Tuesday, 21, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Santhosh vs Power Grid Corporation Of India
2024 Latest Caselaw 12453 Ker

Citation : 2024 Latest Caselaw 12453 Ker
Judgement Date : 21 May, 2024

Kerala High Court

Santhosh vs Power Grid Corporation Of India on 21 May, 2024

Author: V.G.Arun

Bench: V.G.Arun

              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                 PRESENT
                  THE HONOURABLE MR.JUSTICE V.G.ARUN
    TUESDAY, THE 21ST DAY OF MAY 2024 / 31ST VAISAKHA, 1946
                          CRP NO. 390 OF 2021
AGAINST    THE   ORDER   DATED   IN   OPELE   NO.444   OF   2013   OF   VI
ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:

            SANTHOSH
            AGED 47 YEARS
            S/O.NEELAKANDHANNAIR, MADAMPALLI HOUSE, CHERANATTU,
            KOOVAPPADY, PIN - 683 544.
            BY ADV P.T.JOSE


RESPONDENT/S:

    1       POWER GRID CORPORATION OF INDIA
            CONSTRUCTION AREA OFFICE, KAKKANAD, NOW IN PAO/400,
            220KV SUBSTATION, KUMARAPURAM P.O., PALLIKARA, KOCHI
            - 682 303 REP. BY DEPUTY MANAGER.
    2       THE SPECIAL TAHSILDAR (L.A.)
            POWERGRID CORPORATION OF INDIA LTD.,CHEVARAMBALAM,
            KOZHIKODE, NOW IN KAKKANAD, PIN -682 030, NEAR CIVIL
            STATION.
    3       STATE OF KERALA
            REPRESENTED BY DISTRICT COLLECTOR, ERNAKULAM, KOCHI
            - 682 021.
    4       KERALA STATE ELECTRICITY BOARD
            REPRESENTED BY CHAIRMAN AND MANAGING DIRECTOR, KSEB
            LTD., THIRUVANANTHAPURAM - 695 001.
            BY ADV R.HARISHANKAR


OTHER PRESENT:

            K.P.HARISH SR.G.P,A.ARUN KUMAR SC,PRAVEEN K.JOY SC


        THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
19.02.2024,      ALONG WITH CRP.314/2022, THE COURT ON 21.05.2024,
DELIVERED THE FOLLOWING:
 CRP Nos.390/2021 & 314/2022

                                 -2-




              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                               PRESENT
                 THE HONOURABLE MR.JUSTICE V.G.ARUN
    TUESDAY, THE 21ST DAY OF MAY 2024 / 31ST VAISAKHA, 1946
                         CRP NO. 314 OF 2022
AGAINST THE ORDER/JUDGMENT DATED 31.03.2021 IN OPELE NO.444 OF
2013 OF VI ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:

             POWER GRID CORPORATION OF INDIA
             CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY,
             KAKKANAD, COCHIN - 682 030, PRESENTLY AT
             CONSTRUCTION AREA OFFICE, 400/220, KV SUB STATION,
             KUMARAPURAM P.O, PALLIKKARA, ERNAKULAM REPRESENTED
             BY ITS SENIOR GENERAL MANAGER, PIN - 683565
             BY ADV MILLU DANDAPANI


RESPONDENT/S:

     1       SANTHOSH
             AGED 48 YEARS
             S/O. NEELAKANDAN NAIR, MADAMPALLI HOUSE, CHERANATTU,
             KOOVAPPADY VILLAGE, KUNNATHUNADU TALUK, PIN - 683544
     2       THE SPECIAL TAHSILDAR (LA)
             POWER GRID CORPORATION OF INDIA LTD. CHEVARAMBALAM,
             KOZHIKODE, PIN - 673017
     3       STATE OF KERALA
             REPRESENTED BY DISTRICT COLLECTOR, ERNAKULAM, KOCHI,
             PIN - 682030
     4       KERALA STATE ELECTRICITY BOARD - KSEB
             REPRESENTED BY CHAIRMAN & MANAGING DIRECTOR KSEB
             LTD., THIRUVANANTHAPURAM, PIN - 695001
             BY ADV P.T.JOSE


         THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
19.02.2024,     ALONG WITH CRP.390/2021, THE COURT ON 21.05.2024,
DELIVERED THE FOLLOWING:
 CRP Nos.390/2021 & 314/2022

                                   -3-



                                 ORDER

Dated this the 21st day of May, 2024

These revision petitions are filed

challenging the order passed by the Additional

District Judge-VI, Ernakulam in O.P.(Electricity)

No.444 of 2013. The original petition was filed

by the revision petitioner in CRP No.390 of 2021

(hereinafter called 'the claimant'), being

dissatisfied with the compensation awarded

towards the damage and loss sustained due to the

drawing of 400 KV lines across his property by

the Power Grid Corporation of India Ltd

(hereinafter called 'the Corporation'). The

essential facts are as under;

The claimant is in ownership and possession

of landed property having an extent of 18.20

Ares comprised in Sy.No.38/11 of Koovappady

Village in Kunathunadu Taluk. The land was

cultivated with various yielding and non-yielding CRP Nos.390/2021 & 314/2022

trees. According to the claimant, to facilitate

drawing of the lines and smooth transmission of

power, large number of trees were cut from his

property. The drawing of high tension lines

rendered the land underneath and adjacent to the

lines useless, resulting in diminution of the

value of the property. In spite of the huge loss

suffered by the claimant, only an amount of

Rs.2,39,847/- was paid as compensation towards

the value of yielding and non-yielding trees cut.

Surprisingly, no compensation was granted for

diminution in land value. Hence, the original

petition was filed, seeking enhanced compensation

towards the value of trees cut and diminution in

land value.

2. The court below rejected the claim for

enhanced compensation for the value of trees cut

since no evidence in support of the claim was

produced. As far as the claim for enhanced

compensation towards diminution in land value is

concerned, the court below relied on Ext.A7 CRP Nos.390/2021 & 314/2022

document as well as Exts.C6 and C6(a) commission

report and sketch. The court below adopted the

land value of the property involved in Ext.A7

document. Relying on Ext.C6(a) sketch, the extent

of central corridor was held to be 13.665 cents

and that of the outer corridors, 12.555 cents

(12.355 + 0.200). For the central corridor, 40%

of the land value was granted as compensation and

for outer corridors, 20% of the land value. The

court below also took note of the fact that a

major portion of the house is situated in the

extent covered by the central corridor and has

granted Rs.2,00,000/- on that account.

Similarly, Rs.1,00,000/- was awarded for the

remaining property admeasuring 5.630 cents.

Accordingly, the claimant was found entitled to

compensation of Rs.16,55,610/-. Dissatisfied

with the quantum of enhancement, the claimant has

filed CRP No.390 of 2021, whereas the Corporation

has filed CRP No.314 of 2022 contending that the CRP Nos.390/2021 & 314/2022

enhancement ordered is far in excess of the

actual damage sustained.

3. Heard Adv.P.T.Jose for the claimant and

Adv.Millu Dandapani for the Corporation.

4. Learned Counsel for the claimant

contended that the court below committed gross

illegality in refusing to grant enhanced

compensation for the loss sustained due to the

cutting of valuable trees, in spite of the

Advocate Commissioner assessing and reporting the

loss. The findings in the Commissioner's report

were not relied on by the court below for the

reason that the property was inspected much after

the trees were cut. The said reasoning is flawed

since the trees were cut much after issuance of

notification by the Corporation and the cause of

action for filing the original petition arose

only on payment of the initial compensation, even

later.

5. It is submitted that the court below

grossly erred in granting only 40% of the land CRP Nos.390/2021 & 314/2022

value for the central corridor and 20% for outer

corridors. It is further submitted that the

court below is not justified in granting

Rs.2,00,000/- towards injurious affection on the

house situated under the central corridor and

Rs.1,00,000/- as compensation for the remaining

property rendered useless due to drawing of the

electric lines. According to the learned Counsel,

considering the extent of damage sustained and

the diminution in land value consequent to the

drawing of lines, the court below ought to have

granted compensation as claimed.

6. Learned Counsel for the Corporation

contended that, the compensation granted towards

diminution in land value is exorbitant and there

is no rationale in granting 9% interest on that

amount. The court below also erred in relying on

Ext.A7 for fixing the land value of the

claimant's property. As the drawing of electric

lines does not prohibit the landowner from CRP Nos.390/2021 & 314/2022

conducting agricultural activities and putting up

small structures, 40% of land value granted for

central corridor and 20% for the outer corridors

are exorbitant. According to the learned Counsel,

the court below grossly erred in granting

Rs.2,00,000/- towards injurious affection on the

house and Rs.1,00,000/- for the remaining

property, which is in no way affected.

7. A careful scrutiny of the impugned order

reveals that the claim for enhancement of

compensation towards the value of trees cut was

rightly rejected in the absence of any

supporting material other than the findings in

the Advocate Commissioner's report. As found by

the court below, apart from the interested

testimony of a witness, the claimant in some of

the connected cases, no other independent witness

was examined. Indisputably, the trees had been

cut and removed in the year 2011, whereas the

Commissioner inspected the property much later.

Therefore, the court below rightly refused to CRP Nos.390/2021 & 314/2022

accept the assessment made by the Commissioner,

which was based on an overview of the remaining

trees standing in the petition schedule and

neighbouring properties. On the other hand, the

Corporation had assessed the yield on the basis

of local inspection, enquiry and data furnished

by the Government departments. Hence, it was

rightly held by the court below that the evidence

let in by the claimant is not sufficient to

discard the contemporaneous valuation statement

prepared by the Corporation.

8. For fixing the compensation payable

towards diminution in land value, the factors to

be taken into consideration, as laid down in

KSEB v. Livisha [(2007) 6 SCC 792] are as under;

"10. The situs of the land, the distance between the high voltage electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small tract of land or through the middle of the land and other similar relevant factors in our opinion CRP Nos.390/2021 & 314/2022

would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used."

On careful scrutiny of the impugned order, it is

seen that, in the case at hand, the compensation

was fixed after taking all the above factors into

consideration. The nature of the land, the

commercial importance of the area and the manner

in which the land was affected by drawing of the

lines are all seen considered for fixing the land

value as well as the percentage of diminution.

The court below adopted the land value in Ext.A7

document, which according to me, is reasonable.

Similarly, the discretion was properly exercised

by the court below in granting 40% of the land

value as compensation for the central corridor

and 20% for the outer corridors. I am of the

definite opinion that the court below is

justified in granting Rs.2,00,000/- towards CRP Nos.390/2021 & 314/2022

injurious affection on the house situated in the

extent covered by the central corridor and

Rs.1,00,000/- as compensation for the remaining

property.

9. The contention of the Corporation that

the Government having fixed the fair value, the

court below could not have fixed a higher value

is liable to be rejected since, while assessing

the damage sustained and fixing the compensation,

the court is not bound by the guidelines/orders

issued by the Government. The contention that the

court below committed an illegality in awarding

9% interest cannot also be sustained in the light

of the decision of this Court in V.V. Jayaram v

Kerala State Electricity Board [2015 (3) KHC

453]. As such, there is no illegality or material

irregularity in the impugned order, warranting

intervention by this Court in exercise of the

revisional power under Section 115 of the Code of

Civil Procedure.

CRP Nos.390/2021 & 314/2022

For the aforementioned reasons, the civil

revision petitions filed by the claimant as well

as the Corporation are dismissed. The enhanced

compensation fixed by the court below shall be

paid within three months of receipt of a copy of

this order. If any amount is deposited pursuant

to the order of this Court or otherwise, the same

shall forthwith be released to the claimant on

his filing appropriate application.

Sd/-

V.G.ARUN JUDGE Scl/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter