Tuesday, 21, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Power Grid Corporation Of India Ltd vs P.D.Davis
2024 Latest Caselaw 12525 Ker

Citation : 2024 Latest Caselaw 12525 Ker
Judgement Date : 21 May, 2024

Kerala High Court

Power Grid Corporation Of India Ltd vs P.D.Davis on 21 May, 2024

Author: V.G.Arun

Bench: V.G.Arun

              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                PRESENT
                 THE HONOURABLE MR.JUSTICE V.G.ARUN
    TUESDAY, THE 21ST DAY OF MAY 2024 / 31ST VAISAKHA, 1946
                         CRP NO. 384 OF 2021
AGAINST THE ORDER/JUDGMENT DATED IN OPELE NO.902 OF 2013 OF VI
ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:

            POWER GRID CORPORATION OF INDIA LTD
            CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY,
            KAKKANAD, COCHIN 682 030, PRESENTLY AT CONSTRUCTION
            AREA OFFICE, 400/220 KV SUB STATION, KUMARAPURAM
            P.O., PALLIKKARA, ERNAKULAM-683 565, REP.BY ITS
            SENIOR GENERAL MANAGER
            BY ADV MILLU DANDAPANI


RESPONDENT/S:

    1       P.D.DAVIS
            AGED 58 YEARS
            S/O.DEVASSY, RESIDING AT PAYAMPILLY HOUSE,
            PARAPPURAM P.O, KUNJOOR, ALUVA TALUK, MANJAPRA,
            KERALA 683 581
    2       THE SPECIAL TAHASILDAR (LA)
            POWER GRID CORPORATION OF INDIA LTD., CHEVARAMBALAM,
            KOZHIKODE 673 017
            BY ADV P.T.JOSE


OTHER PRESENT:

            B.PRAMOD SC KSEB,PRAVEEN K JOY-R1


        THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
22.02.2024,    ALONG   WITH   CRP.7/2022,   THE   COURT   ON   21.05.2024
DELIVERED THE FOLLOWING:
 CRP Nos.384 of 2021 and 7 of 2022

                                    -2-




              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                               PRESENT
                 THE HONOURABLE MR.JUSTICE V.G.ARUN
    TUESDAY, THE 21ST DAY OF MAY 2024 / 31ST VAISAKHA, 1946
                          CRP NO. 7 OF 2022
AGAINST THE ORDER/JUDGMENT DATED 20.03.2021 IN OPELE NO.902 OF
2013 OF VI ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:

             P.D. DAVIS
             AGED 62 YEARS
             S/O. DEVASSY, PAYYAMPILLI HOUSE, NOW RESIDING AT
             PARAPURAM P. O., KANJOOR, ALUVA TALUK, MANJAPRA P.
             O., ANGAMALY, ERNAKULAM DISTRICT - 683 581.
             BY ADV P.T.JOSE


RESPONDENT/S:

     1       POWER GRID CORPORATION OF INDIA LTD.
             CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY,
             KAKKANAD, COCHIN - 682030, NOW IN PAO/400, 220KV
             SUBSTATION, KUMARAPURAM P. O., PALLIKKARA, COCHIN -
             682030, REP. BY DEPUTY MANAGER.
     2       THE SPECIAL TAHSILDAR (LA)
             POWER GRID CORPORATION OF INDIA LTD., CHEVARAMBALAM,
             KOZHIKKODE - 673 017, NOW IN THRIKKAKARA VILLAGE,
             KANAYANNOOR TALUK, KAKKANAD P. O. - 682030.

         THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
22.02.2024, ALONG WITH CRP.384/2021, THE COURT ON 21.05.2024
DELIVERED THE FOLLOWING:
 CRP Nos.384 of 2021 and 7 of 2022

                                    -3-



                              ORDER
         Dated this the 21st day of             May, 2024



      These       revision           petitions        are      filed

challenging the order passed by the Additional

District Judge-VI, Ernakulam in O.P.(Electricity)

No.902 of 2013. The original petition was filed

by the revision petitioner in CRP No.7 of 2022

(hereinafter called 'the claimant'), being

dissatisfied with the compensation awarded

towards the damage and loss sustained due to the

drawing of 400 KV lines across his property by

the Power Grid Corporation of India Ltd

(hereinafter called 'the Corporation'). The

essential facts are as under;

The claimant is in ownership and possession

of landed property having an extent of 55 cents

comprised in Sy.No.181 of Ayyampuzha Village in

Aluva Taluk. The land was cultivated with various

yielding and non-yielding trees. According to the

claimant, to facilitate drawing of the lines and CRP Nos.384 of 2021 and 7 of 2022

smooth transmission of power, large number of

trees were cut from his property. The drawing of

high tension lines rendered the land underneath

and adjacent to the lines useless, resulting in

diminution of the value of the property. In spite

of the huge loss suffered by the claimant, only

an amount of Rs.2,97,278/- was paid as

compensation towards the value of yielding and

non-yielding trees cut. Surprisingly, no

compensation was granted for diminution in land

value. Hence, the original petition was filed,

seeking enhanced compensation towards the value

of trees cut and diminution in land value.

2. The court below rejected the claim for

enhanced compensation for the value of trees cut

since no evidence in support of the claim was

produced. As far as the claim for enhanced

compensation towards diminution in land value is

concerned, the court below relied on Ext.A7

document as well as Exts.C5 and C5(a) commission

report and sketch. The Advocate Commissioner CRP Nos.384 of 2021 and 7 of 2022

reported that the claimant's property is situated

at a distance of 200 metres from the Panchayat

road and the Manjapra - Chully road lies at a

distance of 1.6 Km. It is also reported that the

Government LP School, Primary Health Centre, GK

Granite and Fathima Matha Church are situated

within a radius of 2 Km. The court below also

took note of the fact that while the property in

Ext.A7 document is having public road access on

two sides, the petition schedule property has no

road access on either side. Based on these

factors, the court below fixed the land value of

the claimant's property at Rs.2,02,571/- per

cent, by deducting 10% of the land value of the

property involved in Ext.A7 document. Relying on

Ext.C5(a) sketch, the extent of central corridor

was held to be 11.710 cents and that of the

outer corridors, 10.325 (10.250 + 0.075) cents.

Taking into account the fact that the remaining

property admeasuring 4 cents is also affected due

to the drawing of electric lines, the court below CRP Nos.384 of 2021 and 7 of 2022

has awarded Rs.1,00,000/- as compensation on that

account. For the central corridor, 40% of the

land value was granted as compensation and for

outer corridors, 20% of the land value.

Accordingly, the claimant was found entitled to

compensation of Rs.14,67,150/-. Dissatisfied with

the quantum of enhancement, the claimant has

filed CRP No.7 of 2022, whereas the Corporation

has filed CRP No.384 of 2021 contending that the

enhancement ordered is far in excess of the

actual damage sustained.

3. Heard Adv.P.T.Jose for the claimant and

Adv.Millu Dandapani for the Corporation.

4. Learned Counsel for the claimant

contended that the court below committed gross

illegality in refusing to grant enhanced

compensation for the loss sustained due to the

cutting of valuable trees, in spite of the

Advocate Commissioner assessing and reporting the

loss. The findings in the Commissioner's report

were not relied on by the court below for the CRP Nos.384 of 2021 and 7 of 2022

reason that the property was inspected much after

the trees were cut. The said reasoning is flawed

since the trees were cut much after issuance of

notification by the Corporation and the cause of

action for filing the original petition arose

only on payment of the initial compensation, even

later. It is submitted that the claimant's

property is situated at a distance of 200 metres

from the Panchayat road and the Manjapra-Chully

road lies at a distance of 1.6 Km. Similarly, the

Government LP School, Primary Health Centre, GK

Granite and Fathima Matha Church are situated

within a radius of 2 Km from the property.

Without considering these crucial factors, 10%

deduction was made from the land value of the

property involved in Ext.A7 document.

5. It is submitted that the court below

grossly erred in granting only 40% of the land

value for the central corridor and 20% for outer

corridors. It is further submitted that the court

below is not justified in granting only CRP Nos.384 of 2021 and 7 of 2022

Rs.1,00,000/-, for the remaining property.

According to the learned Counsel, considering the

extent of damage sustained and the diminution in

land value consequent to the drawing of lines,

the court below ought to have granted

compensation as claimed.

6. Learned Counsel for the Corporation

contended that the compensation granted towards

diminution in land value is exorbitant and there

is no rationale in granting 9% interest on that

amount. The court below also erred in relying on

Ext.A7 for fixing the land value of the

claimant's property. As the drawing of electric

lines does not prohibit the landowner from

conducting agricultural activities and putting up

small structures, 40% of land value granted for

central corridor and 20% for the outer corridors

are exorbitant. According to the learned Counsel,

the court below grossly erred in granting

Rs.1,00,000/- towards the remaining property,

which is in no way affected.

CRP Nos.384 of 2021 and 7 of 2022

7. A careful scrutiny of the impugned order

reveals that the claim for enhancement of

compensation towards the value of trees cut was

rightly rejected in the absence of any

supporting material, other than the findings in

the Advocate Commissioner's report. As found by

the court below, apart from the interested

testimony of a witness, the claimant in one of

the connected cases, no other independent witness

was examined. The court below also took note of

the fact that the Commissioner's assessment was

based on the Mahazar, whereas the Corporation has

assessed the compensation on the basis of details

furnished by the Government departments. It was

therefore held that the evidence let in by the

claimant was not sufficient to discard the

contemporaneous valuation statement prepared by

the Corporation.

8. For fixing the compensation payable

towards diminution in land value, the factors to

be taken into consideration, as laid down in CRP Nos.384 of 2021 and 7 of 2022

KSEB v. Livisha [(2007) 6 SCC 792] are as under;

"10. The situs of the land, the distance between the high voltage electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small tract of land or through the middle of the land and other similar relevant factors in our opinion would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used."

On careful scrutiny of the impugned order, it is

seen that, in the case at hand, the compensation

was fixed after taking all the above factors into

consideration. The nature of the land, the

commercial importance of the area and the manner

in which the land was affected by drawing of the

lines are all seen considered for fixing the land

value as well as the percentage of diminution.

Based on the above factors and a comparison of

the petition schedule property with the property CRP Nos.384 of 2021 and 7 of 2022

involved in Ext.A7, the court below fixed the

land value at Rs.2,02,571/- per cent, viz; 10%

less than the value shown in Ext.A7 document,

which according to me, is reasonable. Similarly,

the discretion was properly exercised by the

court below in granting 40% of the land value as

compensation for the central corridor and 20% for

the outer corridors. The court below has granted

Rs.1,00,000/- as compensation for the remaining

property affected due to the drawing of electric

lines, which also I find to be just and proper.

9. The contention of the Corporation that

the Government having fixed the fair value, the

court below could not have fixed a higher value

is liable to be rejected since, while assessing

the damage sustained and fixing the compensation,

the court is not bound by the guidelines/orders

issued by the Government. The contention that

the court below committed an illegality in

awarding 9% interest cannot also be sustained in

the light of the decision of this Court in V.V. CRP Nos.384 of 2021 and 7 of 2022

Jayaram v Kerala State Electricity Board [2015

(3) KHC 453]. As such, there is no illegality or

material irregularity in the impugned order,

warranting intervention by this Court in exercise

of the revisional power under Section 115 of the

Code of Civil Procedure.

For the aforementioned reasons, the civil

revision petitions filed by the claimant as well

as the Corporation are dismissed. The enhanced

compensation fixed by the court below shall be

paid within three months of receipt of a copy of

this order. If any amount is deposited pursuant

to the order of this Court or otherwise, the same

shall forthwith be released to the claimant on

his filing appropriate application.

Sd/-

V.G.ARUN JUDGE Scl/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter