Citation : 2021 Latest Caselaw 5570 MP
Judgement Date : 17 September, 2021
AC-96/2019
---1---
THE HIGH COURT OF JUDICATURE FOR MADHYA PRADESH
AT JABALPUR
(Single Bench)
Arbitration Case No.96/2019
Cobra-CIPL JV .... Petitioner
Vs.
Chief Project Manager, Railway Electrification, ....Respondent
Jabalpur
___________________________________________________________
Presence:
Shri Kapil Arora, learned Counsel with Shri Shashank Verma and Shri
Mallikarjun Khare, learned counsel for the petitioner.
Shri Atul Choudhary, learned counsel for the respondent.
_______________________________________________________
Heard on: 03.09.2021
_______________________________________________________
ORDER
(Passed on this 17th day of September, 2021)
This order will dispose of the application filed by petitioner Cobra-
CIPL JV, a joint venture established by M/s Cobra Instalaciones Y
Servicios, S.A. and Cobra Instalaciones Y Servicios India Pvt. Ltd. under
Section 11(4) of the Arbitration and Conciliation Act, 1996 (for short "the
Arbitration Act") praying for a direction to appoint the Sole Arbitrator for
resolving the dispute between the petitioner and the respondent.
2. The facts of the case are that the Central Organization for Railway
Electrification, Allahabad (for short "CORE") through the Chief Electrical
Engineer floated a tender in March, 2013 for composite electrical works,
design, supply, erection, testing and commissioning of 25 KV, 50 Hz, AC
single phase electrification works including OHE, TSS and SCADA
works in Satna (Excl.)-Jabalpur (Excl.) Section, Group (Gr.) 174 of AC-96/2019
---2---
Jabalpur Division of West Central Railway under RE project Jabalpur.
The petitioner in response to the aforesaid tender submitted its offer on
22.05.2013 and thereafter submitted negotiated offer on 10.03.2014,
which was accepted by the respondent vide letter of acceptance dated
21.03.2014. The letter of acceptance dated 21.03.2014 was issued by the
Chief Electrical Engineer, CORE, Allahabad vide Annexure A/3.
Consequently, a contract was entered into between the parties on
18.06.2014. Thereafter, on account of disputes having arisen between the
parties, the respondent terminated the contract on 12.02.2019. The
petitioner served a notice on the respondent on 06.08.2019 invoking
arbitration clause 1.2.54 of the contract. The respondent in turn wrote to
the petitioner seeking its consent to waive off the applicability of Section
12(5) of the Arbitration Act. Thereafter, the respondent issued a letter on
25.09.2019 proposing names of four retired Railway Officers and asking
the petitioner to select any two out of the four names so proposed.
According to the petitioner, this was contrary to the terms of the contract
which provides for appointment of serving Railway Officers as
Arbitrators and not retired once. Since the respondent failed to nominate
its Arbitrator within 30 days from the date of notice given by the
petitioner, the petitioner filed the present application on 4.10.2019. While
the respondent put in appearance before this Court on 01.11.2019 but
despite pendency of the present application, the General Manager of
CORE unilaterally appointed an Arbitral Tribunal comprising retired
Railway Officers.
3. Shri Kapil Arora, learned counsel for the petitioner submitted that AC-96/2019
---3---
the respondent have wrongly raised the preliminary objection about
territorial jurisdiction of this Court. It is not correct to contend that the
jurisdiction to file the application would lie only with the Courts at
Allahabad. The respondent has not even remotely alleged in the reply that
the parties had agreed in the agreement or otherwise that the seat of
arbitration shall be only at Allahabad. It is contended that the Allahabad
was only the place from where letter of acceptance was issued. In terms of
Clause 15 of the contract, it is clear that subsequent to award of the
contract, there is no role of the Allahabad office of the respondent. The
aforesaid clause also clarified that prior to award of the contract, any
correspondence and documents in relation to contractual and commercial
matters were required to be sent to the Chief Electrical Engineer, Railway
Electrification, Allahabad. However, subsequent to award of the contract,
all such correspondence and documents in relation to contractual and
commercial matters and also the correspondence and documents in
relation to design, working and drawing as well as field work, scheduling
of quantifies and submission of bills had to be addressed to the Chief
Project Manager, Railway Electrification, Jabalpur. It is clear that in terms
of Clause 15 of the contract, for all purposes arising out of the contract
subsequent to award of the contract, the relevant authority was the Chief
Project Manager, Railway Electrification, Jabalpur and therefore, the
Chief Project Manager, Railway Electrification, Allahabad had no
authority in the matter.
4. Referring to Clause 1.2.54 of the contract, Shri Kapil Arora, learned
counsel argued that Clause 1.2.54(k) has clearly provided that the venue AC-96/2019
---4---
for an arbitration to be the place from where the letter of acceptance of
tender is issued or such other place as the purchaser at his discretion may
determine. In respect of similar project i.e. tender for composite electrical
works, design, supply, erection, testing and commissioning of 25 KV, 50
Hz, AC single phase overhead equipment including TSS and SCADA
works in Manikpur (Excl)-Satna (Incl) and Satna to Rewa Section, Gr.
173-B of Jabalpur Division of West Central Railway under RE Project
Jabalpur, similar disputes had arisen between parties. This Court vide
order dated 4.2.2019 in A.C No.107/2017-Cobra CIPL Vs. Chief Project
Manager while allowing the application appointed Mr. Justice (Retd.)
D.M.Dharmadhikari, former Judge of the Supreme Court as the Sole
Arbitrator. It is argued that the arbitration clause in the aforesaid matter
was exactly similar to the arbitration clause in the present matter. This
Court in the aforesaid case has categorically held that this Court will have
jurisdiction to appoint arbitrator under Section 11 of the Arbitration Act
on the basis that the word 'venue' used in the arbitration clause referred
only to the venue for conducting arbitration proceedings and the same
cannot be construed as or equated with, 'seat' of the arbitration
proceedings. This Court in the aforesaid case held that the definition of
'venue' did not fulfill the requirement to be 'seat: as set forth in Indus
Mobile Distribution Pvt. Ltd. Vs. Datawind Innovations Pvt. Ltd. and
others (2017) 7 SCC 678.
5. The learned counsel argued that the respondent has heavily relied
on the judgment of the Supreme Court in Brahmani River Pellets Ltd.
Vs. Kamachi Industries Ltd. (2020) 5 SCC 462 to argue that this Court AC-96/2019
---5---
will not have territorial jurisdiction to entertain present application. It is
argued that the judgment in Brahmani River Pellets (supra) has been
passed relying on earlier judgment of the Supreme Court in Indus Mobile
(supra). The judgment of the Supreme Court in Indus Mobile (supra) was
also discussed and distinguished by this Court in the earlier case between
the present parties having the exactly similar arbitration clause. Moreover,
the arbitration clause in Brahmani River Pellets (supra) categorically
mentioned that the arbitration shall be under Indian Arbitration and
Conciliation Act, 1996 and venue of arbitration shall be Bhubaneshwar. A
comparison of the arbitration clause in the present matter and the
arbitration clause in the Brahmani River Pellets (supra) would clearly
bring it out that both are entirely different. Even in Indus Mobile (supra),
the agreement provided that all disputes and differences of any kind
whatever arising out of or in connection with the agreement shall be
subject to the exclusive jurisdiction of Courts of Mumbai only, which is
not the situation in the present case. It is argued that after Brahmani
River Pellets judgment, the Supreme Court has examined this issue in
BGS SGS Soma JV Vs. NHPC (2020) 4 SCC 234, which being later
judgment would prevail over the judgments in Brahmani River Pellets
(supra) and Indus Mobile (supra). It is judgment of three-judge Bench
whereas the judgment in Brahmani River Pellets (supra) was delivered
by a two-judge Bench. The arbitration clause in BGS Soma (supra) had
provided that the arbitration proceedings shall be held at New
Delhi/Faridabad, India and the language of the arbitration proceedings and
that of all documents and communications between the parties shall be
English. The learned counsel argued that the test for the seat of the AC-96/2019
---6---
arbitration proceedings in the Shashoua principle has to be applied before
determining the question of jurisdiction. Referring to para 61 of BGS
Soma judgment, learned counsel for the petitioner argued that wherever
there is an express designation of a venue and no designation of any
alternative place as the seat, combined with a supranational body of rules
governing the arbitration and no other significant contrary indicia, the
inexorable conclusion is that the stated venue is actually the jurisdictional
seat of the arbitral proceeding. It is argued that role and purpose of
Section 42 of the Arbitration Act is for determining the jurisdiction of the
Courts where seat is not identifiable from arbitration agreement entered
between the parties and multiple Courts may have jurisdiction because
cause of action arises at multiple places. The Supreme Court while
dealing with Section 20(1) and (2) of the Arbitration Act categorically
mentioned that if seat is not identifiable by bare reading of the contract,
then seat has to be determined by the Arbitral Tribunal under Section
20(2) of the Act and not by the Court. It is argued that for a venue to be
designated as seat, it must be discernible from the clause that the
arbitration proceedings as a whole are to be held at a particular place and
not one or more individual hearings.
6. Shri Kapil Arora, learned counsel has argued that the cause of
action in the present case arose within the territorial jurisdiction of this
Court, inter alia, for the reasons; (1) the tender was floated for composite
electrical works for design, supply, erection, testing and commissioning of
works in Satna-Jabalpur Section, Gr. 174 of Jabalpur Division of West
Central Railway under RE Project Jabalupr; (2) the entire works
pertaining to the contract were performed in Jabalpur and (3) the AC-96/2019
---7---
extension letters were also issued to the petitioner from the office of Chief
Project Director, Railway Electrification, Jabalpur. Moreover, the
petitioner in the present case filed a petition (MJC (AV)-11/2019) under
Section 9 of the Arbitration Act before the District Judge, District Court at
Jabalpur seeking injunction against invocation of bank guarantees. The
respondent did not however raise any objection in that matter to the
jurisdiction of Jabalpur District Court. The respondent filed an appeal
(AA No.91/2019) under Section 37 of the Arbitration Act before this
Court challenging the order dated 17.09.2019 passed by the District
Judge, District Court, Jabalpur in the aforementioned case under Section 9
of the Arbitration Case. The petitioner thereafter also filed an application
under Section 14 of the Arbitration Act before the Jabalpur District Court
challenging the constitution of the Arbitral Tribunal by the respondent.
Even during proceeding of that application, no objection with regard to
territorial jurisdiction was raised by the respondent. The District Court
passed an order dated 10.09.2020 on the aforesaid application. It is argued
that the judgment of the Supreme Court in Central Organization for
Railway Electrification Vs. ECI-SPIC-SMO-MCML, 2019 SCC
OnLine SC 1635 is distinguishable on facts. On the contrary, the Supreme
Court in the case of Union of India Vs. Tantia Constructions, wherein
the Calcutta High Court held that the General Manager of the respondent-
Railway could not appoint any existing Railway Officer as the Arbitrator,
upheld the said order while dismissing SLP No.12670/2020 on
11.01.2021, filed by the Railway.
7. Relying on the judgment of the Supreme Court in Bharat
Broadband Network Limited Vs. United Telecoms Limited, (2019) 5 AC-96/2019
---8---
SCC 755, leaned counsel for the petitioner argued that if a person
becomes ineligible to be appointed as Arbitrator vide Section 12(5) read
with Schedule VII of the Arbitration Act, then an Arbitrator appointed by
him is de jure ineligible and appointment of such Arbitrator is void ab
initio. Moreover, all the members of the Tribunal including the Presiding
Arbitrator were in the present case appointed unilaterally by the General
Manager, CORE without any involvement of the petitioner. Relying on
the judgment of the Supreme Court in TRF Limited Vs. Energo Engg
Project Limited (2017) 8 SCC 377, learned counsel argued that it was
held therein that once the Managing Director has become ineligible to act
as the Arbitrator by operation of law, he cannot nominate another
arbitrator. Aforesaid judgment of TRF Limited (supra) was followed in
Bharat Broadband Network Limited (supra). Since the General
Manager, CORE is the head/employee of the respondent, who is a party to
the dispute, his interest in the outcome of the present matter would only
be natural. Even if retired Railway Officers have been appointed as
Arbitrators, considering the fact that the General Manager became
ineligible, he could not have appointed them as members/presiding
member of the arbitral tribunal. It is argued that the unilateral constitution
of the Arbitral Tribunal by the respondent is in blatant violation of Section
11(6) of the Arbitration Act. Once when this Court was in seisin of the
matter, the respondents lost their right to appoint the arbitrator. The
respondent's right to issue a letter dated 19.11.2019 constituting the
Tribunal was extinguished upon expiry of the statutory period of 30 days
and especially after the present application was filed by the petitioner
before this Court. In support of this argument, learned counsel has relied AC-96/2019
---9---
on the judgments of the Supreme Court in Union of India Vs. Bharat
Battery Manufacturing Co. (P) Ltd. (2007) 7 SCC 684 and Dakshin
Shelters (P) Ltd. Vs. Geeta S.Johari (2012) 5 SCC 152.
8. Per contra, Shri Atul Choudhary, learned counsel for the respondent
argued that contract of the petitioner had to be terminated by the
respondent because it failed to complete the work as per the schedule of
work, which is evident from termination order dated 12.02.2019. The
petitioner submitted a legal notice dated 06.08.2019 invoking arbitration
clause in terms of Clause 1.2.54(b) of the contract, which required that all
such disputes must be referred to an Arbitral Tribunal. This notice was
addressed to the Chief Project Manager and not to the General Manager of
the Zonal Railways, Allahabad, which is requirement of arbitration clause
d(i) and (ii). As per this clause, the application had to be made to the
office of the General Manager, Allahabad and no notice has been filed
with the present application so as to indicate that any application was
made before the General Manager, Allahabad. It is submitted that the
appointment of the Arbitrator was made by the General Manager and it
was informed by e-mail as well as speed post, which was served well
before expiry of 30 days. The argument of the petitioner that the right of
the respondent to appoint Arbitral Tribunal is waived is liable to be
rejected. Learned counsel argued that in the present matter, the questions
which emerge for consideration are that; (1) whether "venue" synonyms
to word "seat"; (2) whether after the amendment of Section 12(5) of the
Arbitration Act, the respondent will have any right to constitute arbitration
tribunal as per procedure given in the agreement; (3) whether in this case
the tribunal was appointed by the respondent after the expiry of 30 days AC-96/2019
---10---
period from the date of receipt of notice and (4) whether the judgment
passed by this Court in earlier application of the petitioner
A.C.No.107/2017 is binding in the light of judgment of the Supreme
Court in Brahmani River Pellets's case (supra)?.
9. Learned counsel for the respondent argued about applicability of
Part 1 of the Arbitration Act to internationally seated arbitrations right
from Bhatia International Vs. Bulk Trading SA (2002) 4 SCC 105,
which was finally settled by the Supreme Court in Bharat Aluminium
Co. Vs. Kaiser Aluminium Technical Services Inc. (2012) 9 SCC 552, it
was held that the place of arbitration to be chosen on behalf of the parties
has to be designated in the arbitration agreement or the terms of the
reference, minutes of proceedings or in some other way as the place or
seat of the arbitration. It would be quite unusual for an Arbitral Tribunal to
hold the meetings in a place other than the designated place of arbitration
either for its own convenience or for the convenience of the parties or
their witnesses. Learned counsel submitted that in view of Section 20(1),
(2) and (3), the correct depiction of the practical consideration and the
distinction between 'seat' and 'venue' would be quite crucial in the event,
the arbitration agreement designates a foreign country as the seat/place of
the arbitration. Only if the agreement of the parties is construed for the
seat/place being in India, Part 1 of the Arbitration Act would be
applicable. If the agreement has provided for a seat/place outside India,
Part 1 would not be applicable to the extent inconsistent with the
arbitration law of the seat. The same principle of law has been laid down
by the Supreme Court in Brahmani River Pellets (supra), which has been
followed in subsequent judgment of Mankastu Impex Pvt. Ltd. Vs. AC-96/2019
---11---
Arivisual Ltd. (2020) 4 SCC 399, wherein the Supreme Court held that
when the seat is agreed by contracting parties to be outside India, in that
case the seat and venue are not synonymous and interchangeable, because
the laws of Hongkong are different than the laws which govern arbitration
in India.
10. Shri Atul Choudhary, learned counsel for the respondent argued that
earlier order passed by this Court in A.C.No.107/2017 was based on
wrong interpretation of the judgment in Bharat Aluminium Co. Vs.
Kaiser Aluminium Technical Services INC (2012) 9 SCC 552. The
findings recorded by this Court in para 13 and 14 of judgment in Cobra
CIPL Vs. Chief Project Manager reported in 2020(2) MPLJ 71 are
therefore liable to be declared per curiam. Aforesaid judgment of this
Court should be taken as impliedly overruled by the Supreme Court in
subsequent judgment of Brahmani River Pellets Ltd. (supra). It is
argued that after the judgment of the Supreme Court in BGS Soma
(supra), the choice of venue is choice of seat in the absence of any
contrary indicia. The Supreme Court in BGS Soma (supra) in para 61 of
the report held that whenever there is an express designation of a venue
and no designation of any alternative place as the seat combined with a
supranational body of rules governing the arbitration and no other
significant contrary indicia, the inexorable conclusion is that the stated
venue is actually the juridical seat of the arbitral proceedings.
11. Learned counsel argued that the Supreme Court in Mankastu
Impex Pvt. Ltd. Vs. Airvisual Ltd. 2020 5 SCC 399 was dealing with
the case where arbitration agreement did not use the words "seat" or
"venue". The arbitration agreement laid down that the arbitration would AC-96/2019
---12---
be administered in Hongkong and the place of arbitration was Hongkong.
The governing law was Indian law and the Courts of New Delhi shall
have jurisdiction. When the disputes arose, Mankastu approached the
Supreme Court for appointment of arbitrator contending that as Indian law
was the governing law and the courts at New Delhi had jurisdiction and
therefore New Delhi was the seat of arbitration. Reliance was placed on
the judgment of Supreme Court in Union of India Vs. Hardy
Exploration and Production (India) INC (2018) SCC Online SC 1640.
The Supreme Court arrived at its conclusion that Hong Kong was the seat
of arbitration. The Supreme Court instead of applying that ratio in Hardy
Exploration (supra) or BGS Soma (supra) employed a different method
of inquiry altogether. It is therefore argued that in cases where the venue
is described in agreement then it will mean that the venue and seat are
same and both are interchangeable. The finding recorded by the leaned
Single Bench in earlier application filed by the petitioner is thus contrary
to the law laid down by the Supreme Court in Brahmani River Pellets
(supra).
12. Shri Atul Choudhary, learned counsel for the respondent argued that
in Union of India Vs. Pradeep Vinod Construction Company, 2020 14
SCC 712, the Supreme Court relying on the earlier judgment in Union of
India vs Parmar Construction Co. (2019) 15 SCC 682 held that the
Court should depart from the agreement procedure for appointment of
arbitrator, only where exceptional reasons exit. Clause 64 of the General
Condition of the Contract in that case is pari materia to the arbitration
clause in the present case which also similarly provided for appointment
of serving railway officers as the arbitrators. The Supreme Court in above AC-96/2019
---13---
case set aside the appointment of the independent arbitrators and directed
the General Manager of the Railways to appoint arbitrator in terms of
Clause 64(3). In that case, the Supreme Court held that the appointment of
an employee as arbitrator cannot be assailed merely because he is a retired
employee of the parties.
13. Learned counsel for the respondent further submitted that the
contention of the petitioner that respondent's right to appoint the arbitrator
was forfeited because they failed to act within 30 days from the date of
receipt of the notice, is factually incorrect. The present application which
was submitted by the petitioner as Annexure A/14 clearly shows that the
application invoking arbitration clause was submitted by the petitioner to
the Chief Project Manager on 06.08.2019 and not to the General Manager.
Therefore, the period of 30 days' as per Section 11(5) of the Arbitration
Act cannot be counted from the date mentioned in the application
submitted before incompetent authority. Then the petitioner submitted a
fresh application on 26.08.2019 and on that basis, a panel of arbitrators
was sent to the petitioner on 25.09.2019 (Annexure R/1) within 30 days
from the date of service of notice. Instead of submitting the response to
the said panel, the petitioner straightaway approached this Court by filing
present application. It is therefore prayed that the application be
dismissed.
14. I have given my anxious consideration to the rival submissions and
perused the record.
15. This Court in earlier application filed by the petitioner having
dispute with the respondent herein, albeit, in the context of another
agreement having similar arbitration clause in Arbitration Case AC-96/2019
---14---
No.107/2017 decided vide judgment dated 04.02.2019 also considered the
same objection regarding lack of territorial jurisdiction which is being
again agitated by the respondent in the present case. The Clause 1.2.54(k)
which is the bone of the contention between the parties in the present
case, was exactly similarly worded in that case as well, which reads as
under:-
"(k) VENUE- the Venue for an arbitration shall be the place from which the letter of acceptance of tender is issued or such other place as the purchaser at his discretion may determine." (Emphasis supplied)
In that case the "letter of acceptance" was issued from Allahabad
but neither "seat" nor "place" of arbitration was indicated in the
agreement. The question was whether "venue" will determine the
jurisdiction of this Court and whether "venue" and "seat" are
synonymous.
16. Relying on the Constitution Bench judgment of the Supreme Court
in BALCO (supra), it was held that since the parties have not mandated
out any clause prescribing the seat of arbitration, it can be safely
concluded that they intended to give jurisdiction to two Courts which
would also include the court having jurisdiction based upon the cause of
action. Since except letter of acceptance from Allahabad, all necessary
events had taken place within the territorial jurisdiction of this Court at
Jabalpur, therefore, mere use of the "venue" in the agreement cannot be
equated with "seat" and it cannot form basis for determining the question
of jurisdiction of this Court.
17. The only additional argument which the learned counsel for the
respondent has now sought to advance for persuading this Court to take a AC-96/2019
---15---
different view than the one taken in the earlier order dated 04.02.2019 is
that in Brahmani River Pellets (supra), the Supreme Court held that
parties are free to agree on the place of arbitration. Party autonomy can be
construed in the context of parties choosing a court which has jurisdiction
out of two or more competent courts having jurisdiction under Section
2(1)(e) of the Arbitration Act. It was held that when the parties, in the
facts of that case agreed to have "venue" of arbitration at Bhubaneswar,
the Madras High Court erred in assuming the jurisdiction under Section
11(6) of the Act, as per which, if the subject matter of the suit is situated
within the arbitral jurisdiction of two or more courts, the parties may
confine jurisdiction in one of the competent courts. For this purpose, the
provisions of Section 2(1)(e) of the Act have to be read in conjunction
with Section 20 of the Arbitration Act which gives recognition to the
autonomy of the parties as to the "place of arbitration". Obviously, unlike
in the present case, relevant clause of the observation in Brahmani River
Pellets (supra), Bhubaneshwar was indicated as the one venue of
arbitration. However, in the present case, this is not the position. Even in
Indus Mobile Distribution (P) Ltd. (supra), the judgment relied by the
Supreme Court in Brahmani River Pellets (supra), the relevant clause of
arbitration provided that all disputes and differences of any kind whatever
arising of or in connection with the agreement shall be subject to
exclusive jurisdiction of courts at Mumbai only. Even that is not the
situation in the present case.
18. This issue in fact has been clarified in later three-judge Bench
judgment of the Supreme Court in BGS SGS Soma JV (supra) on
analysis of Constitution Bench judgment in BALCO (supra) holding that AC-96/2019
---16---
juridical or legal seat of arbitration once designated or determined,
exclusively determines which courts will have jurisdiction over the
arbitration, as opposed to the place where all or part of the cause of action
arises. Once the seat of arbitration is designated or determined, the same
operates as an exclusive jurisdiction clause as a result of which only the
courts where the seat is located would have the jurisdiction over the
arbitration to the exclusion of all other courts, even courts where part of
cause of action may have arisen. However, where it is found on facts of
the very case that either no "seat" is designated by agreement or has not
been so determined by the arbitral tribunal or the so-called "seat" is only a
convenient "venue", then there may be several courts where a part of
cause of action arises, that may have jurisdiction over arbitration. It was
held that an application under Section 9 of the Arbitration Act, in such a
situation, may be preferred before a court in which part of the cause of
action arises in a case where the parties have not agreed on the "seat" of
arbitration and before such a "seat" may have been determined, on the
facts of the particular case by the arbitral tribunal under Section 20(2) of
the Arbitration Act. The Supreme Court held that test for determination of
juridical seat wherever there is an express designation of a "venue" and no
designation any alternative place as the "seat" under Indian law as laid
down by the Constitution Bench of the Supreme Court in BALCO(supra)
is the Shashoua principle as laid down in Shashoua, 2009 EWHC 957
(Comm).
19. The Supreme Court in Central Organisation for Railway
Electrification (supra) was dealing with the case where as per the
agreement procedure, the contractor was to suggest to General Manager at AC-96/2019
---17---
least two names out of the panel of four names sent by the Department,
for appointment as his nominee and the General Manager had to appoint
at least one out of them to three-member arbitral tribunal as his nominee.
It was held that since the contractor had been given the power to select
two names out of panel of four retired railway officers, at least one of
them has to be appointed as one of three arbitrators by the General
Manager as per the agreed procedure. It was held that the right of General
Manager, who is himself ineligible to act as arbitrator, in formation of the
arbitral tribunal was counterbalanced by the respondent's above said
power to choose any two from out of the four names. In that case also
panel of the arbitrators consisted of retired Railway employees who have
worked with the Railways and it was held that this did not make him
eligible to act as arbitrator.
20. The Supreme Court in Union of India vs. M/s Tantia
Constructions Limited in Special Leave to Appeal No.12670/2020 vide
order dated 11.01.2021 while disagreeing with the view taken in that case
observing that once appointing authority itself is incapacitated from
referring the matter to arbitration, it does not then follow that
notwithstanding this yet appointments may be valid depending on the
facts of the case. The aforesaid judgment, therefore, cannot help in any
manner in the present facts of the case. As to the relevance of Section 42
of the Arbitration Act, it was held that it is the seat of arbitration alone and
not the place where the cause of action arises wholly or partly, which
determines the jurisdiction of courts over the arbitration, when such seat is
found to be designated or determined. Section 42 is meant to avoid
conflicts in jurisdiction of courts by placing the supervisory jurisdiction AC-96/2019
---18---
over all arbitral proceedings in connection with the arbitration in one
court exclusively. Further, where it is found on the facts of a particular
case that either no "seat" is designated by agreement, or the so-called
"seat" is only a convenient "venue", then there may be several courts
where the part of the cause of action arises that may have jurisdiction and
application under Section 9 of the Act may be preferred in a case where
the parties have not agreed as regards the "seat" of arbitration and before
such "seat" may have been determined on the facts of a particular case by
the arbitral tribunal under Section 20(2).
21. Contention of the respondent that since the "venue" was clearly
defined in the agreement between the parties and, therefore, "letter of
acceptance" having been issued from Allahabad, "venue" in this context
should be taken as a "seat" of the arbitration and the court of Allahabad
would have only the jurisdiction if it cannot be that clause 1.2.54(k) while
providing that the "venue" for arbitration shall be the place from which
the "letter of acceptance" of tender is issued also alternatively provided
such other place as the purchaser at his discretion may determine. On a
pointed query by the court whether the respondent, independent of the
"letter of acceptance" ever separately conveyed to the petitioner in
response to its notices invoking the arbitration clause or otherwise in the
pleadings before this Court that they as purchasers in their discretion have
determined Allahabad as the "venue", the learned counsel for the
respondents was not in a position to dispute that no such option was ever
exercised. The clause of the arbitration in the arbitration case, apart from
the fact that it does not indicate "seat" of arbitration but has merely
mentioned "venue" has itself left the possibility of having more than one AC-96/2019
---19---
places as possible venue. Since the respondent failed to act in response to
notice of the petitioner served on them on 06.08.2019 invoking
arbitration clause followed by another notice dated 26.08.2019 and did not
act upon the said notices in accordance with the agreed procedure in the
agreement by proposing name of serving Railway Officers till the filing of
application on 04.10.2019 and rather offered the name of four retired
Railway Officers vide letter dated 25.09.2019, it would be deemed that
the respondents have failed to act according to the agreed procedure
thereby forfeiting their right to appoint arbitrators in terms of the Section
11(6) of the Arbitration Act. Moreover, the identical application between
the same parties in respect of the similar dispute having been already
allowed by this Court in view of Section 12(5) of the Act, when the
respondent-Railway have decided not to challenge any further, they
cannot be now allowed to proceed with the appointment of their own
employees as the arbitrators. The present application, therefore, deserves
to succeed and is allowed.
22. Resultantly, I deem it proper to provisionally appoint Hon'ble Shri
Justice D.M. Dharmadhikari, Former Judge of Supreme Court of India as
a Provisional Arbitrator in the present case. The Registry of this Court
shall seek his consent/willingness in terms of section 11(8) of the Act.
23. List the matter on 22.10.2021.
(Mohammad Rafiq) Chief Justice
C.
Digitally signed by CHRISTOPHER PHILIP Date: 2021.09.20 16:31:16 +05'30'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!