Tuesday, 21, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Power Grid Corporation Of India vs Suresh P A
2024 Latest Caselaw 12517 Ker

Citation : 2024 Latest Caselaw 12517 Ker
Judgement Date : 21 May, 2024

Kerala High Court

Power Grid Corporation Of India vs Suresh P A on 21 May, 2024

Author: V.G.Arun

Bench: V.G.Arun

              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                              PRESENT
                 THE HONOURABLE MR.JUSTICE V.G.ARUN
    TUESDAY, THE 21ST DAY OF MAY 2024 / 31ST VAISAKHA, 1946
                        CRP NO. 372 OF 2021
AGAINST THE ORDER/JUDGMENT DATED IN OPELE NO.587 OF 2013 OF VI
ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:

            SURESH P A
            AGED 55 YEARS
            S/O.AYYAPPANKUTTY, PEECHAMPILLI HOUSE,
            ELABAKKAPPILLI, AYMURIKKARA, KOOVAPPADY VILLAGE,
            KUNNATHUNADU TALUK, 683 544
            BY ADV P.T.JOSE


RESPONDENT/S:

    1       POWER GRID CORPORATION OF INDIA LTD
            CONSTRUCTION AREA OFFICE, KAKKANAD, NOW IN PAO/400,
            220KV SUBSTATION, KUMARAPURAM P.O., PALLIKARA, KOCHI
            682 303, REP.BY DEPUTY MANAGER
    2       THE SPECIAL TAHSILDAR (L.A.)
            POWER GRID CORPORATION OF INDIA, CHEVARAMBALAM,
            KOZHIKODE, NOW NEAR CIVIL STATION, KAKKANAD,
            ERNAKULAM DISTRICT, PIN 682 030
    3       STATE OF KERALA
            REP.BY DISTRICT COLLECTOR, ERNAKULAM, KOCHI 682 030
    4       KERALA STATE ELECTRICITY BOARD,
            REP.BY CHAIRMAN AND MANAGING DIRECTOR, KSEB LTD.,
            THIRUVANANTHAPURAM 695 001
            BY ADV R.HARISHANKAR


OTHER PRESENT:

            SR.GP.K.P.HARISH,A.ARUN KUMAR SC,KSEB.,PRAVEEN K.JOY


        THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
19.02.2024,     ALONG WITH CRP.165/2022, THE COURT ON 21.05.2024
DELIVERED THE FOLLOWING:
 CRP Nos.372 of 2021 and 165 of 2022

                                 -2-




              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                               PRESENT
                 THE HONOURABLE MR.JUSTICE V.G.ARUN
    TUESDAY, THE 21ST DAY OF MAY 2024 / 31ST VAISAKHA, 1946
                         CRP NO. 165 OF 2022
AGAINST THE ORDER/JUDGMENT DATED IN OPELE NO.587 OF 2013 OF VI
ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:

             POWER GRID CORPORATION OF INDIA
             CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY,
             KAKKANAD, COCHIN - 682 030, PRESENTLY AT
             CONSTRUCTION AREA OFFICE, 400/220, KV SUB STATION,
             KUMARAPURAM P.O, PALLIKKARA, ERNAKULAM - 683 565,
             REPRESENTED BY ITS SENIOR GENERAL MANAGER, PIN -
             683565
             BY ADV MILLU DANDAPANI


RESPONDENT/S:

     1       SURESH P A
             AGED 47 YEARS
             S/O AYYAPPANKUTTY, AGED 47 YEARS, PEECHAMPILLY
             HOUSE,ELAMBAKKAPILLI, AYMURIKKARA, KOOVAPPADY
             VILLAGE, KUNNATHUNADU TALUK, PIN - 683544
     2       THE SPECIAL TAHSILDAR (LA)
             POWER GRID CORPORATION OF INDIA LTD. CHEVARAMBALAM,
             KOZHIKODE - 673 017, PIN - 673017
     3       STATE OF KERALA
             REPRESENTED BY DISTRICT COLLECTOR, ERNAKULAM, KOCHI
             - 682 030, PIN - 682030
     4       KERALA STATE ELECTRICITY BOARD
             REPRESENTED BY CHAIRMAN & MANAGING DIRECTOR KSEB
             LTD., THIRUVANANTHAPURAM - 695 001, PIN - 695001
             BY ADV P.T.JOSE

         THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON

19.02.2024,     ALONG WITH CRP.372/2021, THE COURT ON 21.05.2024

DELIVERED THE FOLLOWING:
 CRP Nos.372 of 2021 and 165 of 2022

                                 -3-



                                ORDER

Dated this the 21st day of May, 2024

These revision petitions are filed

challenging the order passed by the Additional

District Judge-VI, Ernakulam in O.P.(Electricity)

No.587 of 2013. The original petition was filed

by the revision petitioner in CRP No.372 of 2021

(hereinafter called 'the claimant'), being

dissatisfied with the compensation awarded

towards the damage and loss sustained due to the

drawing of 400 KV lines across his property by

the Power Grid Corporation of India Ltd

(hereinafter called 'the Corporation'). The

essential facts are as under;

The claimant is in ownership and possession

of landed property having an extent of 4.13 Ares

in Sy.No.220/2 of Koovappady Village in

Kunnathunadu Taluk. The land was cultivated with

various yielding and non-yielding trees. CRP Nos.372 of 2021 and 165 of 2022

According to the claimant, to facilitate drawing

of the lines and smooth transmission of power,

large number of trees were cut from his property.

The drawing of high tension lines rendered the

land underneath and adjacent to the lines

useless, resulting in diminution of the value of

the property. In spite of the huge loss suffered

by the claimant, only an amount of Rs.25,500/-

was paid as compensation towards the value of

yielding and non-yielding trees cut.

Surprisingly, no compensation was granted for

diminution in land value. Hence, the original

petition was filed, seeking enhanced compensation

towards the value of trees cut and diminution in

land value.

2. The court below rejected the claim for

enhanced compensation for the value of trees cut

since no evidence in support of the claim was

produced. As far as the claim for enhanced

compensation towards diminution in land value is

concerned, the court below relied on Ext.A7 CRP Nos.372 of 2021 and 165 of 2022

document as well as Exts.C13 and C13(a)

commission report and sketch. The court below

adopted the land value in Ext.A7 document.

Relying on Ext.C13(a) sketch, the extent of

central corridor was held to be 7.165 cents and

that of the outer corridor, 3.040 cents. The

court below also took note of the fact that a

house is situated in the extent covered by the

central corridor and has granted Rs.2,00,000/- as

compensation on that account. For the central

corridor, 40% of the land value was granted as

compensation and for outer corridor, 20% of the

land value. Since it was found that a small

portion of land is left as remaining property and

the entire property is affected by the drawing of

electric lines, the court below has also granted

Rs.1,00,000/- to the claimant. Accordingly, the

claimant was found entitled to compensation of

Rs.8,90,371/-. Dissatisfied with the quantum of

enhancement, the claimant has filed CRP No.372 of

2021, whereas the Corporation has filed CRP CRP Nos.372 of 2021 and 165 of 2022

No.165 of 2022 contending that the enhancement

ordered is far in excess of the actual damage

sustained.

3. Heard Adv.P.T.Jose for the claimant and

Adv.Millu Dandapani for the Corporation.

4. Learned Counsel for the claimant

contended that the court below committed gross

illegality in refusing to grant enhanced

compensation for the loss sustained due to the

cutting of valuable trees, in spite of the

Advocate Commissioner assessing and reporting the

loss. The findings in the Commissioner's report

were not relied on by the court below for the

reason that the property was inspected much after

the trees were cut. The said reasoning is flawed

since the trees were cut much after issuance of

notification by the Corporation and the cause of

action for filing the original petition arose

only on payment of the initial compensation, even

later.

5. It is submitted that the court below CRP Nos.372 of 2021 and 165 of 2022

grossly erred in granting only 40% of the land

value for the central corridor and 20% for the

outer corridor. It is further submitted that the

court below is not justified in granting only

Rs.2,00,000/- towards the injurious affection on

house situated in the extent covered by central

corridor and Rs.1,00,000/- as compensation even

after finding the entire property is affected due

to the drawing of electric lines. According to

the learned Counsel, considering the extent of

damage sustained and the diminution in land value

consequent to the drawing of lines, the court

below ought to have granted compensation as

claimed.

6. Learned Counsel for the Corporation

contended that the compensation granted towards

diminution in land value is exorbitant and there

is no rationale in granting 9% interest on that

amount. The court below also erred in relying on

Ext.A7 for fixing the land value of the

claimant's property. As the drawing of electric CRP Nos.372 of 2021 and 165 of 2022

lines does not prohibit the landowner from

conducting agricultural activities and putting up

small structures, 40% of the land value granted

for the central corridor and 20% for the outer

corridor are exorbitant. According to the learned

Counsel, the court below grossly erred in

granting Rs.2,00,00/- towards the injurious

affection on the house and Rs.1,00,000/- for the

property, which is in no way affected.

7. A careful scrutiny of the impugned order

reveals that the claim for enhancement of

compensation towards the value of trees cut was

rightly rejected in the absence of any

supporting material other than the findings in

the Advocate Commissioner's report. As found by

the court below, apart from the interested

testimony of a witness, the claimant in some of

the connected cases, no other independent witness

was examined. The court below also took note of

the fact that the trees had been cut and removed

in the year 2011, whereas the Commissioner CRP Nos.372 of 2021 and 165 of 2022

inspected the property much later. Therefore, the

court below rightly refused to accept the

assessment made by the Commissioner, which was

based on an overview of the remaining trees in

the petition schedule and neighbouring

properties. On the other hand, the Corporation

had assessed the yield on the basis of local

inspection, enquiry and data furnished by the

Government departments. Hence, it was rightly

held by the court below that the evidence let in

by the claimant is not sufficient to discard the

contemporaneous valuation statement prepared by

the Corporation.

8. For fixing the compensation payable

towards the diminution in land value, the factors

to be taken into consideration, as laid down in

KSEB v. Livisha [(2007) 6 SCC 792] are as under;

"10. The situs of the land, the distance between the high voltage electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line CRP Nos.372 of 2021 and 165 of 2022

passes over a small tract of land or through the middle of the land and other similar relevant factors in our opinion would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used."

On careful scrutiny of the impugned order, it is

seen that, in the case at hand, the compensation

was fixed after taking all the above factors into

consideration. The nature of the land, the

cultivation therein, the commercial importance of

the area and the manner in which the land was

affected by drawing of the lines are all seen

considered for fixing the land value as well as

the percentage of diminution. After considering

the similarities of the properties involved, the

court below adopted the land value in Ext.A7

document, which according to me, is reasonable.

For the central corridor, 40% of the land value

was granted as compensation and for the outer CRP Nos.372 of 2021 and 165 of 2022

corridor, 20% of the land value, which also I

find to be just and proper. Similarly, the

discretion was properly exercised by the court

below in granting Rs.2,00,000/- towards injurious

affection on the house situated in the extent

covered by the central corridor and Rs.1,00,000/-

after finding that a small portion of land is

left as remaining property as well as the entire

property is affected due to the drawing of

electric lines.

9. The contention of the Corporation that

the Government having fixed the fair value, the

court below could not have fixed a higher value

is liable to be rejected since, while assessing

the damage sustained and fixing the compensation,

the court is not bound by the guidelines/orders

issued by the Government. The contention that

the court below committed an illegality in

awarding 9% interest cannot also be sustained in

the light of the decision of this Court in V.V.

Jayaram v Kerala State Electricity Board [2015 CRP Nos.372 of 2021 and 165 of 2022

(3) KHC 453]. As such, there is no illegality or

material irregularity in the impugned order,

warranting intervention by this Court in exercise

of the revisional power under Section 115 of the

Code of Civil Procedure.

For the aforementioned reasons, the civil

revision petitions filed by the claimant as well

as the Corporation are dismissed.

If any amount is deposited pursuant to the

order of this Court or otherwise, the same shall

forthwith be released to the claimant on his

filing appropriate application. The entire

enhanced compensation shall be paid to the

claimant within three months of receipt of a copy

of this order.

Sd/-

V.G.ARUN JUDGE Scl/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter