Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Rubber Board vs Teji Paul
2026 Latest Caselaw 2281 Ker

Citation : 2026 Latest Caselaw 2281 Ker
Judgement Date : 26 March, 2026

[Cites 2, Cited by 0]

Kerala High Court

The Rubber Board vs Teji Paul on 26 March, 2026

                                                          By the



                                                 2026:KER:26752
R.F.A. No. 500 of 2014
                                 -1-

              IN THE HIGH COURT OF KERALA AT ERNAKULAM

                               PRESENT

           THE HONOURABLE MR.JUSTICE MOHAMMED NIAS C.P.

 THURSDAY, THE 26TH DAY OF MARCH 2026 / 5TH CHAITHRA, 1948

                         RFA NO. 500 OF 2014

AGAINST THE JUDGMENT AND DECREE DATED 19.07.2013 IN O.S.
NO. 318/2011 ON THE FILES OF THE PRINCIPAL SUB JUDGE,
KOTTAYAM
APPELLANT/DEFENDANT:

              THE RUBBER BOARD,
              SUB JAIL ROAD, KOTTAYAM-686 009
              REPRESENTED BY ITS SECRETARY

              BY ADVS.
              SRI.V.ABRAHAM MARKOS
              SRI.ABRAHAM JOSEPH MARKOS
              SRI.ABRAHAM VARGHESE THARAKAN
              SRI.BINU MATHEW
              SRI.TOM THOMAS (KAKKUZHIYIL)



RESPONDENT/PLAINTIFF:

              TEJI PAUL,
              AGED 47 YEARS, S/O.PAUL,
              PUTHOOPARAMBIL HOUSE,
              NJEEZHOOR VILLAGE, THIRUVAMPADI P.O.,
              KOTTAYAM DISTRICT, PIN-686 504.

              ADV. NIREESH MATHEW

     THIS REGULAR FIRST APPEAL HAVING COME UP FOR HEARING
ON 26.03.2026, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
                                                                   By the



                                                          2026:KER:26752
R.F.A. No. 500 of 2014
                                     -2-



                       MOHAMMED NIAS C.P., J.
                ----------------------------------------------
                          R.F.A. No. 500 of 2014
                ----------------------------------------------
                Dated this the 26th day of March, 2026

                                JUDGMENT

The Rubber Board, the defendant in O.S. No. 318 of 2011

on the files of the Principal Sub Judge, Kottayam, a suit for

realisation of an amount of Rs. 2,71,869/- instituted by the

respondent herein, is the appellant.

2. The respondent/plaintiff and the defendant/appellant

had entered into a contract pursuant to a tender floated for the

construction of Labour Lines at the Rubber Research Institute of

India, Kottayam. On 04.03.2008, the plaintiff and the defendant

executed Ext. B3, under which the work had to be completed

within six months in accordance with the specification and

schedule appended to the agreement. The plaintiff alleges that the

work of the basement was completed before 15th October, 2008, and

he requested part payment in October itself. The defendant had By the

2026:KER:26752

paid an amount of Rs. 1,40,000/- on 02.09.2008, but the balance

amount of Rs. 1,38,447/- was paid only on 12.05.2009. The plaintiff

would allege that the delay in making payment had affected

further construction. It is also pleaded that after the

commencement of the work, the plaintiff was requested to

construct a side retention wall over and above the work allotted as

per Ext.B3 agreement, whereby the plaintiff was required to do the

work amounting to 476.18 m3 instead of 176 m3 as originally agreed

between the parties.

3. It is alleged that, though the plaintiff requested

enhancement of the rates based on the revision made by the PWD,

the defendant did not accept the same and instead issued Ext.A3

letter dated 06.07.2009 to restart the work. The plaintiff would

allege that during that period, bricks were not available for

construction, and therefore, the plaintiff couldn't restart the work

as required. The plaintiff then informed the defendant about his

inability to restart the work and expressed his willingness to take

the final measurements for the work already completed.

By the

2026:KER:26752

Accordingly, the defendant had taken the final measurements on

13.07.2009. The plaintiff further submits that thereafter, the

defendant, without inviting any tender, had entrusted the work to

a person by the name Reji T. Chacko. It is pleaded that the

defendant had enhanced the rates by giving undue favour to the

second contractor.

4. The plaintiff claimed an amount of Rs. 80,245.30/-

towards the work completed by him. He also claimed the return of

the security deposit to the tune of Rs.1,03,450/- and a further

amount of Rs.25,000/- towards the value of tools illegally detained

by the defendant. Thus, on the date of the suit, the plaintiff claimed

an amount of Rs. 2,51,030/- with further interest at the rate of 12%

per annum.

5. The defendant filed a written statement contending

that the plaintiff was awarded the work as per a work order dated

13.02.2008, calling upon him to execute an agreement within seven

days and directing him to start the work within two weeks and to

complete the same within six months thereof. It was stated that the By the

2026:KER:26752

plaintiff executed the agreement only on 04.03.2008, and the work

was started only on 01.06.2008. As per the agreement, the date of

completion of the work was 27.08.2008, but even the construction

of the foundation was completed only on 15.10.2008. It is admitted

by the defendant that during the progress of the work, an

additional quantity of work was also directed to be done at the

same rates and thus 476.18 m3 of random rubble masonry work had

to be carried out. It is submitted by the defendant that an amount

of Rs. 1,40,000/- was paid to the plaintiff on 02.09.2008, but after

the completion of the foundation work in October 2008, the

plaintiff did not go ahead with the construction. After repeated

requests, the defendant again paid an amount of Rs.1,40,000/-,

which was released on 09.02.2009 on condition that the plaintiff

would resume the work. But the plaintiff did not do so and issued a

letter dated 26.06.2009 seeking enhancement of the rates. By letter

dated 06.07.2009, the defendant gave an ultimatum to the plaintiff

to restart the work by 15.07.2009, making it clear that the

defendant would be forced to terminate the contract without By the

2026:KER:26752

further notice in the event of failure to act as demanded.

6. The plaintiff, vide letter dated 11.07.2009, informed the

defendant that he was not able to carry out the balance work and

requested to take the final measurements on 13.07.2009. The

defendant would allege breach on the part of the plaintiff for not

carrying out the work in terms of Ext.B3 agreement. However, it is

submitted that the final measurements taken by them were

accepted by the plaintiff. In the written statement, the plaintiff was

informed that an amount of Rs.39,120.99/- is due to the defendant.

However, there is no counterclaim as such that was raised by the

defendant. The allegation regarding the non-release of tools was

denied by the defendant. It is further contended that there is no

need for inviting a tender for awarding the balance work, as the

said work was awarded on the same rates and there was no change

of materials and quantity for the work.

7. The plaintiff was examined as PW1 and Exts.A1 to A16

and A17 series were marked. On the side of the defendant, DW1 was

examined, and Exts.B1 to B16 were marked.

By the

2026:KER:26752

8. The trial court found that even going by the case of the

defendant, the plaintiff was requested to do the excess work over

and above the work mentioned in Ext.B3 agreement. It was also

found that, contrary to the initial work of 176 m3, the plaintiff was

asked to do the additional work amounting to 476.18 m 3 without

any enhancement of the rates or increasing the time schedule. The

trial court, accordingly, found that the said circumstances led to

the non-completion of the entire work. Accordingly, the trial court

found that there was an abrupt escalation of the volume of work

within the time frame originally fixed, which was for a lesser

quantity of work and thus the contention of the defendant that

there is a delay on the part of the plaintiff in completing the work

as stipulated in Ext.B3 agreement was not accepted. For the same

reason, it was found that the alleged delay raised by the defendant

also cannot be accepted, despite the finding that the plaintiff had

not completed the work originally granted as per Ext.B3.

9. The trial court further found that the loss sustained by

the defendant was not substantiated by the pleadings or evidence.

By the

2026:KER:26752

It was also found that the defendant did not care to re-tender the

work and instead the same was assigned to Reji T. Chacko on the

reason that he had agreed to complete the work left behind

without any additional cost. This contention of the defendant was

also not accepted as the trial court found that the major portion of

the work relating to fixing of door frame and shutters, fixing of

window frame and shutters, earth work done with the help of JCB

and tippers and the balance earth leveling work, with a value of

Rs.3,55,006/- were excluded from the work assigned to Reji T.

Chacko. Thus, it was found that the contention of the defendant

was only to cover up the irregularity committed by them in

assigning the work without inviting a fresh tender.

10. Although in the Annexure to the written statement,

the defendant had computed the extra expenses incurred by them

in respect of the works shown as item Nos. 3 to 6, which were

excluded from the terms of contract with Reji T. Chacko, the said

contention was not accepted as it was the case of the defendant

that the remaining work was assigned to him without any extra By the

2026:KER:26752

cost. As regards the contention of the defendant for forfeiting the

security deposit and EMD, it was found by the trial court that the

defendant breached the provisions of Ext.B3 agreement by not re-

tendering the work in accordance with Ext.B3 agreement. In this

context, the specific contention of the defendant that they did not

re-tender the work because Reji T. Chacko had agreed to complete

the balance work at the same rates was considered, and it was

found that the defendant could not prove any loss due to the

default on the part of the plaintiff.

11. Under such circumstances, the trial court, relying on

the judgment of this Court in Abdulla v. State of Kerala [2001 (3)

KLT 903], which relied on the judgment of the Supreme Court in

Union of India v. Rampur Distillery & Chemicals Co. Ltd. [AIR

1973 SC 1098], found that the party complaining of breach must be

in a position to adduce evidence whereby the court can access

reasonable compensation. In the instant case, it was found that the

defendant could not prove that the alleged breach of contract on

the part of the plaintiff led to any legal injury. The defendant had By the

2026:KER:26752

no case that they had re-tendered the work and thereby sustained

a loss as a higher amount was to be incurred. Thus it was found

that there was no justification for the refusal on the part of the

defendant to release the security deposit and EMD to the tune of

Rs.1,03,450/- to the plaintiff.

12. The trial court also considered the fact that the

defendant had admitted in the written statement that the actual

value of the work done by the plaintiff was Rs. 6,65,473.30/-,

towards which only Rs.5,85,228/- was paid by the defendant.

Accordingly, it was found that the defendant is bound to pay an

amount of Rs. 80,245.30/- along with the security deposit and the

EMD amounting to Rs. 1,03,450/- with 12% interest from the total

amount of Rs.1,83,695.30/- from 13.07.2013, the date when joint

measurements were taken. Thus, adding the interest of Rs.

88,173.74/-, it was found that the aggregate amount to be paid was

Rs. 2,71,869/-. The plaintiff's claim for the value of the tools was

rejected. Accordingly, the suit was decreed directing the defendant

to pay an amount of Rs.2,71,869/- within thirty days, failing which By the

2026:KER:26752

the plaintiff was entitled to recover and realise the amount with

interest at the rate of 6% per annum from 19.07.2013 till

realisation.

13. The learned counsel for the appellant submits that the

respondent/plaintiff was liable to do the additional works in terms

of Clause 6 of Ext.B3 agreement at the same rates. It is also argued

that the appellant had suffered loss in finishing the work agreed

upon as per Ext.B3 and is therefore entitled to retain the security

deposit and EMD. It is also argued that Ext.A3 notice dated

06.07.2009 threatened the plaintiff with terminating the contract

and therefore, there was compliance with Clause 15 of Ext.B3

agreement.

14. The learned counsel for the respondent/plaintiff

would argue that even going by the case of the defendant, it cannot

be held that they had sustained any loss, as they contend that they

did not re-tender the balance work as the contractor had agreed to

do the balance work at the same rates. Since no injury has been

caused, there is no application under Section 74 of the Contract By the

2026:KER:26752

Act. As regards the work completed, there is no dispute; therefore,

the defendant cannot withhold the payment due to the plaintiff for

the work completed.

15. Having heard the learned counsel on either side and

after perusing the records, I am not inclined to interfere with the

judgment and decree in question for multiple reasons. There is no

dispute that, after the execution of Ext.B3 agreement, additional

works were directed by the defendant, despite which the time

prescribed for performance was not extended. As rightly found by

the trial court, the quantity of work done was increased nearly

three times without any corresponding increase in the time for

performing the contract.

16. It is also not disputed that the defendant did not

terminate the contract as envisaged in Clause 15 of Ext.B3

agreement, whereupon the defendant could forfeit the security

deposit. It is admitted that the balance work was done without any

re-tender and without assessing the cost of completing the work

that was left behind. There is no dispute on the actual amount of By the

2026:KER:26752

work done by the plaintiff, which was Rs. 6,65,473.30/-. For these

reasons, and in view of the non-compliance by the defendant with

the terms of Ext.B3 agreement and based on the specific plea that

the balance work was done at the same rates, in the absence of any

pleadings and evidence, the claim of the defendant that they had

sustained loss due to the breach on the part of the plaintiff cannot

be accepted.

17. The Court below has considered the terms of the

agreement and the entire facts and circumstances, and has

appreciated the evidence, both oral and documentary, in the

correct perspective while decreeing the suit. I do not find any error

of fact or law warranting interference with the judgment of the

trial court.

The appeal fails and is accordingly dismissed.

Sd/-

MOHAMMED NIAS C.P. JUDGE bpr

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter