Citation : 2025 Latest Caselaw 253 Ker
Judgement Date : 2 June, 2025
2025:KER:38784
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE S.MANU
MONDAY, THE 2ND DAY OF JUNE 2025 / 12TH JYAISHTA, 1947
WP(C) NO. 28147 OF 2016
PETITIONER/S:
THOTTATHIL PRADEEPKUMAR
AGED 36 YEARS, S/O.URUVADAN NICHA THOTTATHIL,
AGED 48 YEARS,NICHA HOUSE, KURUVADA, PO.EZHOM,KANNUR
DISTRICT, REPRESENTED BY POWER OF ATTONNEY HOLDER AND
WIFE KV. BEENA, AGED 36 YEARS, NICHA HOUSE,
KURUVADU,P.O.EZHOM, KANNUR DISTRICT
BY ADV SHRI.V.N.RAMESAN NAMBISAN
RESPONDENT/S:
1 GOVERNMENT OF KERALA
REPRESENTED BY THE AGRICULTURAL PRODUCTION
COMMISSIONER, AGRICULTURE (NCA)
DEPARTMENT,THIRUVANANTHAPURAM, PIN - 695001
2 THE DISTRICT COLLECTOR
KANNUR (APPELLATE AUTHORITY UNDER THE CONSERVATION OF
PADDY LAND AND WET ACT, 2008(ACT 28/08) PIN - 670001
3 THE REVENUE DIVISIONAL OFFICER
THALASSERY (CHAIRMAN, DISTRICT LEVEL AUTHORIZED-
COMMITTEE UNDER ACT 28/2008),
KANNUR DISTRICT, PIN - 671104
4 THE PRESIDENT
EZHOM GRAMA PANCHAYATH,KANNUR DISTRICT
(CHAIRMAN, LOCAL MONITORING -COMMITTEE UNDER ACT
28/2008),PIN - 670001
OTHER PRESENT:
SRI M L SAJEEVAN, SPL.GP
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON
02.06.2025, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
W.P.(C) No. 28147 of 2016
2025:KER:38784
2
JUDGMENT
This is the third round of litigation at the instance of the
petitioner for permission to convert his property comprised in
Sy.No.16/2A2 of Ezhom Village, Kannur Taluk for the purpose of
construction of a residential building. Ext. P3 is an application
submitted on 14.02.2011. The application was rejected and the
appeal preferred by the petitioner was also rejected. Thereafter he
approached this Court in W.P.(C) No.3774 of 2013. By judgment
dated 08.02.2013, the writ petition was disposed of directing the
petitioner to avail statutory remedy of revision. Petitioner
thereafter filed a revision petition before the Government. The
revision petition was rejected by the Government by Ext. P10 order
dated 24.07.2013.
2. Petitioner filed W.P.(C) No.20332 of 2013
aggrieved by the rejection of the revision petition. By judgment
dated 02.01.2014, the writ petition was disposed of. This Court
considered the dispute in detail. This Court observed in the
judgment that the conditions mentioned under Section 9(8) of the
Act are satisfied in the case of the petitioner. Factual aspects were
adverted to and it was observed that the property is not
2025:KER:38784
surrounded by paddy lands as a tarred road is situated on one side
of the property. It was also observed that, the petitioner is seeking
permission to utilize the land for constructing a residential building
for his own purpose. Further, this Court noticed that the
respondents have no case that the petitioner or any of his family
members have any other suitable land for constructing a
residential building. Regarding the likelihood of ecological impact
and affecting cultivation in the adjoining paddy land adversely,
this Court took note of the fact that, the 3rd respondent in Ext. P7
report, had noted that even if 5 cents of land is reclaimed, it may
not cause any adverse impact to the environment. Therefore, the
3rd respondent recommended in Ext. P7 to permit reclamation of 5
cents of land for the purpose of construction of a residential
building. This Court finally directed the 2nd respondent to consider
the matter afresh and to pass the order after providing opportunity
of hearing to the petitioner. To facilitate fresh consideration by the
2nd respondent the impugned orders were set aside.
3. In compliance with the direction issued in W.P.(C)
No.20332 of 2013, the 2nd respondent considered the matter and
issued Ext. P14 order on 02.02.2015, rejecting the application of
2025:KER:38784
the petitioner. Petitioner thenceforth filed this writ petition.
Learned Counsel for the petitioner assailed Ext. P14 order by
raising various contentions. The learned Counsel invited attention
of the Court to the following observations and findings of this
Court in Ext. P12 judgment :-
"5. The reason for rejecting the application preferred by the petitioner is merely with reference to the alleged violation of the relevant provisions of Sections 9 (8) (i) to (iv) of the Act 28 of 2008. For convenience of reference, Sections 9 (8) (i) to (iv) are extracted below :
9(8) : Notwithstanding anything contained in sub Section (i), no application shall be considered by the District Level Authorised Committee unless the Local Level Monitoring Committee has recommended that -
(i) such reclamation shall not adversely affect the ecological condition and the cultivation in the adjoining paddy land.
(ii) the owner of the paddy land or his family do not own a suitable land for this purpose in that District.
(iii) the building to be constructed for his own purpose; and
(iv) such paddy land is not situated surrounded by other paddy lands.
Sub clause (ii) of Section 9 (8) of the Act says that a portion of the paddy land can be converted, if the owner or his family does not own suitable land for the construction. The respondents have no case that the petitioner or his family is having any other land for
2025:KER:38784
effecting construction and as such, the said provision has no application to the case in hand. With regard to the mandate under sub clause (iii) of Section 9 (8), the requirement is to the effect that the building shall be constructed for 'own' purpose. In Ext. P3 application preferred by the petitioner itself, a declaration has been given by the petitioner to the effect that the building is to be constructed for own purpose. As such, the said clause also does not have any application at all. Sub Clause (iv) say that property shall not be 'surrounded' by paddy fields. On going through the contents of Ext. P7, it can be seen that there is a mention about a tarred road situated one side of the property and as such, the property cannot considered as one, which is 'surrounded' by paddy fields. It is also relevant to note that the third respondent himself has recommended the reclamation of the land so as to enable the construction of a residential building vide Ext. P7 (obtained by the petitioner invoking the remedy under RTI Act). In the said circumstance, the remaining question to be considered is, whether any violation is there with regard to Clause (i) of Section 9(8). This aspect has already been referred to hereinbefore and the 3 rd respondent himself has observed in Ext. P7 report [while considering and allowing the claim put forward by the petitioner] that there is no chance to have threat to the ecological imbalance, nor with regard to the user of the nearby properties, which are stated as remaining as paddy lands. This being the position, the matter requires to be reconsidered by the second respondent."
4. He contented that the conclusions of the 2 nd
respondent in Ext. P14 order are contrary to the above mentioned
findings and observations of this Court. On a careful reading of Ext.
2025:KER:38784
P14, I am convinced that the said contention is correct. The 2 nd
respondent has made observations in Ext. P14 regarding the same
aspects, totally at variance with the findings of this Court. The
learned Special Government Pleader fairly submitted that Ext. P12
judgment was not challenged and it has become final. Therefore it
was not open to the 2nd respondent to take any discrepant views
regarding issues with respect to which this Court had given
findings and made observations.
5. In view of the above discussion, the Ext. P14 order
cannot be sustained, it is hence quashed. Competent authority
among the respondents shall grant permission to the petitioner for
reclamation as provided under S.9(8) of the Act 28 of 2008.
Appropriate orders shall be issued within a period of six weeks
from the date of issuance of the judgment.
6. Facts of this case brings out the predicament of a
person who has been struggling for about 14 years for permission
to convert a portion of his land as permitted under law for
constructing a dwelling house. He or his family has no other
suitable land and denial of permission has definitely put a family in
uncertainty and desperation for nearly one and a half decades.
2025:KER:38784
Since owning a home is undoubtedly a fundamental aspect of
dignity and a facet of human rights, the Government and its
officials concerned must respond quickly and sympathetically to
requests for conversion for construction of dwelling houses by
those without other suitable properties. I am hoping that those
concerned would recognize the need to handle such requests with
greater sensitivity and tact in future.
Writ petition is disposed of with the above observations
and directions.
Sd/-
S.MANU JUDGE
ANK
2025:KER:38784
APPENDIX OF WP(C) 28147/2016
PETITIONER'S EXHIBITS
EXHIBIT P1 TRUE COPY OF PROPERTY TAX RECEIPT NO.
2789650 DATED 01.12.2012 ISSUED BY VILLAGE OFFICER, EZHOM TO THE PETITIONER
EXHIBIT P2 TRUE PHOTOGRAPHS OF THE PROPERTY COMPRISED IN RS. 16/2A2 OF EZHOM AMSOM, DESOM, KANNUR TALUK OWNED BY THE PETITIONER
EXHIBIT P3 TRUE COPY OF THE APPLICATION DATED 14.02.2011 SUBMITTED BY THE PETITIONER BEFORE THE 3RD RESPONDENT
EXHIBIT P4 TRUE COPY OF THEORDER NO. CG (1) 1055/11 DATED 12.12.2011 ISSUED BY THE CONVENER OF THE DISTRICT LEVEL AUTHORIZED COMMITTEE NAMELY THE PRINCIPAL AGRICULTURAL OFFICER, KANNUR
EXHIBIT P5 TRUE COPY OF THE APPEAL PETITION DATED 14.02.2012 FILED BY THE PETITIONER BEFORE THE 1ST RESPONDENT
EXHIBIT P6 TRUE COPY OF THE ORDER DATED 02.11.2012 ISSUED BY THE APPELLATE AUTHORITY REJECTING EXHIBIT P5
EXHIBIT P7 TRUE COPY OF THE COVERING LETTER NO. L 5- 59079/12 DATED 17.12.2012 ISSUED BY THE 1ST RESPONDENT
EXHIBIT P7 (A) TRUE COPY OF THE REORT OF THE SUB COLLECTOR
EXHIBIT P8 TRUE COPY OF THE JUDGMENT DATED 08.02.2013 IN WPC.NO. 3774/2013
EXHIBIT P9 TRUE COPY OF THE REVISION PETITION FILED
2025:KER:38784
BY THE PETITIONER ON 17.02.2013 BEFORE THE 1ST RESPONDENT
EXHIBIT P10 TRUE COPY OF THE ORDER NO. ORD/NO.
1402/2013 DATED 24.07.2013 ISSUED BY THE 1ST RESPONDENT
EXHIBIT P11 TRUE COPY OF THE CERTIFICATE NO. 169/13 DATED 27.05.2013 ISSUED B THE VILLAGE OFFICER, EZHOME
EXHIBIT P12 TRUE COPY OF THE JUDGMENT DATED 02.01.2014 IN WPC.NO. 20332/2013
EXHIBIT P13 TRUE COPY OF THE MEMO DATED 19.05.2016 OF THE DISTRICT COLLECTOR, KANNUR
EXHIBIT P14 TRUE COPY OF THE ORDER NO. L5/11903/2012 DATED 02.02.2015
EXHIBIT P15 TRUE COPY OF THE ORDER DATED 02.06.2016
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!