Citation : 2024 Latest Caselaw 12443 Ker
Judgement Date : 21 May, 2024
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE V.G.ARUN
TUESDAY, THE 21ST DAY OF MAY 2024 / 31ST VAISAKHA, 1946
CRP NO. 364 OF 2021
AGAINST THE ORDER/JUDGMENT DATED IN OPELE NO.547 OF 2013 OF VI
ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:
UNNIKRISHNAN P.M
AGED 59 YEARS
S/O. MADHAVAGURUKKAL PUTHENPURAYIL HOUSE,
CHERANALLOR, KOOVAPADI VILLAGE , KUNNATHUNADU TALUK,
ERNAKULAM, PIN - 683544
BY ADV P.T.JOSE
RESPONDENT/S:
1 POWER GRID CORPORATION OF INDIA
CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY,
KAKKANAD, COCHIN - 682 030, PRESENTLY AT
CONSTRUCTION AREA OFFICE, 400/220, KV SUB STATION,
KUMARAPURAM P.O, PALLIKKARA, ERNAKULAM REPRESENTED
BY ITS SENIOR GENERAL MANAGER, PIN - 683565
2 THE SPECIAL TAHSILDAR (L.R), POWER GRID CORPORATION
OF INDIA LTD.
CHEVERAMBALAM,KOZHIKODE, NOW IN KAKKANAD P.O, PIN -
682030
3 STATE OF KERALA REPRESENTED BY DISTRICT COLLECTOR
ERNAKULAM, KOCHI - 682021
4 KERALA STATE ELECTRICITY BOARD REPRESENTED BY
CHAIRMAN AND MANAGING DIRECTOR
KSEB LTD, THIRUVANANTHAPURAM - 695 001.
BY ADVS.
R.HARISHANKAR
SHRI.PRAVEEN K. JOY, POWER GRID CORPORATION OF INDIA
LIMITED
OTHER PRESENT:
K.A.HARISH SR. GP.,A,ARUN KUMAR SC KSEB,PRAVEEN
K.JOY R1
THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
19.02.2024, ALONG WITH CRP.200/2022, THE COURT ON 21.05.2024
DELIVERED THE FOLLOWING:
CRP Nos.364 of 2021 and 200 of 2022
-2-
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE V.G.ARUN
TUESDAY, THE 21ST DAY OF MAY 2024 / 31ST VAISAKHA, 1946
CRP NO. 200 OF 2022
AGAINST THE ORDER/JUDGMENT DATED 31.03.2021 IN OPELE NO.547 OF
2013 OF VI ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:
POWER GRID CORPORATION OF INDIA
CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY,
KAKKANAD, COCHIN - 682 030, PRESENTLY AT
CONSTRUCTION AREA OFFICE, 400/220, KV SUB STATION,
KUMARAPURAM P.O, PALLIKKARA, ERNAKULAM REPRESENTED
BY ITS SENIOR GENERAL MANAGER, PIN - 683565
BY ADV MILLU DANDAPANI
RESPONDENT/S:
1 UNNIKRISHNAN P.M
AGED 59 YEARS
S/O. MADHAVAGURUKKAL PUTHENPURAYIL HOUSE,
CHERANALLOR, KOOVAPADI VILLAGE , KUNNATHUNADU TALUK,
ERNAKULAM, PIN - 683544
2 THE SPECIAL TAHSILDAR (LA)
POWER GRID CORPORATION OF INDIA LTD. CHEVARAMBALAM,
KOZHIKODE, PIN - 673017
3 STATE OF KERALA
REPRESENTED BY DISTRICT COLLECTOR, ERNAKULAM, KOCHI,
PIN - 682030
4 KERALA STATE ELECTRICITY BOARD - KSEB
REPRESENTED BY CHAIRMAN & MANAGING DIRECTOR KSEB
LTD., THIRUVANANTHAPURAM, PIN - 695001
BY ADV P.T.JOSE
THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
19.02.2024, ALONG WITH CRP.364/2021, THE COURT ON 21.05.2024
DELIVERED THE FOLLOWING:
CRP Nos.364 of 2021 and 200 of 2022
-3-
CRP Nos.364 of 2021 and 200 of 2022
-4-
CRP Nos.364 of 2021 and 200 of 2022
-5-
ORDER
Dated this the 21st day of May, 2024
These revision petitions are filed
challenging the order passed by the Additional
District Judge-VI, Ernakulam in O.P.(Electricity)
No.547 of 2013. The original petition was filed
by the revision petitioner in CRP No.364 of 2021
(hereinafter called 'the claimant'), being
dissatisfied with the compensation awarded
towards the damage and loss sustained due to the
drawing of 400 KV lines across his property by
the Power Grid Corporation of India Ltd
(hereinafter called 'the Corporation'). The
essential facts are as under;
The claimant is in ownership and possession
of landed property having an extent of 19 Ares in
Sy.No.40/15 of Koovappady Village in Kunnathunadu
Taluk. The land was cultivated with various CRP Nos.364 of 2021 and 200 of 2022
yielding and non-yielding trees. According to
the claimant, to facilitate drawing of the lines
and smooth transmission of power, large number of
trees were cut from his property. The drawing of
high tension lines rendered the land underneath
and adjacent to the lines useless, resulting in
diminution of the value of the property. In
spite of the huge loss suffered by the claimant,
only an amount of Rs.1,14,523/- was paid as
compensation towards the value of yielding and
non-yielding trees cut. Surprisingly, no
compensation was granted for diminution in land
value. Hence, the original petition was filed,
seeking enhanced compensation towards the value
of trees cut and diminution in land value.
2. The court below rejected the claim for
enhanced compensation for the value of trees cut
since no evidence in support of the claim was
produced. As far as the claim for enhanced
compensation towards diminution in land value is
concerned, the court below relied on Ext.A7 CRP Nos.364 of 2021 and 200 of 2022
document as well as Exts.C8 and C8(a) commission
report and sketch. The court below adopted the
land value of the property involved in Ext.A7
document. Relying on Ext.C8(a) sketch, the extent
of central corridor was held to be 15.616 cents
and that of the outer corridors, 15.62 cents
(15.320 + 0.300). For the central corridor, 40%
of the land value was granted as compensation and
for the outer corridors, 20% of the land value.
Accordingly, the claimant was found entitled to
compensation of Rs.15,92,405/-. Dissatisfied with
the quantum of enhancement, the claimant has
filed CRP No.364 of 2021, whereas the Corporation
has filed CRP No.200 of 2022 contending that the
enhancement ordered is far in excess of the
actual damage sustained.
3. Heard Adv.P.T.Jose for the claimant and
Adv.Millu Dandapani for the Corporation.
4. Learned Counsel for the claimant
contended that the court below committed gross
illegality in refusing to grant enhanced CRP Nos.364 of 2021 and 200 of 2022
compensation for the loss sustained due to the
cutting of valuable trees, in spite of the
Advocate Commissioner assessing and reporting the
loss. The findings in the Commissioner's report
were not relied on by the court below for the
reason that the property was inspected much after
the trees were cut. The said reasoning is flawed
since the trees were cut much after issuance of
notification by the Corporation and the cause of
action for filing the original petition arose
only on payment of the initial compensation, even
later.
5. It is submitted that the court below
grossly erred in granting only 40% of the land
value for the central corridor and 20% for the
outer corridors. According to the learned
Counsel, considering the extent of damage
sustained and the diminution in land value
consequent to the drawing of lines, the court
below ought to have granted compensation as
claimed.
CRP Nos.364 of 2021 and 200 of 2022
6. Learned Counsel for the Corporation
contended that the compensation granted towards
diminution in land value is exorbitant and there
is no rationale in granting 9% interest on that
amount. The court below also erred in relying on
Ext.A7 for fixing the land value of the
claimant's property. As the drawing of electric
lines does not prohibit the landowner from
conducting agricultural activities and putting up
small structures, 40% of the land value granted
for the central corridor and 20% for the outer
corridors are exorbitant.
7. A careful scrutiny of the impugned order
reveals that the claim for enhancement of
compensation towards the value of trees cut was
rightly rejected in the absence of any supporting
material other than the findings in the Advocate
Commissioner's report. As found by the court
below, apart from the interested testimony of a
witness, the claimant in some of the connected
cases, no other independent witness was examined. CRP Nos.364 of 2021 and 200 of 2022
The court below also took note of the fact that
the trees had been cut and removed in the year
2011, whereas the Commissioner inspected the
property much later. Therefore, the court below
rightly refused to accept the assessment made by
the Commissioner, which was based on an overview
of the remaining trees in the petition schedule
and neighbouring properties. On the other hand,
the Corporation had assessed the yield on the
basis of local inspection, enquiry and data
furnished by the Government departments. Hence,
it was rightly held by the court below that the
evidence let in by the claimant is not sufficient
to discard the contemporaneous valuation
statement prepared by the Corporation.
8. For fixing the compensation payable
towards diminution in land value, the factors to
be taken into consideration, as laid down in
KSEB v. Livisha [(2007) 6 SCC 792] are as under;
"10. The situs of the land, the distance between the high voltage CRP Nos.364 of 2021 and 200 of 2022
electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small tract of land or through the middle of the land and other similar relevant factors in our opinion would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used."
On careful scrutiny of the impugned order, it is
seen that, in the case at hand, the compensation
was fixed after taking all the above factors into
consideration. The nature of the land, the
cultivation therein, the commercial importance of
the area and the manner in which the land was
affected by drawing of the lines are all seen
considered for fixing the land value as well as
the percentage of diminution. After considering
the similarities of the properties involved, the
court below adopted the land value in Ext.A7
document, which according to me, is reasonable. CRP Nos.364 of 2021 and 200 of 2022
Similarly, the discretion was properly exercised
by the court below in granting 40% of the land
value as compensation for the central corridor
and 20% for the outer corridors.
9. The contention of the Corporation that
the Government having fixed the fair value, the
court below could not have fixed a higher value
is liable to be rejected since, while assessing
the damage sustained and fixing the compensation,
the court is not bound by the guidelines/orders
issued by the Government. The contention that
the court below committed an illegality in
awarding 9% interest cannot also be sustained in
the light of the decision of this Court in V.V.
Jayaram v Kerala State Electricity Board [2015
(3) KHC 453]. As such, there is no illegality or
material irregularity in the impugned order,
warranting intervention by this Court in exercise
of the revisional power under Section 115 of the
Code of Civil Procedure.
CRP Nos.364 of 2021 and 200 of 2022
For the aforementioned reasons, the civil
revision petitions filed by the claimant as well
as the Corporation are dismissed.
If any amount is deposited pursuant to the
order of this Court or otherwise, the same shall
forthwith be released to the claimant on his
filing appropriate application. The entire
enhanced compensation shall be paid to the
claimant within three months of receipt of a copy
of this order.
Sd/-
V.G.ARUN JUDGE Scl/
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!