Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Vsc Villaments vs Aryanad Grama Panchayat
2025 Latest Caselaw 6653 Ker

Citation : 2025 Latest Caselaw 6653 Ker
Judgement Date : 12 June, 2025

Kerala High Court

M/S. Vsc Villaments vs Aryanad Grama Panchayat on 12 June, 2025

Author: C.S.Dias
Bench: C.S.Dias
WP(C) NO. 19292 OF 2025                 1


                                                               2025:KER:41544

             IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                  PRESENT

                THE HONOURABLE MR.JUSTICE C.S.DIAS

     THURSDAY, THE 12TH DAY OF JUNE 2025 / 22ND JYAISHTA, 1947

                      WP(C) NO. 19292 OF 2025

PETITIONER:

             M/S. VSC VILLAMENTS
             TC 54/928, ROHINI SADANAM, MELAMCODE, NEMOM P.O,
             THIRUVANANTHAPURAM REPRESENTED BY ITS MANAGING
             PARTNER SRI. SREEJITH S.S., PIN - 695020


             BY ADVS. SRI.ENOCH DAVID SIMON JOEL
             SRI.S.SREEDEV
             SRI.RONY JOSE
             SHRI.LEO LUKOSE
             SRI.KAROL MATHEWS SEBASTIAN ALENCHERRY
             SHRI.DERICK MATHAI SAJI
             SHRI.KARAN SCARIA ABRAHAM
             SHRI.ITTOOP JOY THATTIL

RESPONDENTS:

      1      ARYANAD GRAMA PANCHAYAT
             ARYANAD P.O, THIRUVANANTHAPURAM
             REPRESENTED BY ITS SECRETARY, PIN - 695542

      2      SECRETARY
             ARYANAD GRAMA PANCHAYAT, ARYANAD P.O,
             THIRUVANANTHAPURAM, PIN - 695542


             BY ADV SHRI.SUMAN CHAKRAVARTHY, SC, ARYANAD GRAMA
             PANCHAYAT


       THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION
ON    12.06.2025,   THE   COURT    ON       THE   SAME   DAY   DELIVERED   THE
FOLLOWING:
 WP(C) NO. 19292 OF 2025          2


                                                       2025:KER:41544



                           JUDGMENT

Dated this the 12th day of June, 2025

The writ petition is filed to declare that the

petitioner has obtained a deemed trade licence under

Section 236(3) the Kerala Panchayat Raj Act, 1994 (for

short 'Act'), to operate a granite building stone quarry

('quarry', for brevity).

2. The petitioner proposes to start a quarry.

Accordingly, after obtaining the licenses and permissions

from the competent statutory authorities, the petitioner

submitted an application for trade licence to the 2 nd

respondent on 20.02.2025, as evidenced by Ext.P5

receipt. On 19.03.2025, the 2nd respondent issued a letter

to the petitioner, directing them to produce certain

additional documents. The petitioner produced the

required documents on 21.03.2025, as per Ext.P7

covering letter. After that, the petitioner also produced a

No Objection Certificate (NOC) from the Irrigation

2025:KER:41544

Department on 15.04.2025, though it was not necessary.

However, the 2nd respondent failed to process the

application for the trade licence within the mandatory

time period of 30 days as envisaged under Section 236(3)

of the Act. Instead, the 2nd respondent sent Ext.P8

rejection order, in Ext.P9 postal cover, only on

20.05.2025, i.e., after the expiry of 30 days from

15.04.2025. Therefore, the petitioner is entitled to a

declaration as prayed in the writ petition.

3. The 2nd respondent has filed a statement

refuting the allegations in the writ petition. It is

contended that Ext.P5 application was rejected by the 2 nd

respondent on 23.04.2025 by Ext.P8 order. Therefore,

the deeming provision under the Act is not attracted.

4. The petitioner has filed a reply affidavit

denying the allegations in the counter affidavit. The

petitioner has produced Ext.P9 postal cover and Ext.P10

track consignment letter, to establish that Ext.P8 order

was sent by the 2nd respondent by registered post on

2025:KER:41544

20.05.2025 and was received by the petitioner only on

21.05.2025.

5. When the writ petition came up for

consideration on 26.05.2025, the learned Standing

Counsel appearing for the respondents submitted that, a

copy of Ext.P8 order was served on the authorised

representative of the petitioner. Accordingly, this Court

directed the respondents to produce the proof of delivery

of Ext.P8 order.

6. Pursuant to the said order, the 2nd

respondent has filed an affidavit stating that, after the

receipt of the NOC from the Irrigation Department on

15.04.2025, the 2nd respondent passed Ext.P8 order on

23.04.2025, which is within eight days. The order was

collected by a representative of the petitioner from the 2nd

respondent on 24.04.2025. Thereafter, the Managing

Partner of the petitioner also collected a copy of the order

from the 2nd respondent on 12.05.2025. However, the

respondents have candidly admitted that they have not

2025:KER:41544

obtained any acknowledgment regarding the service of a

copy of the order. Subsequently, Ext.P8 order was

dispatched by registered post to the petitioner on

20.05.2025, in the routine course of business.

7. Heard; the learned Counsel for the

petitioner and the learned Standing Counsel appearing

for the respondents.

8. It is not in dispute that the petitioner had

submitted Ext.P5 application on 20.02.2025. In response

to Ext.P6 letter, the petitioner had submitted the

additional documents and Ext.R2(a) NOC from the

Irrigation Department before the 2nd respondent on

21.03.2025 and 15.04.2025, respectively.

9. In the above context, it is necessary to refer to

Section 236(3) of the Act, which reads as follows:

"236.General provisions regarding licences and permissions:-

(1) xxxx (2) xxxx (3) Save as aforesaid, if orders on an application for any such licence or permission are not communicated to the applicant within thirty days or such longer period as may be

2025:KER:41544

prescribed in any class of cases after the receipt of the application by the Secretary, the application shall be deemed to have been allowed for the period, if any, for which it would have been ordinarily allowed and subject to the law, rules and bye-laws and all conditions ordinarily imposed."

10. A reading of the above provision mandates

that an order passed by the statutory authority under the

Act has to be communicated to the applicant within 30

days from the date of passing of the order.

11. The mandatory compliance of the above

provision is no longer res integra in view of the decision

of the Division Bench of this Court Koottikkal Grama

Panchayath and Another v. Vazhathara Granites and

Aggregates Pvt.Ltd. [2018 KHC 4640].

12. In Jalaludeen K v. Veliyam Grama

Panchayat [2024 KHC 1108], this Court has held that,

the mere dispatch of a letter would not suffice to avoid

the consequence of the deeming provision. The order has

to be communicated to the applicant in order to avoid the

consequence of the deeming factor.

2025:KER:41544

13. In view of the affidavit filed by the

respondents dated 05.06.2025, it is not in dispute that the

2nd respondent had only sent Ext.P8 order by registered

post on 20.05.2025. Even though it is alleged that a copy

of Ext.P8 order was collected by the petitioner's

representative on 24.04.2025 and the petitioner's

Managing Partner on 12.05.2025, admittedly, there is no

acknowledgment or proof of service/communication.

Therefore, the said statement is not satisfactory and

worthy of credence to fulfill the mandatory requirement

envisaged under Section 236 of Act and the

interpretations given by this Court in the aforesaid

decisions.

In the aforesaid circumstances, I allow the writ

petition by quashing Ext.P8 order and declaring that the

petitioner has secured a valid trade licence under

Sections 232 and 233 of the Act, by virtue of Section 236

(3) of the Act. Consequently, the 2nd respondent is

directed to issue the petitioner the trade licence in the

2025:KER:41544

paper form within one week from the date of production

of a copy of this judgment. Needless to mention, in case

the petitioner violates the conditions of the licence, it

would be open to the 2nd respondent to cancel the licence,

in accordance with law.

The writ petition is ordered accordingly.

Sd/-

C.S.DIAS, JUDGE NAB

2025:KER:41544

APPENDIX OF WP(C) 19292/2025

PETITIONER EXHIBITS

EXHIBIT P1 TRUE COPY OF THE LETTER OF INTENT DATED 06.02.2023 ISSUED BY THE DIRECTOR OF MINING AND GEOLOGY.

EXHIBIT P2 TRUE COPY OF THE CONSENT TO OPERATE DATED 04.01.2025 VALID TILL 31.10.2029 ISSUED BY THE POLLUTION CONTROL BOARD.

EXHIBIT P3 TRUE COPY OF THE ENVIRONMENTAL CLEARANCE DATED 23.10.2024 ISSUED BY THE SEIAA. EXHIBIT P4 TRUE COPY OF THE EXPLOSIVE LICENSE VALID TILL 31.03.2030.

EXHIBIT P5 TRUE COPY OF THE RECEIPT DATED 20.02.2025 ISSUED BY THE 2ND RESPONDENT.

EXHIBIT P6 TRUE COPY OF THE LETTER DATED 19.03.2025 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER.

EXHIBIT P7 TRUE COPY OF THE LETTER DATED 21.03.2025 SUBMITTED BY THE PETITIONER BEFORE THE 2ND RESPONDENT.

EXHIBIT P8 TRUE COPY OF THE ORDER DATED 23.04.2025 BEARING NO. JC3.884/2025 ISSUED BY THE 2ND RESPONDENT.

EXHIBIT P9 A TRUE COPY OF THE POSTAL COVER ENCLOSING EXT.P8.

EXHIBIT P10         TRUE COPY OF THE CONSIGNMENT DETAILS OF
                    THE    CONSIGNMENT    BEARING    NO.   RL

159870101IN AS AVAILABLE FROM THE POSTAL WEBSITE.

RESPONDENT ANNEXURES

ANNEXURE-R2(a) THE COVERING LETTER DATED 15.04.2025 SUBMITTED BY THE PETITIONER BEFORE THE RESPONDENTS

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter