Tuesday, 21, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Power Grid Corporation Of India vs Siby Varky
2024 Latest Caselaw 12516 Ker

Citation : 2024 Latest Caselaw 12516 Ker
Judgement Date : 21 May, 2024

Kerala High Court

Power Grid Corporation Of India vs Siby Varky on 21 May, 2024

Author: V.G.Arun

Bench: V.G.Arun

              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                              PRESENT
                 THE HONOURABLE MR.JUSTICE V.G.ARUN
    TUESDAY, THE 21ST DAY OF MAY 2024 / 31ST VAISAKHA, 1946
                        CRP NO. 360 OF 2021
AGAINST THE ORDER/JUDGMENT DATED IN OPELE NO.548 OF 2013 OF VI
ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:

            SIBI VARKEY
            AGED 46 YEARS
            S/O VARKEY, AGED 46 YEARS, VADAKKEPURATHAN HOUSE,
            CHERANELLUR, KOOVAPPADY, KUNNATHUNADU.
            BY ADV P.T.JOSE


RESPONDENT/S:

    1       POWER GRID CORPORATION OF INDIA LTD.
            CONSTRUCTION AREA OFFICE, KAKKANAD, NOW IN PAO/400,
            220 KV SUBSTATION, KUMARAPURAM P.O., PALLIKARA,
            KOCHI-682 303, REP. BY DEPUTY MANAGER
    2       THE SPECIAL TAHSILDAR(L.A.)
            POWERGRID CORPORATION OF INDIA LTD., CHEVARAMBALAM,
            KOZHIKODE, NOW IN KAKKANAD P.O. 682 030
    3       ADDL.R3: STATE OF KERALA,
            REPRESENTED BY DISTRICT COLLECTOR, ERNAKULAM, KOCHI
    4       ADDL.R4: KERALA STATE ELECTRICITY BOARD
            REPRESENTED BY CHAIRMAN AND MANAGING DIRECTOR, KSEB
            LTD., THIRUVANANTHAPURAM
            BY ADV R.HARISHANKAR


OTHER PRESENT:

            A.ARUN KUMAR,K.P.HARISH SR.GP. PRAVEEN K. JOY-R1


        THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
19.02.2024,     ALONG WITH CRP.318/2022, THE COURT ON 21.05.2024
DELIVERED THE FOLLOWING:
 CRP Nos.360 of 2021 and 318 of 2022


                                 -2-



              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                              PRESENT
                THE HONOURABLE MR.JUSTICE V.G.ARUN
    TUESDAY, THE 21ST DAY OF MAY 2024 / 31ST VAISAKHA, 1946
                        CRP NO. 318 OF 2022
AGAINST THE ORDER/JUDGMENT DATED 31.03.2021 IN OPELE NO.548 OF
2013 OF VI ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:

           POWER GRID CORPORATION OF INDIA
           CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY,
           KAKKANAD, COCHIN - 682 030, PRESENTLY AT
           CONSTRUCTION AREA OFFICE, 400/220, KV SUB STATION,
           KUMARAPURAM P.O, PALLIKKARA, ERNAKULAM - 683 565,
           REPRESENTED BY ITS SENIOR GENERAL MANAGER, PIN -
           683565
           BY ADV MILLU DANDAPANI

RESPONDENT/S:
     1    SIBY VARKY
          AGED 47 YEARS, S/O VARKEY , AGED 47 YEARS ,
          VADAKKEPURATHAN HOUSE , CHERANELLUR , KOOVAPPADY ,
          KUNNATHNADU, PIN - 683544
     2    THE SPECIAL TAHSILDAR (LA), POWER GRID CORPORATION
          OF INDIA LTD. CHEVARAMBALAM, KOZHIKODE - 673 017,
          PIN - 673017
     3    STATE OF KERALA
          REPRESENTED BY DISTRICT COLLECTOR, ERNAKULAM, KOCHI
          - 682 030, PIN - 682030
     4    KERALA STATE ELECTRICITY BOARD
          KERALA STATE ELECTRICITY BOARD, REPRESENTED BY
          CHAIRMAN & MANAGING DIRECTOR KSEB LTD.,
          THIRUVANANTHAPURAM - 695 001, PIN - 695001
          BY ADVS.
          P.T.JOSE
          S.ASHITHA(K/000357/2018)

      THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
19.02.2024,    ALONG WITH CRP.360/2021, THE COURT ON 21.05.2024
DELIVERED THE FOLLOWING:
 CRP Nos.360 of 2021 and 318 of 2022


                                 -3-



                              ORDER

Dated this the 21st day of May, 2024

These revision petitions are filed

challenging the order passed by the Additional

District Judge-VI, Ernakulam in O.P.(Electricity)

No.548 of 2013. The original petition was filed

by the revision petitioner in CRP No.360 of 2021

(hereinafter called "the claimant"), being

dissatisfied with the compensation awarded

towards the damage and loss sustained due to the

drawing of 400 KV lines across his property by

the Power Grid Corporation of India Ltd

(hereinafter called "the Corporation"). The

essential facts are as under;

The claimant is in ownership and possession

of landed property having an extent of 4.86 Ares

comprised in Sy.No.101/13-2 of Koovappady Village

in Kunnathunadu Taluk. The land was cultivated

with various yielding and non- yielding trees. CRP Nos.360 of 2021 and 318 of 2022

According to the claimant, to facilitate drawing

of the lines and smooth transmission of power,

large number of trees were cut from his property.

The drawing of high tension lines rendered the

land underneath and adjacent to the lines

useless, resulting in diminution of the value of

the property. In spite of the huge loss suffered

by the claimant, only an amount of Rs.17,859/-

was paid as compensation towards the value of

yielding and non-yielding trees cut.

Surprisingly, no compensation was granted for

diminution in land value. Hence, the original

petition was filed, seeking enhanced compensation

towards the value of trees cut and diminution in

land value.

2. The court below rejected the claim for

enhanced compensation for the value of trees cut

since no evidence in support of the claim was

produced. As far as the claim for enhanced

compensation towards diminution in land value is CRP Nos.360 of 2021 and 318 of 2022

concerned, the court below relied on Ext.A7

document as well as Exts.C9 and C9(a) commission

report and sketch. The court below adopted the

land value of the property involved in Ext.A7

document. Relying on Ext.C9(a) sketch, the extent

of central corridor was held to be 5.660 cents

and that of the outer corridors, 5.735 cents

(5.660 + 0.075). For the central corridor, 40% of

the land value was granted as compensation and

for outer corridors, 20% of the land value. The

court below also took note of the fact that a

house is situated in the extent covered by the

corridors and has granted Rs.2,00,000/- as

compensation on that account. Similarly, taking

into account the fact that the entire petition

schedule property is affected due to the drawing

of electric lines, the court below has also

awarded a compensation of Rs.1,00,000/- to the

claimant. Accordingly, the claimant was found

entitled to compensation of Rs.8,79,665/-. CRP Nos.360 of 2021 and 318 of 2022

Dissatisfied with the quantum of enhancement, the

claimant has filed CRP No.360 of 2021, whereas

the Corporation has filed CRP No.318 of 2022

contending that the enhancement ordered is far in

excess of the actual damage sustained.

3. Heard Adv.P.T.Jose for the claimant and

Adv.Millu Dandapani for the Corporation.

4. Learned Counsel for the claimant contended

that the court below committed gross illegality

in refusing to grant enhanced compensation for

the loss sustained due to the cutting of valuable

trees, in spite of the Advocate Commissioner

assessing and reporting the loss. The findings in

the Commissioner's report were not relied on by

the court below for the reason that the property

was inspected much after the trees were cut. The

said reasoning is flawed since the trees were cut

much after issuance of notification by the

Corporation and the cause of action for filing

the original petition arose only on payment of CRP Nos.360 of 2021 and 318 of 2022

the initial compensation, even later.

5. It is submitted that the court below

grossly erred in granting only 40% of the land

value for the central corridor and 20% for outer

corridors. It is further submitted that the court

below is not justified in granting only

Rs.2,00,000/- towards injurious affection on the

house situated in the corridors and only

Rs.1,00,000/-, even after finding that the entire

petition schedule property is affected due to

drawing of electric lines. According to the

learned Counsel, considering the extent of damage

sustained and the diminution in land value

consequent to the drawing of lines, the court

below ought to have granted compensation as

claimed.

6. Learned Counsel for the Corporation

contended that, the compensation granted towards

diminution in land value is exorbitant and there

is no rationale in granting 9% interest on that CRP Nos.360 of 2021 and 318 of 2022

amount. The court below also erred in relying on

Ext.A7 for fixing the land value of the

claimant's property. As the drawing of electric

lines does not prohibit the landowner from

conducting agricultural activities and putting up

small structures, 40% of land value granted for

central corridor and 20% for the outer corridors

are exorbitant. According to the learned Counsel,

the court below grossly erred in granting

Rs.2,00,000/- towards the injurious affection on

the house and Rs.1,00,000/- for the property,

which is in no way affected.

7. A careful scrutiny of the impugned order

reveals that the claim for enhancement of

compensation towards the value of trees cut was

rightly rejected in the absence of any supporting

material other than the findings in the Advocate

Commissioner's report. As found by the court

below, apart from the interested testimony of a

witness, the claimant in some of the connected CRP Nos.360 of 2021 and 318 of 2022

cases, no other independent witnesses were

examined. Indisputably, the trees were cut and

removed in the year 2011 and the Commissioner

inspected the property much later. Therefore, the

court below rightly refused to accept the

assessment made by the Commissioner, which was

based on an overview of the remaining trees in

the petition schedule and the neighbouring

properties. On the other hand, the court below

found the Corporation to have assessed the yield

on the basis of local inspection, enquiry and

data furnished by the Government departments. It

was therefore held that the evidence let in by

the claimant was not sufficient to discard the

contemporaneous valuation statement prepared at

the instance of the Corporation.

8. As far as the diminution in land value

is concerned, the factors to be taken into

consideration, as laid down in KSEB v. Livisha

[(2007) 6 SCC 792] are as under;

CRP Nos.360 of 2021 and 318 of 2022

"10. The situs of the land, the distance between the high voltage electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small tract of land or through the middle of the land and other similar relevant factors in our opinion would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used."

On careful scrutiny of the impugned order, it is

seen that, in the case at hand, the compensation

was enhanced after taking all the above factors

into consideration. The nature of the land, the

commercial importance of the area and the manner

in which the land was affected by drawing of the

lines are all seen considered for fixing the land

value as well as the percentage of diminution.

The court below adopted the land value in Ext.A7

document, which according to me, is reasonable.

Similarly, the discretion was properly exercised CRP Nos.360 of 2021 and 318 of 2022

by the court below in granting 40% of the land

value as compensation for the central corridor

and 20% for the outer corridors. Taking into

account the fact that the house is situated in

the extent covered by the corridors, the court

below has granted Rs.2,00,000/- towards injurious

affection on the house and also granted

Rs.1,00,000/-, finding that the entire petition

schedule property is affected due to the drawing

of electric line, which also I find to be just

and proper.

9. The contention of the Corporation that

the Government having fixed the fair value, the

court below could not have fixed a higher value

is liable to be rejected since, while assessing

the damage sustained and fixing the compensation,

the court is not bound by the guidelines/orders

issued by the Government. The contention that

the court below committed an illegality in

awarding 9% interest cannot also be sustained in CRP Nos.360 of 2021 and 318 of 2022

the light of the decision of this Court in V.V.

Jayaram v Kerala State Electricity Board [2015

(3) KHC 453]. As such, there is no illegality or

material irregularity in the impugned order,

warranting intervention by this Court in exercise

of the revisional power under Section 115 of the

Code of Civil Procedure.

For the aforementioned reasons, the civil

revision petitions filed by the claimant as well

as the Corporation are dismissed. The enhanced

compensation fixed by the court below shall be

paid within three months of receipt of a copy of

this order. If any amount is deposited pursuant

to the order of this Court or otherwise, the same

shall forthwith be released to the claimant on

his filing appropriate application.

Sd/-

V.G.ARUN JUDGE Scl/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter