Tuesday, 21, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

George Joseph vs Power Grid Corporation Of India Ltd
2024 Latest Caselaw 12529 Ker

Citation : 2024 Latest Caselaw 12529 Ker
Judgement Date : 21 May, 2024

Kerala High Court

George Joseph vs Power Grid Corporation Of India Ltd on 21 May, 2024

Author: V.G.Arun

Bench: V.G.Arun

              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                              PRESENT
                 THE HONOURABLE MR.JUSTICE V.G.ARUN
    TUESDAY, THE 21ST DAY OF MAY 2024 / 31ST VAISAKHA, 1946
                        CRP NO. 367 OF 2021
AGAINST THE ORDER/JUDGMENT DATED IN OPELE NO.1225 OF 2014 OF
VI ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:

            GEORGE JOSEPH
            AGED 49 YEARS
            S/O. JOSEPH, KOZHUKKATTA HOUSE, CHERANELLOOR P.O.,
            KOOVAPPADY, ERNAKULAM-683 544
            BY ADV P.T.JOSE


RESPONDENT/S:

    1       POWER GRID CORPORATION OF INDIA LTD
            CONSTRUCTION AREA OFFICE, KAKKANAD, NOW IN FAO/400,
            220 KV SUBSTATION, KUMARAPURAM P.O., PALLIKARA,
            KOCHI-682 303 REP BY DEPUTY MANAGER
    2       THE SPECIAL TAHSILDAR (LA),
            POWER GRID CORPORATION OF INDIA LTD., THRIKKAKARA
            VILLAGE, KANAYANNOOR TALUK, KAKKANAD, ERNAKULAM
            P.O., -682 030,
    3       ADDL.R3- STATE OF KERALA,
            REPRESENTED BY DISTRICT COLLECTOR, CIVIL STATION
            BUILDING, KAKKANAD, ERNAKULAM, KOCHI-682 030
    4       ADDL.R4-KERALA STATE ELECTRICITY BOARD,
            REPRESENTED BY CHAIRMAN AND MANAGING DIRECTOR, KSEB
            LTD., THIRUVANANTHAPURAM
            BY ADV R.HARISHANKAR


OTHER PRESENT:

            PRAVEEN K.JOY-R1,SR.GP.V.TEKCHAND,B.PRAMOD SC ,KSEB


        THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
08.04.2024,     ALONG WITH CRP.74/2022, THE COURT ON 21.05.2024,
DELIVERED THE FOLLOWING:
 CRP Nos.367 of 2021 & 74 of 2022

                                   -2-



              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                               PRESENT
                 THE HONOURABLE MR.JUSTICE V.G.ARUN
    TUESDAY, THE 21ST DAY OF MAY 2024 / 31ST VAISAKHA, 1946
                         CRP NO. 74 OF 2022
AGAINST THE ORDER/JUDGMENT DATED IN OPELE NO.1225 OF 2014 OF
VI ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:

             POWER GRID CORPORATION OF INDIA LTD
             POWER GRID CORPORATION OF INDIA LTD CONSTRUCTION
             AREA OFFICE, MAVELIPURAM COLONY, KAKKANAD, COCHIN -
             682 030, PRESENTLY AT CONSTRUCTION AREA OFFICE,
             400/220, KV SUB STATION, KUMARAPURAM P.O.,
             PALLIKKARA, ERNAKULAM - 683 565, REPRESENTED BY ITS
             SENIOR GENERAL MANAGER.
             BY ADV MILLU DANDAPANI

RESPONDENT/S:

     1       GEORGE JOSEPH
             AGED 57 YEARS
             S/O JOSEOH, KOZHUKKATTA HOUSE, CHERANALLOOR P.O,
             KOOVAPPADY, ERNAKULAM, PIN - 683544
     2       THE SPECIAL TAHSILDAR (LA)
             POWER GRID CORPORATION OF INDIA LTD., THRIKKAKKRA
             VILLAGE, KANAYANNUR TALUK, KAKKANAD, ERNAKULAM-
             682030
     3       STATE OF KERALA
             REPRESENTED BY DISTRICT COLLECTOR, CIVIL STATION,
             KAKKANAD, ERNAKULAM, KOCHI - 682 030.
     4       KERALA STATE ELECTRICITY BOARD
             REPRESENTED BY CHAIRMAN & MANAGING DIRECTOR, KSEB
             LTD., VAIDHYTHI BHAVAN, PATTOM P.O.,
             THIRUVANANTHAPURAM - 695 004.
             BY ADV P.T.JOSE

         THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
08.04.2024,     ALONG WITH CRP.367/2021, THE COURT ON 21.05.2024,
DELIVERED THE FOLLOWING:
 CRP Nos.367 of 2021 & 74 of 2022

                                   -3-



                              ORDER

Dated this the 21st day of May, 2024

These revision petitions are filed

challenging the order passed by the Additional

District Judge-VI, Ernakulam in O.P.(Electricity)

No.1225 of 2014. The original petition was filed

by the revision petitioner in CRP No.367 of 2021

(hereinafter called 'the claimant'), being

dissatisfied with the compensation awarded

towards the damage and loss sustained due to the

drawing of 400 KV lines across his property by

the Power Grid Corporation of India Ltd

(hereinafter called 'the Corporation'). The

essential facts are as under;

The claimant is in ownership and possession

of landed property having an extent of 7.23 Ares

comprised in Re-Sy.No.41/15 of Koovappady Village

in Kunnathunadu Taluk. The land was cultivated

with various yielding and non-yielding trees. CRP Nos.367 of 2021 & 74 of 2022

According to the claimant, to facilitate drawing

of the lines and smooth transmission of power,

large number of trees were cut from his property.

The drawing of high tension lines rendered the

land underneath and adjacent to the lines

useless, resulting in diminution of the value of

the property. In spite of the huge loss suffered

by the claimant, only an amount of Rs.54,665/-

was paid as compensation towards the value of

yielding and non-yielding trees cut.

Surprisingly, no compensation was granted for

diminution in land value. Hence, the original

petition was filed, seeking enhanced compensation

towards the value of trees cut and diminution in

land value.

2. The court below allowed the claim for

enhanced compensation for the value of trees cut

by awarding 50% of the compensation already

granted by the Corporation. Thus, the claimant

was found entitled for Rs.27,332/- towards the CRP Nos.367 of 2021 & 74 of 2022

value of trees cut. As far as the claim for

enhanced compensation towards diminution in land

value is concerned, the court below relied on

Ext.A4 document as well as Exts.C5 and C5(a)

commission report and plan. The court below took

note of the fact that the Thottuva - Kalady road

lies at a distance of about 450 metres on the

northern side of the petition schedule property

and a pathway having a width of 2.4 metres that

starts from the claimant's property leads to the

said road. Based on these factors, the court

below fixed the land value of the claimant's

property at Rs.1,53,000/- per cent, which is

equivalent to 10% less than the land value of the

property involved in Ext.A4 document. Relying on

Ext.C5(a) sketch, the extent of central corridor

was held to be 7.215 cents and that of the outer

corridor, 10.650 cents. For the central corridor,

40% of the land value was granted as compensation

and for outer corridor, 20% of the land value. CRP Nos.367 of 2021 & 74 of 2022

After taking into account the fact that the

entire petition schedule property is covered by

the central and outer corridors and a portion of

the line passes across the residential building,

the court below granted Rs.5,00,000/- as

compensation on that account. Accordingly, the

claimant was found entitled to compensation of

Rs.12,67,448/- towards diminution in land value.

Dissatisfied with the quantum of enhancement, the

claimant has filed CRP No.367 of 2021, whereas

the Corporation has filed CRP No.74 of 2022

contending that the enhancement ordered is far in

excess of the actual damage sustained.

3. Heard Adv.P.T.Jose for the claimant and

Adv.Millu Dandapani for the Corporation.

4. Learned Counsel for the claimant

contended that the court below committed gross

illegality in granting only 50% of the amount

already paid as enhanced compensation for the

loss sustained due to the cutting of valuable CRP Nos.367 of 2021 & 74 of 2022

trees, in spite of the Advocate Commissioner

assessing and reporting the loss. It is submitted

that the Thottuva - Kalady road lies at a

distance of about 450 metres on the northern side

of the petition schedule property and a pathway

having a width of 2.4 metres that starts from the

claimant's property leads to the said road.

Without properly considering these crucial

factors, the land value of the property is fixed

as only Rs.1,53,000/- per cent.

5. It is submitted that the court below

grossly erred in granting only 40% of the land

value for the central corridor and 20% for the

outer corridor. It is further submitted that the

court below is not justified in granting only

Rs.5,00,000/- as compensation, even after finding

the entire petition schedule property is covered

by the corridors and a portion of the line also

passes across the residential building situated

in the property. According to the learned CRP Nos.367 of 2021 & 74 of 2022

Counsel, considering the extent of damage

sustained and the diminution in land value

consequent to the drawing of lines, the court

below ought to have granted compensation as

claimed.

6. Learned Counsel for the Corporation

contended that the compensation granted towards

the trees cut and diminution in land value is

exorbitant and there is no rationale in granting

9% interest on that amount. The court below also

erred in relying on Ext.A4 for fixing the land

value of the claimant's property. As the drawing

of electric lines does not prohibit the landowner

from conducting agricultural activities and

putting up small structures, 40% of the land

value granted for the central corridor and 20%

for the outer corridor are exorbitant. According

to the learned Counsel, the court below grossly

erred in granting Rs.5,00,000/- as compensation

towards injurious affection on the house and for CRP Nos.367 of 2021 & 74 of 2022

the remaining property, which is in no way

affected.

7. The court below had awarded 50% of the

compensation already granted as additional

compensation towards the value of trees cut,

based on the Commission report as well as the

Detailed Valuation Statement. A careful scrutiny

of the impugned order reveals that the claim for

enhancement of compensation towards the value of

trees cut was rightly considered on the basis of

available evidence produced.

8. For fixing the compensation payable

towards diminution in land value, the factors to

be taken into consideration, as laid down in

KSEB v. Livisha [(2007) 6 SCC 792] are as under;

"10. The situs of the land, the distance between the high voltage electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small tract of land or through the middle of the land and other similar relevant factors in our opinion CRP Nos.367 of 2021 & 74 of 2022

would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used."

On careful scrutiny of the impugned order, it is

seen that, in the case at hand, the compensation

was fixed after taking all the above factors into

consideration. The nature of the land, the

cultivation therein, and the manner in which the

land was affected by drawing of the lines are all

seen considered for fixing the land value as well

as the percentage of diminution. Based on the

above factors and a comparison of the petition

schedule property with the property involved in

Ext.A4, the court below fixed the land value at

Rs.1,53,000/- per cent, viz; 10% less than the

land value of the property involved in Ext.A4

document, which according to me, is reasonable.

Similarly, the discretion was properly exercised

by the court below in granting 40% of the land CRP Nos.367 of 2021 & 74 of 2022

value for the central corridor and 20% for the

outer corridor. Taking into account the fact that

the entire petition schedule property is covered

by the corridors and a portion of the line passes

across the residential building situated in the

property, the court below has granted

Rs.5,00,000/- as compensation to the claimant,

which also I find to be just and proper.

9. The contention of the Corporation that

the Government having fixed the fair value, the

court below could not have fixed a higher value

is liable to be rejected since, while assessing

the damage sustained and fixing the compensation,

the court is not bound by the guidelines/orders

issued by the Government. The contention that

the court below committed an illegality in

awarding 9% interest cannot also be sustained in

the light of the decision of this Court in V.V.

Jayaram v Kerala State Electricity Board [2015

(3) KHC 453]. As such, there is no illegality or CRP Nos.367 of 2021 & 74 of 2022

material irregularity in the impugned order,

warranting intervention by this Court in exercise

of the revisional power under Section 115 of the

Code of Civil Procedure.

For the aforementioned reasons, the civil

revision petitions filed by the claimant as well

as the Corporation are dismissed. The enhanced

compensation fixed by the court below shall be

paid within three months of receipt of a copy of

this order. If any amount is deposited pursuant

to the order of this Court or otherwise, the same

shall forthwith be released to the claimant on

his filing appropriate application.

Sd/-

V.G.ARUN JUDGE Scl/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter