of PSC Sleepers, which were supplied belatedly. Before

arriving at such conclusion, in a table at paragraph 3 of the Award, the

Arbitral Tribunal set out the dates of supply of specific quantities and held

that liquidated damages are applicable for the quantity supplied belatedly.

There is no consideration of the question whether the Respondents suffered

loss as a result of belated supply and, most certainly, no discussion or

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.185 of 2015

conclusion with regard to the quantum of loss and the proof thereof in the

Award. Thus, the award of liquidated damages is completely unsustainable

in light of the law laid down in such regard. The Hon'ble Supreme Court

held in Fateh Chand v. Balkishan Das, AIR 1963 SC 1405, that forfeiture of

any amount deposited under the contract should satisfy the requirements of

Section 74 of the Indian Contract Act, 1872. Except for recording that the

supply was belated and drawing reference to paragraph 0504 of IRS

condition and Clause 8.4 of the contract, the Award contains no discussion

on loss in the context of forfeiture of security deposit too. These

conclusions qualify as being patently illegal. Consequently, the Award

merits interference under Section 34 of the Arbitration and Conciliation

Act, 1996.

17. The settled legal position is that an Arbitral Award can be

severed and upheld in part while being set aside in part. However, such

Award cannot be modified under Section 34.

18. For reasons set out above, O.P.No.185 of 2021 is allowed by

setting aside the Award as regards the refusal to grant interest as per the

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.185 of 2015

MSMED Act and as regards the grant of liquidated damages and forfeiture

of security deposit. However, it is made clear that nothing in this order

should be construed as a finding that the Petitioner is entitled to interest as

per the MSMED Act. As a corollary, it is open to the Petitioner to institute

de novo arbitral proceedings in such regard in accordance with the relevant

contract. If such proceedings are instituted, the Petitioner shall be entitled

to the benefit of Section 43(4) of the Arbitration and Conciliation Act,

1996. Consequently, connected applications are closed.



                                                                                   06.12.2021

                Index    :Yes
                Internet :Yes
                rrg




                _____________
https://www.mhc.tn.gov.in/judis

                                                         O.P.No.185 of 2015


                                   SENTHILKUMAR RAMAMOORTHY J.,

                                                                     rrg




                                                  O.P.No.185 of 2015




                                                         06.12.2021




                _____________
https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter