Tuesday, 21, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Scariya Paul vs Deputy General Manager
2024 Latest Caselaw 12872 Ker

Citation : 2024 Latest Caselaw 12872 Ker
Judgement Date : 22 May, 2024

Kerala High Court

Scariya Paul vs Deputy General Manager on 22 May, 2024

Author: V.G.Arun

Bench: V.G.Arun

         IN THE HIGH COURT OF KERALA AT ERNAKULAM
                           PRESENT
            THE HONOURABLE MR.JUSTICE V.G.ARUN
 WEDNESDAY, THE 22ND DAY OF MAY 2024 / 1ST JYAISHTA, 1946
                     CRP NO. 128 OF 2019
AGAINST THE ORDER/JUDGMENT DATED IN OP NO.245 OF 2010 OF
           ADDITIONAL DISTRICT COURT, KOZHIKODE
REVISION PETITIONER/S:

          SCARIYA PAUL,
          AGED 46 YEARS
          S/O.PAULOSE, MALIYELI HOUSE, VELANKODE,
          KODENCHERRY VILLAGE, KOZHIKODE TALUK, KOZHIKODE
          DISTRICT.
          BY ADV C.P.PEETHAMBARAN


RESPONDENT/S:

          DEPUTY GENERAL MANAGER,
          POWER GRID CORPORATION OF INDIA LTD.,
          P.O.URAPURAM, AREEKODE, ERNAD TALUK, MALAPPURAM
          DISTRICT- 673639.
     THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
07.03.2024, THE COURT ON 22.05.2024, DELIVERED THE FOLLOWING:
 CRP No.128 of 2019


                                   -2-




                               ORDER

Dated this the 22nd day of May, 2024

This revision petition is filed challenging

the order passed by the Additional District

Judge-I, Kozhikode in O.P.(Electricity) No.245 of

2010. The original petition was filed by the

revision petitioner being dissatisfied with the

compensation awarded towards the damage and loss

sustained due to the drawing of 400 KV lines

across his property by the Power Grid Corporation

of India Ltd (hereinafter called 'the

Corporation'). The essential facts are as under;

The petitioner is in ownership and possession

of landed property having an extent of 15 cents

in Kodencherry Village of Kozhikode Taluk. The

land was cultivated with various yielding and

non-yielding trees. In order to facilitate

drawing of 400 KV electric lines for the smooth

transmission of power in the Mysore-Kozhikode

sector, large number of trees were cut from the

property. According to the petitioner, the

drawing of high tension lines had rendered the

land underneath and adjacent useless, resulting

in diminution of the land value. In spite of the

huge loss suffered by the petitioner, only small

amount was granted as compensation. Hence, the

petitioner filed original petition, seeking

enhanced compensation towards the value of trees

cut and diminution in land value.

2. Thereafter, being dissatisfied with the

enhancement of compensation awarded by the court

below, petitioner preferred civil revision

petition and the same was allowed by this Court

and the case remanded back with a direction to

determine yield from each tree and to consider

all components of diminution in land value

including prevailing market price of the land and

any new factor which may be brought to the notice

of the court by the petitioner. After remand, the

petitioner filed a statement before the court

below clarifying that he is not claiming

additional compensation for loss in value of

improvements. Hence, the court below considered

the claim for enhanced compensation towards

diminution in land value alone and passed the

impugned order.

3. After remand, learned Counsel for the

revision petitioner contended before the court

below that the land value was improperly fixed on

the basis of fair value extract and this

resulted in the fixation of land value as well as

the percentage of diminution being on the lower

side. It was also contended that, the land value

fixed in O.P.(Ele) No.136 of 2010 and connected

cases should be considered for fixing the land

value of the petition schedule property. The

properties involved in Exts.A15 and A16 documents

were pointed out as comparable lands and prayer

made to enhance the compensation accordingly.

4. Learned Counsel for the respondent

Corporation argued that the petition schedule

property is a wetland without direct road

frontage even to the Panchayat Road and access to

the property is through a mud road. Therefore,

the land value fixed for plots abutting PWD and

Panchayat roads cannot be adopted for fixing the

land value of the petition schedule property.

According to the learned Counsel, the land value

was fixed after considering the locational

features and civic amenities available and any

further enhancement will be excessive and

improper.

5. Although petitioner relied on Exts.A15

and A16 documents, the court below refused to

accept the properties involved in the said

documents as comparable lands. It was found that,

while those properties are garden lands as well

as commercial sites, the petition schedule

property is a residential compound. The

petitioner's property is situated at a distance

of 41 metres from the PWD road, which is

connected through a 3 metre wide mud road. The

court below also found that 6.75 cents out of 15

cents is affected due to the drawing of electric

lines and the electric lines were drawn at a

height of only 10 metres above a portion of the

house situated in the property. On consideration

of the above factors along with the locational

features and on comparison of the petition

schedule property with the properties involved in

Exts.A15 and A16 documents, the court below fixed

the land value at Rs.20,000/- per cent, as

against Rs.8,000/- per cent fixed earlier. As the

electric lines were drawn at a height of only 10

metres above a portion of the petitioner's house,

the court below had fixed the percentage of

diminution at 50% of the land value before remand

and the said finding was affirmed by the impugned

order. A table containing the compensation thus

awarded is appended below;

     Sl    Case    Affected     Land      Percentage Compensation Compensation     Balance
                                                                                 Compensation
     No    No.      area        value         of        payable       paid           due
                              per cent    diminution
     1    OP     6.75         20,000     50%            67,500       27,000       40,500



In        view         of     the      decision          of        this    Court           in

P.Raghavan v. KSEB [CRP No.3256 of 2001], the

interest on the additional compensation was

directed to be paid at the rate of 12% per annum

from the date of cutting of trees till the date

of payment.

6. Heard learned Counsel appearing on

either side.

7. On careful scrutiny of the impugned

order, it is seen that the compensation due

towards diminution in land value was fixed based

on factors like situs of the land, the extent to

which the land is adversely affected and

consequent diminution in the value of the land,

as laid down by the Apex Court in KSEB v. Livisha

[(2007) 6 SCC 792]. Similarly, the discretion

vested with the court was properly exercised by

affirming 50% of the land value as compensation

for the land affected due to the drawing of

electric lines. As such, there is no illegality

or material irregularity in the impugned order,

warranting this Court's interference in exercise

of the revisional power under Section 115 of the

Code of Civil Procedure.

For the aforementioned reasons, the civil

revision petition is dismissed.

If any amount is deposited pursuant to the

order of this Court or otherwise, the same shall

forthwith be released to the petitioner on his

filing appropriate application. The entire

enhanced compensation shall be paid to the

petitioner within three months of receipt of a

copy of this order.

Sd/-

V.G.ARUN JUDGE Scl/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter