Citation : 2024 Latest Caselaw 12439 Ker
Judgement Date : 21 May, 2024
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE V.G.ARUN
TUESDAY, THE 21ST DAY OF MAY 2024 / 31ST VAISAKHA, 1946
CRP NO. 355 OF 2021
AGAINST THE ORDER/JUDGMENT DATED 31.03.2021 IN OPELE NO.355 OF
2013 OF VI ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:
SIVAN
AGED 49 YEARS
S/O.RAMAN, ELLIKKAKKUDI, ELAMBAKKAPILLI, KOOVAPPADY
VILLAGE, KUNNATHUNAD TALUK
BY ADV P.T.JOSE
RESPONDENT/S:
1 POWER GRID CORPORATION OF INDIA LTD.
CONSTRUCTION AREA OFFICE, KAKKANAD, NOW IN PAO/400,
220KV SUBSTATION, KUMARAPURAM P.O., PALLIKARA, KOCHI
682 303, REP.BY DEPUTY MANAGER
2 THE SPECIAL TAHASILDAR (L.A.)
POWER GRID CORPORATION OF INDIA LTD., CHEVARAMBALAM,
KOZHIKODE, NOW IN KAKKANAD P.O.682 030
3 STATE OF KERALA
REP.BY DISTRICT COLLECTOR, ERNAKULAM KOCHI 682 031
4 KERALA STATE ELECTRICITY BOARD
REP.BY CHAIRMAN AND MANAGING DIRECTOR, KSEB LTD.,
THIRUVANANTHAPURAM 695 001
BY ADV R.HARISHANKAR
OTHER PRESENT:
ADV.PARAMESWARAN K.JOY-R1,B.PRAMOD SC KSEB.,SR.GP
V.TEKCHAND
THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
08.04.2024, ALONG WITH CRP.173/2022, THE COURT ON 21.05.2024
DELIVERED THE FOLLOWING:
CRP Nos.355 of 2021 and 173 of 2022
-2-
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE V.G.ARUN
TUESDAY, THE 21ST DAY OF MAY 2024 / 31ST VAISAKHA, 1946
CRP NO. 173 OF 2022
AGAINST THE ORDER/JUDGMENT DATED IN OPELE NO.355 OF 2013 OF VI
ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:
POWER GRID CORPORATION OF INDIA
CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY,
KAKKANAD, COCHIN - 682 030, PRESENTLY AT
CONSTRUCTION AREA OFFICE, 400/220, KV SUB STATION,
KUMARAPURAM P.O, PALLIKKARA, ERNAKULAM, REPRESENTED
BY ITS SENIOR GENERAL MANAGER, PIN - 683565
BY ADV MILLU DANDAPANI
RESPONDENT/S:
1 SIVAN
S/O. RAMAN, AGED 50 YEARS, ELLIKKAKKUDI,
ELAMBAKKAPILLI, KOOVAPPADY VILLAGE, KUNNATHUNADU
TALUK, PIN - 683544
2 THE SPECIAL TAHSILDAR (LA)
POWER GRID CORPORATION OF INDIA LTD. CHEVARAMBALAM,
KOZHIKODE, PIN - 673017
3 STATE OF KERALA
REPRESENTED BY DISTRICT COLLECTOR, ERNAKULAM, KOCHI,
PIN - 682030
4 KERALA STATE ELECTRICITY BOARD - KSEB
REPRESENTED BY CHAIRMAN & MANAGING DIRECTOR KSEB
LTD., THIRUVANANTHAPURAM., PIN - 695001
BY ADV P.T.JOSE
THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
08.04.2024, ALONG WITH CRP.355/2021, THE COURT ON 21.05.2024
DELIVERED THE FOLLOWING:
CRP Nos.355 of 2021 and 173 of 2022
-3-
ORDER
Dated this the 21st day of May, 2024
These revision petitions are filed
challenging the order passed by the Additional
District Judge-VI, Ernakulam in O.P.(Electricity)
No.355 of 2013. The original petition was filed
by the revision petitioner in CRP No.355 of 2021
(hereinafter called 'the claimant'), being
dissatisfied with the compensation awarded
towards the damage and loss sustained due to the
drawing of 400 KV lines across his property by
the Power Grid Corporation of India Ltd
(hereinafter called 'the Corporation'). The
essential facts are as under;
The claimant is in ownership and possession
of landed property having an extent of 8.09 Ares
in Sy.No.220/11-2-4 and 7.28 Ares in
Sy.No.220/11-2-5 of Koovappady Village in
Kunnathunadu Taluk. The land was cultivated with CRP Nos.355 of 2021 and 173 of 2022
various yielding and non-yielding trees.
According to the claimant, to facilitate drawing
of the lines and smooth transmission of power,
large number of trees were cut from his property.
The drawing of high tension lines rendered the
land underneath and adjacent to the lines
useless, resulting in diminution of the value of
the property. In spite of the huge loss suffered
by the claimant, only an amount of Rs.2,56,038/-
(2,46,054 + 9,984) was paid as compensation
towards the value of yielding and non-yielding
trees cut. Surprisingly, no compensation was
granted for diminution in land value. Hence, the
original petition was filed, seeking enhanced
compensation towards the value of trees cut and
diminution in land value.
2. The court below rejected the claim for
enhanced compensation for the value of trees cut
since no evidence in support of the claim was
produced. As far as the claim for enhanced
compensation towards diminution in land value is CRP Nos.355 of 2021 and 173 of 2022
concerned, the court below relied on Ext.A7
document as well as Exts.C4 and C4(a) commission
report and sketch. The court below adopted the
land value of the property involved in Ext.A7
document. Relying on Ext.C4(a) sketch, the extent
of central corridor was held to be 17.072 cents
(13.367 + 2.297 + 1.408) and that of the outer
corridors, 17.049 cents (16.974 + 0.075). For
the central corridor, 40% of the land value was
granted as compensation and for outer corridors,
20% of the land value. Accordingly, the claimant
was found entitled to compensation of
Rs.17,39,947/-. Dissatisfied with the quantum of
enhancement, the claimant has filed CRP No.355 of
2021, whereas the Corporation has filed CRP
No.173 of 2022 contending that the enhancement
ordered is far in excess of the actual damage
sustained.
3. Heard Adv.P.T.Jose for the claimant and
Adv.Millu Dandapani for the Corporation.
4. Learned Counsel for the claimant CRP Nos.355 of 2021 and 173 of 2022
contended that the court below committed gross
illegality in refusing to grant enhanced
compensation for the loss sustained due to the
cutting of valuable trees, in spite of the
Advocate Commissioner assessing and reporting the
loss. The findings in the Commissioner's report
were not relied on by the court below for the
reason that the property was inspected much after
the trees were cut. The said reasoning is flawed
since the trees were cut much after issuance of
notification by the Corporation and the cause of
action for filing the original petition arose
only on payment of the initial compensation, even
later.
5. It is further submitted that the court
below grossly erred in granting only 40% of the
land value for the central corridor and 20% for
the outer corridors. According to the learned
Counsel, considering the extent of damage
sustained and the diminution in land value
consequent to the drawing of lines, the court CRP Nos.355 of 2021 and 173 of 2022
below ought to have granted compensation as
claimed.
6. Learned Counsel for the Corporation
contended that the compensation granted towards
diminution in land value is exorbitant and there
is no rationale in granting 9% interest on that
amount. The court below also erred in relying on
Ext.A7 for fixing the land value of the
claimant's property. As the drawing of electric
lines does not prohibit the landowner from
conducting agricultural activities and putting up
small structures, 40% of the land value granted
for the central corridor and 20% for the outer
corridors are exorbitant.
7. A careful scrutiny of the impugned order
reveals that the claim for enhancement of
compensation towards the value of trees cut was
rightly rejected in the absence of any supporting
material, other than the findings in the Advocate
Commissioner's report. 5. It is further submitted
that the court below grossly erred in granting CRP Nos.355 of 2021 and 173 of 2022
only 40% of the land value for the central
corridor and 20% for the outer corridors.
According to the learned Counsel, considering the
extent of damage sustained and the diminution in
land value consequent to the drawing of lines,
the court below ought to have granted
compensation as claimed.
6. Learned Counsel for the Corporation
contended that the compensation granted towards
diminution in land value is exorbitant and there
is no rationale in granting 9% interest on that
amount. The court below also erred in relying on
Ext.A7 for fixing the land value of the
claimant's property. As the drawing of electric
lines does not prohibit the landowner from
conducting agricultural activities and putting up
small structures, 40% of the land value granted
for the central corridor and 20% for the outer
corridors are exorbitant.
7. A careful scrutiny of the impugned order
reveals that the claim for enhancement of CRP Nos.355 of 2021 and 173 of 2022
compensation towards the value of trees cut was
rightly rejected in the absence of any supporting
material, other than the findings in the Advocate
Commissioner's report. As found by the court
below, apart from the interested testimony of a
witness, the claimant in some of the connected
cases, no other independent witness was examined.
The court below also took note of the fact that
the trees had been cut and removed in the year
2011, whereas the Commissioner inspected the
property much later. Therefore, the court below
rightly refused to accept the assessment made by
the Commissioner, which was based on an overview
of the remaining trees in the petition schedule
and neighbouring properties. On the other hand,
the Corporation had assessed the yield on the
basis of local inspection, enquiry and data
furnished by the Government departments. Hence,
it was rightly held by the court below that the
evidence let in by the claimant is not sufficient
to discard the contemporaneous valuation CRP Nos.355 of 2021 and 173 of 2022
statement prepared by the Corporation.
8. For fixing the compensation payable
towards diminution in land value, the factors to
be taken into consideration, as laid down in
KSEB v. Livisha [(2007) 6 SCC 792] are as under;
"10. The situs of the land, the distance between the high voltage electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small tract of land or through the middle of the land and other similar relevant factors in our opinion would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used."
On careful scrutiny of the impugned order, it is
seen that, in the case at hand, the compensation
was fixed after taking all the above factors into
consideration. The nature of the land, the
cultivation therein, the commercial importance of CRP Nos.355 of 2021 and 173 of 2022
the area and the manner in which the land was
affected by drawing of the lines are all seen
considered for fixing the land value as well as
the percentage of diminution. After considering
the similarities of the properties involved, the
court below adopted the land value in Ext.A7
document, which according to me, is reasonable.
Similarly, the discretion was properly exercised
by the court below in granting 40% of the land
value as compensation for the central corridor
and 20% for the outer corridors.
9. The contention of the Corporation that
the Government having fixed the fair value, the
court below could not have fixed a higher value
is liable to be rejected since, while assessing
the damage sustained and fixing the compensation,
the court is not bound by the guidelines/orders
issued by the Government. The contention that
the court below committed an illegality in
awarding 9% interest cannot also be sustained in
the light of the decision of this Court in V.V. CRP Nos.355 of 2021 and 173 of 2022
Jayaram v Kerala State Electricity Board [2015
(3) KHC 453]. As such, there is no illegality or
material irregularity in the impugned order,
warranting intervention by this Court in exercise
of the revisional power under Section 115 of the
Code of Civil Procedure.
For the aforementioned reasons, the civil
revision petitions filed by the claimant as well
as the Corporation are dismissed.
If any amount is deposited pursuant to the
order of this Court or otherwise, the same shall
forthwith be released to the claimant on his
filing appropriate application. The entire
enhanced compensation shall be paid to the
claimant within three months of receipt of a copy
of this order.
Sd/-
V.G.ARUN JUDGE Scl/
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!