Citation : 2021 Latest Caselaw 6246 MP
Judgement Date : 30 September, 2021
THE HIGH COURT OF MADHYA PRADESH
W.P No. 6507/2020
(U.P State Bridge Corporation Limited Vs. The State of M.P &others)
JABALPUR, DATED: 30.09.2021
Shri Anshuman Singh, learned counsel for the petitioner.
Shri Purushaindra Kaurav, learned Advocate General with Shri Swapnil
Ganguly, learned Deputy Advocate General for the respondent/State.
Shri Shekhar Sharma, learned counsel for the respondent no.3.
This petition has been filed by petitioner-U.P State Bridge Corporation
Limited, a public sector undertaking challenging the communication dated
06/03/2020 and tender summary report dated 11/03/2020, with the prayer that
the respondent no.1 and 2 be directed to consider the financial bid of the
petitioner and not to treat the petitioner as disqualified.
2. Shri Anshuman Singh, learned counsel for the petitioner submitted that
an accident happened during the construction of bridge by the petitioner at
Varansi on 15th May, 2018 and FIR was registered under sections, 304, 308,
427, read with section 34 of the I.P.C and section 3/4 of Prevention of Damage
to Public Property Act, 1984 was lodged against some of the employees of the
petitioner and the contractor undertaking the said construction. The
investigation in that was ordered to be stayed by Allahabad High Court vide
order dated 30th July, 2019. Sometime thereafter, an NIT was issued by the
respondents on 30th November, 2019 for construction of elevated corridor
(flyover) from Damoh Naka to Ranital Chowk Madan Mahal Chowk (upto
medical Road) in Jabalpur city in Madhya Pradesh, with 16/01/2020 as last date of submission of the tenders. The respondent no.1 and 2 issued a letter dated
25/02/2020 stating that petitioner did not qualify threshold technical capacity as
per Clause 2.2.2(i) and 2.2.6(ii). The petitioner gave response to that on
26/02/2020 stating that all necessary details are present in the bid submitted by
the petitioner, therefore he is fully qualified. The General Manager of the
petitioner personally attended the office of respondent no.2 on 27/02/2020 and
explained all the details already submitted with the bid. The respondent no.2
issued letter dated 04/03/2020 alleging that the information required to be given
by the petitioner in Clause 7(a) and (b) of Annexure 1 of Appendix 1A was
incorrect as it did not disclose about the above criminal case. The petitioner on
the same day itself refuted the aforesaid allegation. Yet the respondent no.2
issued impugned communication dated 06/03/2021 declaring bid of the
petitioner as non responsive. The petitioner in response to the aforesaid letter
issued letter dated 07/03/2021 wrote back that the communication dated
06/03/2021 was completely arbitrary and illegal and the petitioner's bid cannot
be said to be non-responsive and he cannot be disqualified. Thereafter, in the
meantime the respondent no.1 and 2 uploaded a tender summery report on
11/03/2020 on the official website of the Government of Madhya Pradesh, in
which the petitioner has been shown to be technically disqualified and
respondent no.3 and 4 are shown to be technically qualified.
3. Learned counsel for the petitioner submitted that eventually the work was
awarded to respondent no.3. The petitioner had to thereafter amend the writ
petition. He filed two IA. 5593/2020 and 6354/2020 alleging that as many as 6
FIR have been lodged against the respondent no.3, with far more severe
allegations. It is contended that while in the case of the petitioner, the
respondents on similar ground have taken the view that the petitioner was
disqualified in some other contract of the respondent department. The petitioner
filed W.P No. 6681/2020 challenging the same which was allowed vide order
dated 15/06/2020 holding that the petitioner cannot be taken as disqualified. The
aforesaid judgment of the Indore Bench of this Court was challenged before the
Supreme Court in Civil Appeal No. 4002/2020. The Hon'ble Supreme Court has
reversed the judgment of this Court vide order dated 08/12/2020, upholding the
decision of the respondents to treat the petitioner disqualified.
4. Argument of learned counsel for the petitioner is that while in the case of
the petitioner there was one FIR and against the respondent no.3 as many as 6
FIR which have been brought on record vide IA No. 5593/2020 and IA no.
6354/2020, with regard to different cases with allegations of execution of sub
standard quality of work, offence under Prevention of Corruption Act and
collapse of bridge etc. Therefore the respondents ought to have not awarded
work to the respondent no.3. Action of the respondents is discriminatory being
violative of Article 14 of the Constitution. The respondent no.3 having
concealed all material from the respondent no.1 and 2 also ought not to have
been awarded the work. It is contended that in the agreement executed between
the parties as there is clause that even during the execution of the work, if it transpires that the bidder, who was awarded work, concealed some vital
information, the employer can take decision to terminate the work.
5. Shri Shekhar Sharma, learned counsel for the respondent no.3 submitted
that petitioner has not formally amended the writ petition to bring on record all
these alleged FIR said to be registered against the respondent no.3. It is
contended that not only letter of intent has been issued to the respondent no.3
but agreement was executed in favour of the respondent no.3 by respondent no.1
and 2 and he has started executing the work. The work has progressed.
6. Shri Purushaindra Kaurav, learned Advocate General for the
respondent/State submitted that as per his instructions, the total work of 183.4
crores, which constitute 16% of the total value, has been executed by the
petitioner. In the present facts of the case, because at the time of evaluation of
bid neither these allegations were brought to the notice of the respondents either
by the petitioner nor were disclosed in the tender documents even by the
respondent no.3, therefore, at this stage it is difficult to accept that they are
factually correct. But he submitted that the respondents are open to consider the
objections of the petitioner only after they have verified it's correctness.
7. Having heard learned counsel for the parties and material available on
record and considering the fact that work has already been awarded and
executed thereafter to some extent, we do not wish to interfere in the matter.
However at the same time, we set the petitioner at liberty to approach the
respondent no.2 Chief Engineer, Public Works Department (Bridge
Construction), Bhopal, Government of Madhya Pradesh by means of
comprehensive complaint to place before him all the material he wants to cite in support of his arguments that the judgment of the Supreme Court, shall equally
apply to the respondent no.3, who (the respondent no.2) after giving opportunity
of hearing to both the petitioner and the respondent no.3 shall take final view in
the matter considering the relevant clause of the agreement executed between
the parties, within a period of 6 weeks from the date of receipt of such
complaint. It is made clear that we have not expressed any opinion on the merit
of the case.
With the aforesaid direction, the petition is disposed of.
(MOHAMMAD RAFIQ) (VIJAY KUMAR SHUKLA)
CHIEF JUSTICE JUDGE
Digitally signed
by tarun
TARUN
KUMAR SALUNKE
Date: 2021.10.01
10:38:51 +05'30'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!