Citation : 2025 Latest Caselaw 6443 Ker
Judgement Date : 29 May, 2025
WP(C) NO. 31130 OF 2024 1 2025:KER:38052
"C.R"
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE C. JAYACHANDRAN
THURSDAY, THE 29TH DAY OF MAY 2025 / 8TH JYAISHTA, 1947
WP(C) NO. 31130 OF 2024
PETITIONER:
THOMAS MATHAI,
AGED 81 YEARS
CHENGALATHU HOUSE, PATHANAMTHITTA P.O, PATHANAMTHITTA,
PIN - 689645
BY ADVS.
SRI.JACOB P.ALEX
SRI.JOSEPH P.ALEX
SHRI.MANU SANKAR P.
SHRI.AMAL AMIR ALI
RESPONDENTS:
1 STATE ENVIRONMENTAL IMPACT ASSESSMENT AUTHORITY
(SEIAA), KERALA,
REPRESENTED BY ITS MEMBER SECRETARY, DIRECTORATE OF
ENVIRONMENTAL AND CLIMATE CHANGE 4TH FLOOR, KSRTC BUS
TERMINAL, THAMPANOOR THIRUVANANTHAPURAM, KERALA,
PIN - 695001
2 DISTRICT GEOLOGIST,
PATHANAMTHITTA, DISTRICT OFFICE,DEPARTMENT OF MINING &
GEOLOGY, NEAR KENDRIYA VIDYALAYA,ADOOR P. O.
PATHANAMTHITTA, PIN - 691523
BY ADVS.
SRI.M.P.SREEKRISHNAN
SHRI.JOHNY K.GEORGE
SMT. ATHULYA MARTIN
SRI.AJITH VISWANATHAN
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
29.05.2025, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C) NO. 31130 OF 2024 2 2025:KER:38052
"C.R"
JUDGMENT
This judgment has to be read in continuation of,
and as a sequel to, the judgment in W.P.(C.)
No.8820/2023 dated 03.04.2024, produced at Ext.P15
herein.
2. Petitioner's application for issuance of
Environmental Clearance (E.C.) was originally rejected
by the 1st respondent State Environmental Impact
Assessment Authority (SEIAA) vide Exts.P4 and P13
Orders. Challenging the Orders, the petitioner
approached this Court. The challenge was upheld and
Exts.P4 and P13 decisions were set aside by this Court,
by virtue of Ext.P15 judgment. The 1st respondent herein
was directed to reconsider the petitioner's application
for issuance of E.C. (produced as Ext.P8 in that Writ
Petition). Exts.P4 and P13 decisions were frowned upon
by this Court in Ext.P15 judgment citing three specific
reasons, which are available in the penultimate
paragraph of Ext.P15. The first is that no reason, WP(C) NO. 31130 OF 2024 3 2025:KER:38052
whatsoever, is stated to take a view different from that
of the well considered recommendation of the expert
body, State Expert Appraisal Committee (SEAC). This
reason was stated in the light of the judgment of the
Hon'ble Supreme Court in Hanuman Laxman Aroskar v.
Union of India [(2019) 15 SCC 401], which underscored
the primacy of the recommendations made by the SEAC, and
its binding nature on SEIAA in normal circumstances. The
said judgment of the Hon'ble Supreme Court also held
that in case SEIAA is to overlook the recommendations
made by the expert body SEAC, they have to state reasons
and the matter will have to be sent back to SEAC for
reconsideration, which obviously was not reflected in
Exts.P4 and P13 decisions.
3. The second aspect which weighed with the learned
Single Judge is the finding of SEAC that no cluster is
formed in the petitioner's case and that, the judgment
of the National Green Tribunal (NGT) in Satendra Pandey
v. Ministry of Environment, Forest & Climate Change &
Another, (O.A.No.186 of 2016) has not invalidated WP(C) NO. 31130 OF 2024 4 2025:KER:38052
Appendix XI of E.I.A. notification. The learned Single
Judge found that this was also not properly considered
in Ext.P13 decision. A third aspect- described by the
learned Single Judge as a crucial aspect - is with
respect to the expiry of the lease mentioned in Ext.P2
certificate granted on 06.03.2012, by virtue of which,
the total extent is admittedly below 5 hectares,
wherefore a comprehensive E.C. for the entire 5 hectares
is impossible.
4. It is on the strength of these specific findings that
Exts.P4 and P13 decisions of the 1st respondent were set
aside by the learned Single Judge and directed
reconsideration of the same.
5. I am at loss to find that none of the above
parameters- specifically pointed out by this Court in
Ext.P15- were not referred, much less considered, by the
1st respondent in Ext.P17 Order, impugned herein. The
matter did not end there. The petitioner filed a review
petition vide Ext.P18, pointing out the above anomaly of WP(C) NO. 31130 OF 2024 5 2025:KER:38052
not referring to any of these parameters, besides
pointing out the recommendations of SEAC, which has to
be followed by SEIAA ordinarily, as held in Hanuman
Laxman Aroskar (supra). Ext.P18 also did not evoke any
response and the 1st respondent/SEIAA came up with
Ext.P19 decision, without referring to any of the above
aspects, but finding a new ground to reject the
petitioner's application, holding that the splitting up
of the area into three parts will be against the spirit
of the judgment of the Apex Court in Deepak Kumar and
others v. State of Haryana and others [2012 (4) SCC
629].
6. Sri.Jacob P. Alex, learned Counsel for the petitioner
pointed out that Deepak Kumar (supra) is rendered
entirely in a different context. Where the law mandates
E.C. only in cases of mining exceeding 5 hectares,
unscrupulous project proponents started dividing larger
extents to extents less than 5 hectares and conducting
quarrying mining without E.C. This was frowned upon the
Hon'ble Supreme Court in Deepak Kumar (supra) and it was WP(C) NO. 31130 OF 2024 6 2025:KER:38052
held that even for mining in areas less than 5 hectares,
E.C. is necessary. Distinguishing the facts in the
instant case, learned counsel pointed out that the
petitioner had sought for - and he was in fact issued
with - an E.C. in respect of 3.1473 hectares earlier in
the year 2013; and that he had sought for a separate
E.C. this time, in respect of 0.99 hectares. Learned
Counsel would clarify that E.C. granted in the year 2013
was in respect of 4.8493 hectares, that is the total
area; whereas the same has been limited to 3.1473, when
the E.C. was renewed in the year 2019. The point remains
that the petitioner had applied for separate E.Cs in
respect of both the extents, wherefore the application
of Deepak Kumar (supra) does not come into play at all.
Learned counsel for the petitioner also invited my
attention to paragraph nos.41.5, 41.6, 54, 58, 118,
123.1 and 124 of Hanuman Laxman Aroskar (supra), which
categorically held that the recommendation of the expert
body SEAC, or for that matter E.A.C., to grant E.C. to
an applicant or to reject the same is to be accepted by WP(C) NO. 31130 OF 2024 7 2025:KER:38052
the regulatory authority, normally. In paragraph no.58,
a specific reason has been assigned by the Hon'ble
Supreme Court, that SEAC is a body constituted of
experts in the field of environment. The judgment also
underscores the requirement to state specific and cogent
reasons in case the regulatory authority/R1 differs with
the recommendation made by the expert body SEAC, in
which case, the course open to the regulatory authority
like R1 is only to remand the matter to the expert
body/SEAC for reconsideration.
7. Learned Standing Counsel for the SEIAA would invite
the attention of this Court to Clause 8, Sub clause 2 of
E.I.A. notification which would precisely lend support
to the dictum laid down by the Hon'ble Supreme Court
that SEAC's recommendation shall ordinarily be accepted,
and in case the regulatory body disagrees, it will have
to be sent back to SEAC for reconsideration. Such
reconsidered recommendation received from SEAC has to be
considered by the regulatory body and a decision has to
be taken, which has been made final as per the statutory WP(C) NO. 31130 OF 2024 8 2025:KER:38052
notification. Learned Standing Counsel pointed out that
this procedure has been adopted by virtue of Ext.P4. But
it should be noticed immediately that Ext.P4, as well as
Ext.P13, has been set aside by this Court as per Ext.P15
judgment, wherefore the compliance, if any, by virtue of
Ext.P4 cannot be gainsaid by the 1st respondent
regulatory authority.
8. More importantly, this Court notice that no specific
reason is stated by the 1st respondent authority, either
in Ext.P17 Order or in Ext.P19 Order, except saying that
the petitioner is to get a mining plan for the entire
area. None of the reasons, which have been considered
and recognized by SEAC and the reasons which
specifically weighed with the learned Single Judge in
setting aside Exts.P4 and P13 Orders, is seen considered
by the 1st respondent while passing Ext.P17 and Ext.P19
orders.
9. This Court is of the opinion that this is not a case
where a mere setting aside of Exts.P17 and P19 Orders WP(C) NO. 31130 OF 2024 9 2025:KER:38052
would meet the interest of justice. This Court notice a
clear dereliction of duty on the part of the members of
SEIAA in- (1) complying with this Court's Order produced
at Ext.P15; (2) in complying with the mandate and dictum
of the Hon'ble Supreme Court in Hanuman Laxman Aroskar
and (3) in not considering the recommendations of SEAC.
I am of the opinion that such non-consideration is not
an omission, but deliberate. This is axiomatic from the
fact that the petitioner had preferred Ext.P18 review
pointing out these aspects, which also fell in the deaf
ears of the members of the 1st respondent authority. It
requires no mention that a judgment considers the
legality and correctness of a course of action adopted
by an authority, including a statutory body. If a Court
chooses to set aside such action as reflected in an
Order, the same will obviously for reasons recorded in
that judgment. Ext.P15 contains cogent reasons, which
has been narrated all throughout the judgment and pin-
pointed in the penultimate paragraph of the judgment. It
is after specifically referring to the illegalities in WP(C) NO. 31130 OF 2024 10 2025:KER:38052
Exts.P4 and P13 Orders that the learned Single Judge
chose to set aside the same and directed reconsideration
of the same. It is, therefore, incumbent on the
authority to consider those reasons - which weighed with
the learned Single Judge in setting aside Exts.P4 and
P13 Orders- while reconsidering petitioner's application
for issuance of E.C, in compliance with the directions
of the judgment. I am of the firm opinion that Exts.P17
and P19 Orders are in utter disregard of Ext.P15
judgment. Palpable recalcitrance to change SEIAA's stand
- dehors the directions in Ext.P15 judgment and the
binding nature of SEAC's recommendation in normal
circumstances - is manifest in Exts.P17 and P19 Orders,
especially in the latter.
10. In the circumstances, this Writ Petition is allowed
with costs. Exts.P17 and P19 Orders are set aside.
Besides, this Court directs the 1st respondent SEIAA to
pay a cost of Rs.75,000/- to the petitioner within a
period of one month from today, each member of SEIAA
paying Rs.25,000/- each.
WP(C) NO. 31130 OF 2024 11 2025:KER:38052
11. It is pointed out by the learned Standing Counsel
that SEIAA/1st respondent is not functioning now, since
their period is over. Dehors the same, the above
direction to pay cost will operate as against the
individual members of SEIAA. Needless to say that the
cost above referred has to be paid by them individually,
without in any way burdening the public exchequer.
12. It will be open for the petitioner to seek
compensation for the business lost, because of the
erroneous Orders passed by the 1st respondent authority,
in case the E.C. sought for by the petitioner is
ultimately allowed.
13. The 1st respondent (in case new SEIAA is
constituted) or the Ministry of Environment, Forest and
Climate Change of India (as provided in Clause IV (3) of
EIA notification) will consider the petitioner's
application for issuance of E.C. as directed in Ext.P15
judgment, in the light of the observations contained
therein, as also, those contained in this judgment, in WP(C) NO. 31130 OF 2024 12 2025:KER:38052
accordance with law, within a period of two months from
the date of receipt of a copy of this judgment. To
enable the same, the Ministry of Environment, Forest and
Climate Change of India is suo motu impleaded as the 3 rd
respondent, for which entity, Sri.C.Dinesh takes notice.
The gist of this Order will be communicated forthwith by
Sri.C.Dinesh to the competent officer in the Ministry
for necessary compliance within time. Besides, it will
be open for the petitioner to produce a copy of this
judgment before the said authority, to ensure
compliance.
This WP(C) is allowed with cost as above.
Sd/-
C. JAYACHANDRAN
JUDGE
ska WP(C) NO. 31130 OF 2024 13 2025:KER:38052
APPENDIX OF WP(C) 31130/2024
PETITIONER EXHIBITS
Exhibit P1 TRUE COPY OF THE ENVIRONMENTAL CLEARANCE BEARING NO. 77/SEIAA/KL/172/2013 DATED 28-12-2019 Exhibit P2 TRUE COPY OF THE CERTIFICATE BEARING NO.
943/DOPTA/M/2019 DATED 07-04-2022 ISSUED BY THE 2ND RESPONDENT Exhibit P2(a) TRUE COPY OF THE CERTIFICATE BEARING NO.
426/DOPTA/M/2024 DATED 29-05-2024 ISSUED BY THE 2ND RESPONDENT Exhibit P3 TRUE COPY OF THE RELEVANT PAGES OF THE MINUTES OF THE 136TH MEETING OF SEAC Exhibit P3(a) TRUE COPY OF THE RELEVANT PAGES OF THE MINUTES OF THE 124TH MEETING OF SEAC Exhibit P3(b) TRUE COPY OF THE EXPLANATION DATED 18-04-2022 SUBMITTED BY THE PETITIONER BEFORE THE SEAC THROUGH 1ST RESPONDENT (WITHOUT ANNEXURE) Exhibit P4 TRUE COPY OF THE RELEVANT PAGE OF THE MINUTES OF THE 123RD MEETING OF THE 1ST RESPONDENT ON 27&28 JANUARY, 2023 Exhibit P5 TRUE COPY OF THE RELEVANT PAGES OF NOTIFICATION BEARING SO NO. 2269(E) DATED 01-07-2016 ISSUED BY THE MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE, GOVERNMENT OF INDIA Exhibit P6 TRUE COPY OF THE RELEVANT PAGES OF NOTIFICATION BEARING SO NO.3977(E) DATED 14-08-2018 ISSUED BY THE MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE, GOVERNMENT OF INDIA Exhibit P7 TRUE COPY OF THE E-FILE BEARING NO.
12.1/SEIAA/2013-14/16/KER/1351 DATED 24-02- 2023 ISSUED BY THE IRO OF MOEF &CC Exhibit P8 TRUE COPY OF THE REPRESENTATION DATED 08-03- 2023 SUBMITTED BY PETITIONER BEFORE THE 1ST RESPONDENT (WITHOUT ENCLOSURES) Exhibit P9 TRUE COPY OF THE RELEVANT PAGES OF THE MINUTES OF THE 139TH MEETING OF SEAC WP(C) NO. 31130 OF 2024 14 2025:KER:38052
Exhibit P10 TRUE COPY OF THE RELEVANT PAGES OF THE MINUTES OF THE 141ST MEETING OF SEAC Exhibit P11 TRUE COPY OF THE RELEVANT PAGES OF THE MINUTES OF THE 144TH MEETING OF SEAC Exhibit P12 TRUE COPY OF THE RELEVANT PAGES OF THE MINUTES OF THE 147TH MEETING OF SEAC Exhibit P13 TRUE COPY OF THE RELEVANT PAGES OF THE MINUTES OF THE 131ST MEETING OF 1ST RESPONDENT - SEIAA Exhibit P14 TRUE COPY OF THE SKETCH APPROVED BY THE DISTRICT GEOLOGIST APPENDED WITH THE MINING PLAN SUBMITTED BEFORE THE 1ST RESPONDENT Exhibit P15 TRUE COPY OF THE JUDGMENT DATED 03-04-2024 IN WPC NO. 8820 OF 2023 Exhibit P16 TRUE COPY OF THE HEARING NOTE DATED 31-05- 2024 SUBMITTED BY THE PETITIONER BEFORE THE 1ST RESPONDENT Exhibit P17 TRUE COPY OF THE RELEVANT PAGES OF THE DECISION OF 1ST RESPONDENT (ITEM NO. 144.09) IN ITS 144TH MEETING HELD ON 28TH AND 29TH JUNE, 2024 Exhibit P18 TRUE COPY OF THE REPRESENTATION DATED 23-07- 2024 SUBMITTED BY THE PETITIONER BEFORE THE 1ST RESPONDENT Exhibit P19 TRUE COPY OF THE RELEVANT PAGES OF THE DECISION OF 1ST RESPONDENT (ITEM NO. 146.21) IN ITS 146TH MEETING HELD ON 29TH AND 30TH JULY, 2024 RESPONDENT ANNEXURES
Annexure A1 THE TRUE COPY OF THE LICENCE ISSUED BY THE KONNI GRAMA PANCHAYAT DATED 23.03.2020 Annexure A2 THE COMPLAINT FILED BY ME BEFORE THE SECRETARY KONNITHAZHAM PANCHAYATH DATED 01.11.2024 Annexure A3 THE TRUE COPY OF THE NOTICE ISSUED BY THE ENVIRONMENTAL ENGINEER TO VILLAGE OFFICE KONNITHAZHAM VILLAGE DATED 07.10.2024 REGARDING THE UNAUTHORISED CONCRETE CONSTRUCTION IN THE STREAM Annexure A4 THE TRUE COPY OF THE NOTICE ISSUED BY THE WP(C) NO. 31130 OF 2024 15 2025:KER:38052
ENVIRONMENTAL ENGINEER TO THE SECRETARY KONNI GRAMA PANCHAYAT REGARDING THE UNAUTHORISED CONSTRUCTION OF GATE DATED 07.10.2024 Annexure A5 THE TRUE COPY OF THE NOTICE ISSUED BY THE ENVIRONMENTAL ENGINEER DATED 18.10.2024 REGARDING THE FLOW OF WASTE WATER
Annexure A6 A TRUE COPY OF THE GOVERNMENT ORDER GO(MS) NO. 6/2025/WRD DATED 20.01.2025 PETITIONER EXHIBITS
Exhibit P20 True copy of the relevant page of Mine closure report in respect of Lease bearing No. 68/2012-13/3664/M3/12/DMG dated 27-04-
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!