Tuesday, 21, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

O.V.George vs State Of Kerala
2024 Latest Caselaw 12431 Ker

Citation : 2024 Latest Caselaw 12431 Ker
Judgement Date : 21 May, 2024

Kerala High Court

O.V.George vs State Of Kerala on 21 May, 2024

        IN THE HIGH COURT OF KERALA AT ERNAKULAM
                           PRESENT
        THE HONOURABLE MR.JUSTICE P.G. AJITHKUMAR
 TUESDAY, THE 21ST DAY OF MAY 2024 / 31ST VAISAKHA, 1946
                  CRL.APPEAL NO. 478 OF 2024
  AGAINST THE JUDGMENT DATED 28.01.2011 IN SC NO.274 OF
  2008 OF ADDITIONAL SESSIONS COURT (SPECIAL COURT)-II,
         KOTTAYAM / I ADDITIONAL MACT, KOTTAYAM
  (CC NO.669 OF 2005 OF JUDL. MAGI. OF FIRST CLASS-III,
                          KOTTAYAM)
APPELLANT/ACCUSED:

            O.V.GEORGE
            OOMELIL, KOKKAPPILLY, THIRUVANKULAM, NOW
            RESIDING AT OOMELIL, THAZHATHANGADI P.O.,
            KOTTAYAM.

            BY ADVS.
            SRI.KMV.PANDALAI
            SMT.S.HEMALATHA


RESPONDENT/COMPLAINANT:

            STATE OF KERALA
            DIRECTOR OF PROSECUTIONS, HIGH COURT OF KERALA.

            SMT.SEENA C., PUBLIC PROSECUTOR


     THIS    CRIMINAL   APPEAL   HAVING   COME   UP   FOR   FINAL
HEARING ON 08.04.2024, THE COURT ON 21.05.2024 DELIVERED
THE FOLLOWING:
                                  2
Crl.Appeal No.478 of 2024



                     P.G. AJITHKUMAR, J.
    -----------------------------------------------------------
                  Crl.Appeal No.478 of 2024
    -----------------------------------------------------------
             Dated this the 21st day of May, 2024

                            JUDGMENT

The judgment of conviction rendered by the Additional

Sessions Judge (Special), Kottayam in S.C.No.274 of 2008 is

under challenge in this appeal. It was filed originally as a Criminal

Revision Petition. This Court, as per the order dated 05.03.2024,

converted it as an appeal in view of the provisions under Section

401(5) of the Code of Criminal Procedure, 1973.

2. The prosecution was initiated with the following

allegations:

The appellant was conducting Hotel Aiswarya International in

the ground floor of a seven-storied building belonging to

Aiswarya Tourist Home Pvt.Ltd. at Kottayam. Electricity

energy meter installed to the power connection provided to

the building by the Kerala State Electricity Board was having

the number 2129523. It was installed in the cellar portion of

the building. The appellant installed three resistances each of

10 Ohms in the power meter, resulting in reduced recording of

the electricity consumption by 80%. By such manipulation of

the power meter for a period of 2½ years upto 17.08.2003,

on which date the manipulation was detected by PW1 and his

colleagues, the appellant caused a loss of Rs.26 lakhs to the

Kerala State Electricity Board. Thereby the appellant

committed the offences punishable under Section 39 of the

Indian Electricity Act, 1910 read with Rules 56, 57 and 138 of

the Indian Electricity Rules, 1956.

3. The prosecution has examined PWs.1 to 9 and

proved Exts.P1 to P13 to establish the charge framed against

the appellant. MOs.1 to 3 were identified also. After closing

the prosecution evidence, the appellant was questioned

under Section 313(1)(b) of the Code. He denied the

incriminating circumstances appeared in evidence against

him. He further stated that he was in occupation of a portion

of the building alone and the power meter was intended for

the whole building. The electricity meter was under the

control of the building owner. He used to pay the electricity

charges to the building owner, who in turn used to pay in the

Electricity Board. The appellant further denied his

committing any kind of manipulation in the power meter.

DW1 was examined and Exts.D1 to D4 were marked on his

side.

4. The trial court, after considering the entire

evidence, repelled the contentions of the appellant and held

that the power meter was tampered with by or on behalf of

the appellant. The tampering of the power meter and loss

thereby occasioned to the Kerala State Electricity Board are

proved beyond doubt. Whether or not the appellant was the

beneficiary of such manipulation of the power meter, he being

the person in control and having domain over the power

meter, the facts about the manipulation were within his

exclusive knowledge, but he did not discharge his burden of

proving that fact. The trial court accordingly found the

appellant guilty of the offence charged against him.

5. Heard the learned counsel for the appellant and the

learned Public Prosecutor.

6. PW1 was the Assistant Engineer in the Central

Section, Kottayam of the Kerala State Electricity Board. PW2

was the Assistant Engineer in Kottayam anti-power theft squad

unit. On 17.03.2003 they, along with their colleagues in the

Board, detected the electricity theft. Both of them deposed in

detail about the inspection of the premises, where hotel

Aiswarya International was functioning. They entertained a

doubt about tampering of the power meter installed to the

power connection provided to that building and therefore they

tested the meter by installing another one, obviously bypassing

the power meter in question. They noticed 80% deduction from

the actual consumption of the power while using the meter in

question. Therefore, they seized the existing power meter and

took it into custody under a mahazar. They wrapped and sealed

it. They identified MO1 before the court as the said meter.

Based on the said findings, PW1 lodged Ext.P1 complaint in

police, upon which the prosecution was initiated.

7. PW4 was the electrician in Hotel Aiswarya

International. He deposed that he saw the Electricity Board

officials seizing the power meter installed in the premises of

the Hotel Aiswarya International, of which the appellant was

the owner. Although the evidence of these witnesses was

challenged and they were cross-examined at length, nothing

to disbelieve their testimony concerning inspection of the

premises and seizure of MO1 power meter could be brought

out. When PW4, who was an employee of the appellant,

deposed in court in categorical terms that the premises was

inspected and the power meter was seized by the Electricity

Board officials, there is no reason to disbelieve PWs1 and 2

insofar as those aspects are concerned.

8. MO1 was tested by PW3 in the Transformer and

Meter Testing Repair (TMR) unit of the Electricity Board. He

was the Assistant Engineer and on 17.03.2003 he tested the

meter. Ext.P3 is his report. It is his version that he received the

meter in a sealed cover, and on its examination, three resistors

each of 10 Ohms were seen installed in the secondary circuit of

the meter. It is his assertion that such tampering of the meter

could be confirmed since seals of the KSEB and the company

on the meter were seen lost. The said report of PW3 confirmed

the fact that MO1 meter, which was installed to the power

supply connection provided to the building where Aiswarya

Hotel had been functioning, was tampered with. PWs.1 and 2

deposed that on account of such tampering, which lasted for a

period of 2½ years, the Board sustained a loss of Rs.26 lakhs.

The quantification of the loss is not challenged. In such

circumstances, the allegation that MO1 power meter was

tampered with, on account of which the KSEB sustained a loss

of Rs.26 lakhs, can be said to be proved.

9. The contention of the appellant is that he was in

occupation of one floor of the the seven-storied building alone

and the entire remaining area was under the control and

occupation of the owner of the building. Case of the prosecution

is that in terms of the licence agreement under which the

appellant was occupying the ground floor, the appellant was

responsible to pay the electricity and water charges and that he

was in control of the power meter. Indisputably, the power

meter was installed in the cellar portion of the building. PW6 is

one of the owners of the building. His father was the Managing

Director of the company, which owned the building. After his

death, PW6's mother Smt.Savithrikutty Amma was in control of

the building.

10. Hotel Aishwarya International premises was handed

over to the appellant in terms of an agreement entered into

between himself and the father of PW6. That agreement was

not produced before the court. PW7 is the investigating

officer. He stated that on 23.03.2003 he saw the said

agreement and prepared Ext.P5 mahazar. PW6 is an attestor

to the said mahazar. The mother of PW6 was the custodian of

the agreement and PW7 gave it to her in interim custody on

executing her kychit, Ext,P8. Based on that agreement the

prosecution has set forth the case that it was the appellant

who was the real consumer and MO1 meter was in his control

and custody. PW6 asserted that fact.

11. The learned counsel for the appellant would submit

that in the absence of the agreement the oral testimony of

PW6 cannot be acted upon so as to enter a finding that the

appellant was the consumer having control over the power

meter. The appellant stated during 313 questioning that he

was not in control of the power meter and he used to give the

electricity charges to the owner of the building.

12. The learned Public Prosecutor would point out that

when PWs.1, 2, 4 and 6 stated that the appellant was the

person, who had domain over the power meter, the trial court

was right in finding that he was responsible for the tampering

of the meter.

13. PWs.1 and 2 did not have any personal knowledge

as to who had the domain over the power meter. The oral

testimony of PW4 is also not helpful to find that fact in favour

of the prosecution. Of course, PW6 stated that in terms of the

agreement, it was the appellant, who had to pay the

electricity charges. Although a few recitals in the agreement

between the appellant and the owner of the building are

narrated in Ext.P5 mahazar, nothing regarding the building

scheduled as the subject matter of the agreement had been

extracted in the mahazar.

14. As stated, Hotel Aiswarya was functioning in the

first floor of the seven storied building. The appellant did not

have possession or occupation of other parts of the building.

There is nothing in evidence to show in whose possession

and occupation are the remaining parts of the building.

Neither the agreement is produced nor, atleast, the relevant

recitals from the agreement are extracted in Ext.P5 mahazar.

Hence, we are at dark as to whether the cellar portion of the

building, where the meter was installed, had been put in

possession of the appellant. The finding of the court below

that that was a fact within the exclusive knowledge of the

appellant is incorrect. Whether the domain over the cellar

portion and the power meter was given to the appellant is a

fact not only known to the owner of the building, but also

borne by records. The prosecution could have adduced

evidence in uncertain terms regarding that fact. But, the

prosecution failed. Except tendering the oral testimony of

PW6, which is insufficient, the prosecution did not adduce

any evidence to prove that fact.

15. It may be noted that the appellant has a case that

the landlord had been trying to evict him from the premises.

Steps for eviction were initiated as could be seen from

Exts.B1 and B1(a). It is alleged that as a sequel to that the

landlord instigated the Electricity Board officials to inspect the

premises. In the wake of such a contention the prosecution

ought to have adduced reliable evidence to show that the

appellant had absolute control over the power meter and he

was the principal beneficiary of the manipulation of the meter.

In the absence of cogent and reliable evidence in that regard,

it cannot be said that the charge of electricity theft against

the appellant is proved beyond doubt. Therefore, the finding

of the trial court holding the appellant guilty is incorrect. The

appeal therefore is liable to be allowed.

In the result, the appeal is allowed. The appellant is

acquitted of the charge levelled against him. He is set at

liberty.

Sd/-

P.G. AJITHKUMAR, JUDGE dkr/pv

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter