Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Assistant Executive Engineer vs State Electricity Ombudsman
2024 Latest Caselaw 13752 Ker

Citation : 2024 Latest Caselaw 13752 Ker
Judgement Date : 28 May, 2024

Kerala High Court

The Assistant Executive Engineer vs State Electricity Ombudsman on 28 May, 2024

Author: Dinesh Kumar Singh

Bench: Dinesh Kumar Singh

                IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                  PRESENT
             THE HONOURABLE MR. JUSTICE DINESH KUMAR SINGH
           TUESDAY, THE 28TH DAY OF MAY 2024 / 7TH JYAISHTA, 1946
                           WP(C) NO. 34675 OF 2017
PETITIONER/S:

             THE ASSISTANT EXECUTIVE ENGINEER
             ELECTRICAL SUBDIVISION, KSEB LTD, PAPPINISSERY, KANNUR.

             BY ADVS. MS POOJA JOSE, SRI.N. RAPHY RAJ, SC, SRI.N.SATHEESH,
             NIRMAL.S



RESPONDENT/S:

     1       STATE ELECTRICITY OMBUDSMAN
             CHARANGATTU BHAVAN, BUILDING NO.34/895, MAMANGALAM -
             ANCHUMANA ROAD, EDAPPALLY, KOCHI - 682024.

     2       SMT.E. SHOBANA
             "RIVIRESA", KOKKANPARA ROAD, PALLIKKUNNU, KANNUR - 670004.

             BY ADV RAJESH NAMBIAR


         THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
28.05.2024, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 W.P.(C) No.34675/2017
                                   -2-




                        JUDGMENT

The present writ petition has been filed on behalf of the

Kerala State Electricity Board impugning the order passed by

the State Electricity Ombudsman, Edappally, Kochi, in Appeal

Petition No.P/057/2016 dated 14.12.2016 in Ext.P4.

2. The 2nd respondent had obtained a three-phase

service connection under LT-IVA tariff (Industrial) with a

connected load of 134625 Watts with effect from 06.01.1996 for

an industrial unit in the name and style of M/s. Design and

Interiors, Mundappuram. A surprise inspection was

conducted on the premises of the 2nd respondent on

16.06.2015, and it was detected that one phase of the Current

Transformer (CT) to the meter was not working. It was

concluded that less consumption was recorded in the meter

than the actual energy consumed. A spot mahazer was

prepared, and thereafter, a short assessment bill for

Rs.1,64,125/- was issued to the 2nd respondent assessing the

unrecorded portion of the energy consumed by the 2nd

respondent for the past one year at the prevailing tariff rate.

2.1 Aggrieved by the bill, the 2nd respondent filed a

petition before the CGRF Kozhikode, which, however, came to

be dismissed vide judgment dated 16.06.2016 in O.P.

No.20/2016-17. Thereafter, the 2nd respondent approached the

State Electricity Ombudsman by filing Appeal Petition

No.P/057/2016, as mentioned above.

2.2 The Ombudsman has recorded a finding that

though the surprise inspection was conducted by KSEB

authorities on 16.06.2015, the provisional short assessment bill

amounting to Rs.1,64,125/--was served on the 2nd respondent

after three months, i.e., on 16.09.2015. The bill does not bear

any date and lacks basic details. The final bill was served only

on 22.02.2016, i.e., after five months from the date of issuance

of the provisional bill.

2.3 The Ombudsman, in the impugned order, has, after

considering the provisions of Regulation 152 and Regulation

115(9) of the Electricity Supply Code 2014, held that there are

marked differences in the contents of Regulation 115 and 152

of the Supply Code, 2014. These Regulations are distinct and

different, and their provisions operate in different fields and

have no common premise in law. Regulation 152 gives liberty

to the licensee to realise the amount of electricity charges

short collected by the licensee from the consumer under the

standard tariff applicable to the period during which such

anomalies persisted. Even if it is presumed that one phase of

the energy meter was missing as on the inspection date, the

Board failed to establish the actual date of missing energy in

one phase. The only reason stated is that the current

transformer installed in the 2nd respondent's premises was

tested at the TMR Division and declared faulty on 16.09.2015.

2.4 After perusing the records, the Ombudsman

concluded that the Board had not issued any notice as

stipulated in Regulation 115(5) of the Supply Code 2014 while

testing the transformer/meter. Further, the Board took three

months to test the alleged CT at the TMR Division, and there

was undue delay in issuing the provisional assessment and the

final bill to the 2nd respondent. The Ombudsman held that the

final bill was issued without observing the mandatory

provisions and, therefore, could not be sustainable.

3. Learned Standing Counsel for the Board submits

that the 2nd respondent has not denied that the correct

consumption from one phase was not recorded in the meter.

Regulation 152 of the Supply Code 2014 provides that if, on

inspection, the anomalies are attributable to the licensee, such

as wrong application of multiplication factor or incorrect

application of tariff by the licensee, it shall not attract the

provisions of Section 126 or Section 135 of the Act. In such

cases, the amount of short electricity charges collected by the

licensee, if any, shall only be realised from the consumer

under the standard tariff applicable to the period during

which such anomalies persisted. He further submits that

Regulation 115 is not applicable in the facts and circumstances

of the case, and the impugned order is not unsustainable.

4. Learned Counsel for the 2nd respondent, however,

submits that the 2nd respondent approached the CGRF, and the

CGRF rejected the petition against which she filed an appeal

before the Ombudsman. It is further submitted that the

Ombudsman's decision was in favour of the 2nd respondent, so

the Board would not have the right to appeal against the said

order, in the sense that the Board is impugning the decision of

the Ombudsman, a statutory authority under the provisions of

the Electricity Act and the Regulations made thereunder. The

impugned judgment does not suffer from any perversity, and

it cannot be said that it is without jurisdiction; therefore, this

Court, in the exercise of its jurisdiction under Article 227 of

the Constitution of India, may not interfere with the decision

of the Ombudsman.

5. The short assessment bill has been issued for the

past one year. However, Regulation 152 specifically provides

that in such a situation where the licensee had failed to

maintain proper instruments or anomalies are attributable to

the licensee, the provisions of Section 126 or Section 135 of the

Act would not be applicable. The short assessment charges can

only be realised from the consumer under the standard tariff

applicable to the period during which such anomalies

persisted. Regulation 115(9) of the Electricity Supply Code

provides that in case the meter is found to be faulty, revision

of the bill on the basis of the test report is to be done for a

maximum period of six months or from the date of last testing

whichever is shorter and the excess or deficit charges on

account of such revision shall be adjusted in the two

subsequent bills.

5.1 The procedure for testing the meter is also

prescribed in Regulation 115(5), which provides that the

licensee shall be given advance notice of three days,

intimating the date, time and place of testing so that the

consumer or his authorised representative can at his option,

be present at the testing. Admittedly, when the meter or

transformer was tested, the 2nd respondent was not issued

notice, so there was a violation of Regulation 115(5). Further,

there is no finding recorded in the short assessment bill from

which date the meter could not record the correct reading of

one phase because of the faulty transformer. Even Regulation

115(9) provides that on the basis of the test report, revision

could be possible for a maximum period of six months or from

the date of last testing, whichever is shorter.

5.2 In the present case, the revision has been done for

a period of 12 months, which is also against Regulation 115(9)

of the Code. When the meter/transformer was not tested as

per the provisions of Regulation 115(5), and it was the duty of

the Board to maintain the transformer, the 2nd respondent

cannot be saddled with the liability of the short assessment

bill.

5.3 Considering this Court's limited jurisdiction under

Article 227 of the Constitution of India, the impugned order

passed by the Ombudsman in Ext.P4 requires no interference

as it is not without jurisdiction or against law.

The writ petition fails, which is hereby dismissed.

Interim order, if any, stands vacated.

Sd/-

DINESH KUMAR SINGH JUDGE

jjj

APPENDIX OF WP(C) 34675/2017

PETITIONER EXHIBITS

EXHIBIT-P1: TRUE COPY OF THE MAHAZER DATED 16.07.2015.

EXHIBIT-P2: TRUE COPY OF FINAL BILL DATED 22.03.2016.

EXHIBIT-P3: TRUE COPY OF METER READING REGISTER DATED 06.01.1996.

EXHIBIT-P4: TRUE COPY OF ORDER DATED 14.12.2016 OF OMBUDSMAN.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter