Citation : 2024 Latest Caselaw 8901 Ker
Judgement Date : 27 March, 2024
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE GOPINATH P.
WEDNESDAY, THE 27TH DAY OF MARCH 2024 / 7TH CHAITHRA, 1946
WP(C) NO. 2318 OF 2014
PETITIONER/S:
JAYACHANDRAN
AGED 52 YEARS
S/O.GOVINDAN NAMBIAR, LAKSHMIGOVIND, MAYYIL P.O.,
KANNUR-670602.
BY ADVS.
SRI.K.V.PAVITHRAN
SRI.JAYANANDAN MADAYI PUTHIYAVEETTIL
SRI.P.SAJU
SRI.E.M.UNNIKRISHNAN MANJERI
RESPONDENT/S:
1 SECRETARY, IRIKKUR BLOCK PANCHAYATH
IRIKKUR BLOCK PANCHAYATH, IRRIKKU,
KANNUR DISTRICT, 670593.
2 PROJECT DIRECTOR, POVERTY ALLOCATION UNIT,
(DISTRICT PANCHAYATH), KANNUR, 670001.
3 SPECIAL DEPUTY TAHSILDAR
REVENUE RECOVERY, TALUK OFFICE,
TALIPARAMBA, KANNUR-670143.
SRI.BINOY DAVIS (GP)
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
27.03.2024, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C) NO. 2318 OF 2014 2
JUDGMENT
The petitioner has approached this Court, challenging the
revenue recovery proceedings initiated to recover the amounts
mentioned in Ext.P7.
2. Brief facts of the case are as follows:-
The petitioner is a contractor, who was awarded with
certain works by the Irikkur Block Panchayath for which,
agreement No.8/2006-07 dated 19.06.2000 was executed by
the petitioner. It appears from a reading of Ext.P7 that though
the petitioner had completed the work, the same was not
completed within time and therefore, a sum of Rs.4,04,547/-
(Rupees Four lakhs four thousand five hundred and forty seven
only) had to be recovered from the petitioner as penalty for
the delay in completing the work. It is also seen from Ext.P4
that the said demands had been based on certain observations
of the audit wing, which opined that penalty was to be levied
on the petitioner. The petitioner has a case that the
determination that the petitioner was liable to penalty on the
basis of the observations of the audit wing, cannot be
sustained in law. It is his case that the audit wing has not
considered the entire facts and circumstances and the reasons
for the delay in completing the work (if any) and the 1 st
respondent could not have unilaterally proceeded to hold that
the amount mentioned in Ext.P7 is to be recovered from the
petitioner.
3. Despite service of notice, there is no appearance for
the 1st respondent.
4. Learned Government Pleader appearing for
respondent Nos.2 and 3 would submit that the proceedings for
imposition of penalty appears to have been taken on the basis
of the fact that the petitioner had not completed the work
awarded to him within the time specified.
5. Having heard the learned counsel appearing for the
petitioner and the learned Government Pleader, I am of the
view that since Ext.P7 is a unilateral determination by the 1 st
respondent that the petitioner is liable to penalty for a sum of
Rs.4,04,547/-, the revenue recovery proceedings against the
petitioner initiated on the basis of Ext.P7 must be quashed.
The requirements of natural justice indicate that the petitioner
must be afforded an opportunity of being heard and there must
be a determination before any penalty in the nature of Ext.P7
is imposed on him. Ext.P7 can therefore be treated as a show
cause notice and the petitioner shall be permitted to file his
objections to Ext.P7 and thereafter, the 1 st respondent shall
take a decision in the matter affording an opportunity of
hearing to the petitioner.
In the light of the above, the writ petition will stand
disposed of with the following directions:-
(i) Ext.P7 shall be treated as a show cause notice, calling
upon the petitioner to show cause why the penalty imposed on
the petitioner should not be recovered from the petitioner.
The petitioner shall file a reply to Ext.P7, within a period of
two weeks from the date of receipt a copy of this judgment.
The petitioner shall, thereafter, appear before the 1 st
respondent at 11.00 AM on 19.04.2024 along with a copy of
the writ petition and certified copy of this judgment and
thereafter, the matter shall be adjudicated by the 1 st
respondent, as directed above, after hearing the petitioner.
(ii) The revenue recovery proceedings initiated against
the petitioner to recover the amounts found due under Ext.P7
stand quashed, making it clear that further revenue recovery
proceedings can be initiated against the petitioner, if at all the
petitioner is found liable to pay any amount on the basis of the
fresh orders to be issued by the 1 st respondent, as directed
above.
The writ petition is disposed of as above.
Sd/-
GOPINATH P. JUDGE ajt
APPENDIX OF WP(C) 2318/2014
PETITIONER EXHIBITS EXHIBIT-P1: TRUE COPY OF THE AGREEMENT NO.8/2006-07 DATED 19.6.2006.
EXHIBIT-P1(a): TRUE COPY OF SITE HANDLING OVER REPORT DATED 19.6.2006.
EXHIBIT-P2: TRUE COPY OF THE PAGES 1 TO 45 OF THE MEASUREMENT BOOK NO.10/06-07.
EXHIBIT-P3: A TRUE COPY OF THE LETTER DATED 5.5.09.RECEIVED BY THE ASSISTANT ENGINEER FROM THE PRINCIPAL OF THE INSTITUTE.
EXHIBIT-P4: TRUE COPY OF THE PROJECT COMPLETION REPORT. EXHIBIT-P5: TRUE COPY OF THE ANNUAL PLAN PROPOSAL MOOTED BY R1.
EXHIBIT-P6: A TRUE COPY OF THE LETTER DATED 22.4.2010. EXHIBIT-P6(a): A TRUE COPY OF THE FINAL BILL. EXHIBIT-P7: A TRUE COPY OF THE LETTER DATED 17.9.2012. EXHIBIT-P8: TRUE COPY OF THE REVENUE RECOVERY NOTICE.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!