Citation : 2024 Latest Caselaw 12485 Ker
Judgement Date : 21 May, 2024
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE V.G.ARUN
TUESDAY, THE 21ST DAY OF MAY 2024 / 31ST VAISAKHA, 1946
CRP NO. 121 OF 2022
AGAINST THE ORDER/JUDGMENT DATED 29.03.2021 IN OPELE NO.121 OF
2013 OF VI ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:
1 SURESH
AGED 59 YEARS
S/O K A.KUTTAPPAN, KOTTAKKAL HOUSE, PADUVAPURAM,
KARUKUTTY, ANGAMALY.
2 KARTHIYAYINI
AGED 79 YEARS
W/O K A KUTTAPPAN, KOTTAKKAL HOUSE, PADUVAPURAM,
KARUKUTTY, ANGAMALY.
3 RAJI
AGED 53 YEARS
D/O K A KUTTAPPAN, KOTTAKKAL HOUSE, PADUVAPURAM,
KARUKUTTY, ANGAMALY.
BY ADV P.T.JOSE
RESPONDENT/S:
1 POWER GRID CORPORATION OF INDIA LTD
CORPORATION OF INDIA LTD, CONSTRUCTION AREA OFFICE,
MAVELIPURAM COLONY, KAKKANAD, COCHIN-682030. NOW IN
PAO/400,220KV SUBSTATION, KUMARAPURAM P O,
PALLIKARA, KOCHI-682303, REPRESENTED BY DEPUTY
MANAGER.
2 THE SPECIAL TAHSILDAR (LA)
POWER GRID CORPORATION OF INDIA LTD, CHEVARAMBALAM,
KOZHIKODE-673017, NOW IN THRIKKAKARA VILLAGE,
KANAYANNOOR TALUK, KAKKANAD P O, PIN-682030.
OTHER PRESENT:
PRAVEEN K.JOY-R1,A.ARUN KUMAR SC
THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD
ON28.02.2024, THE COURT ON 21.05.2024 DELIVERED THE
FOLLOWING:
CRP No.121 of 2022
-2-
ORDER
Dated this the 21st day of May, 2024
This revision petition is filed challenging
the order passed by the Additional District
Judge-VI, Ernakulam in O.P.(Electricity) No.121
of 2013. The original petition was filed by the
revision petitioners (hereinafter called 'the
claimants'), being dissatisfied with the
compensation awarded towards the damage and loss
sustained due to the drawing of 400 KV lines
across their property by the Power Grid
Corporation of India Ltd (hereinafter called 'the
Corporation'). The essential facts are as under;
The claimants are in ownership and possession
of landed property having an extent of 26 cents
comprised in Sy.No.190/1 of Karukutty Village in
Aluva Taluk. The land was cultivated with various
yielding and non-yielding trees. According to
the claimants, to facilitate drawing of the lines
and smooth transmission of power, large number of
trees were cut from their property. The drawing
of high tension lines rendered the land
underneath and adjacent to the lines useless,
resulting in diminution of the value of the
property. In spite of the huge loss suffered by
the claimants, only Rs.1,16,898/- was paid as
compensation towards the value of yielding and
non-yielding trees cut. Surprisingly, no
compensation was granted for diminution in land
value. Hence, the original petition was filed,
seeking enhanced compensation towards the value
of trees cut and diminution in land value.
2. The court below rejected the claim for
enhanced compensation for the value of trees cut
since no evidence in support of the claim was
produced. As far as the claim for enhanced
compensation towards diminution in land value is
concerned, the court below relied on Ext.A5
document as well as Exts.C13 and C13(a)
commission report and sketch. The Advocate
Commissioner reported that the petition schedule
property is situated at a distance of 400 metres
from the Government Higher Secondary School and
Government Hospital. It is also reported that
the petition schedule property lies at a distance
of 750 metres from St.George Church and 1 Km from
Naipunniya Public School. The court below also
took note of the fact that the petition schedule
property is situated at a distance of 100 metres
from the Karukutty Palissery Munnoorpilly Road,
which is a bus route and a canal road passes
through the southern side of the property. Based
on the said factors, the court below fixed the
land value of the petition schedule property at
Rs.1,80,063/- per cent, by deducting 20% of the
value shown in Ext.A5 document. Relying on
Ext.C13(a) sketch, the extent of central corridor
was held to be 3.953 cents and that of the outer
corridors, 5.165 cents (2.595+2.570). For the
central corridor, 40% of the land value was
granted as compensation and for outer corridors,
20% of the land value. Accordingly, the
claimants were found entitled to compensation of
Rs.4,70,720/-.
3. Heard Adv.P.T.Jose for the claimants
and Adv.Millu Dandapani for the Corporation.
4. Learned Counsel for the claimants
contended that the court below committed gross
illegality in refusing to grant enhanced
compensation for the loss sustained due to the
cutting of valuable trees, in spite of the
Advocate Commissioner assessing and reporting the
loss. The findings in the Commissioner's report
were not relied on by the court below for the
reason that the property was inspected much after
the trees were cut. The said reasoning is flawed
since the trees were cut much after issuance of
notification by the Corporation and the cause of
action for filing the original petition arose
only on payment of the initial compensation, even
later. It is submitted that the petition schedule
property is situated at a distance of 400 metres
from the Government Higher Secondary School and
Government Hospital. Similarly, the property lies
at a distance of 750 metres from St.George Church
and 1 Km from Naipunniya Public School.
Moreover, the petition schedule property is
situated at a distance of 100 metres from the
Karukutty Palissery Munnoorpilly Road, which is a
bus route and a canal road passes through the
southern side of the property. Without
considering these crucial factors, 20% deduction
was made from the value of the property involved
in Ext.A5 document.
5. It is further submitted that the court
below grossly erred in granting only 40% of the
land value for the central corridor and 20% for
the outer corridors. According to the learned
Counsel, considering the extent of damage
sustained and the diminution in land value
consequent to the drawing of lines, the court
below ought to have granted compensation as
claimed.
6. Learned Counsel for the Corporation
contended that, the compensation granted towards
diminution in land value is even otherwise
exorbitant and the drawing of electric lines does
not prohibit the landowners from conducting
agricultural activities and putting up small
structures.
7. A careful scrutiny of the impugned order
reveals that the claim for enhancement of
compensation towards the value of trees cut was
rightly rejected in the absence of any supporting
material, other than the findings in the Advocate
Commissioner's report. As found by the court
below, apart from the interested testimony of a
witness, the claimant in some of the connected
cases, no other independent witness was examined.
It is also not in dispute that the trees were cut
in the year 2011, whereas the Commissioner
inspected the property in the year 2015 and
assessed the value of the trees based on an
overview of the trees standing in the nearby
properties. Such comparison, having no scientific
basis, is not sufficient to discard the
contemporaneous valuation statement prepared by
the Corporation.
8. As far as the diminution in land value
is concerned, the factors to be taken into
consideration, as laid down in KSEB v. Livisha
[(2007) 6 SCC 792] are as under;
"10. The situs of the land, the distance between the high voltage electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small tract of land or through the middle of the land and other similar relevant factors in our opinion would be determinative. The value of the land would also be a relevant factor. The
owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used."
On careful scrutiny of the impugned order, it is
seen that the compensation was enhanced after
taking all the above factors into consideration.
The nature of the land, the cultivation therein
and the manner in which the land was affected by
drawing of the lines are all seen considered for
fixing the land value as well as the percentage
of diminution. Based on the above factors and a
comparison of the petition schedule property with
the property involved in Ext.A5, the court below
deducted 20% of the land value of the property in
Ext.A5 document, which according to me, is
reasonable. Similarly, the discretion vested with
it was properly exercised by the court below in
granting 40% of the land value as compensation
for central corridor and 20% for the outer
corridors. As such, there is no illegality or
material irregularity in the impugned order,
warranting intervention by this Court in exercise
of the revisional power under Section 115 of the
Code of Civil Procedure.
For the aforementioned reasons, the civil
revision petition is dismissed.
If any amount is deposited pursuant to the
order of this Court or otherwise, the same shall
forthwith be released to the claimants on their
filing appropriate application. The entire
enhanced compensation shall be paid to the
claimants within three months of receipt of a
copy of this order.
sd/-
V.G.ARUN JUDGE Scl/
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!