Friday, 15, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Assistant Executive Engineer vs Alex Soharab V.F
2024 Latest Caselaw 15577 Ker

Citation : 2024 Latest Caselaw 15577 Ker
Judgement Date : 6 June, 2024

Kerala High Court

The Assistant Executive Engineer vs Alex Soharab V.F on 6 June, 2024

Author: Dinesh Kumar Singh

Bench: Dinesh Kumar Singh

               IN THE HIGH COURT OF KERALA AT ERNAKULAM
                               PRESENT
          THE HONOURABLE MR. JUSTICE DINESH KUMAR SINGH
     THURSDAY, THE 6TH DAY OF JUNE 2024 / 16TH JYAISHTA, 1946
                        WP(C) NO. 3649 OF 2021

PETITIONERS:

    1     THE ASSISTANT EXECUTIVE ENGINEER,
          KERALA STATE ELECTRICITY BOARD LTD.,
          ELECTRICAL SUB DIVISION, ALUVA TOWN,
          ERNAKULAM DISTRICT, PIN - 683 101.

    2     THE ASSISTANT ENGINEER,
          KERALA STATE ELECTRICITY BOARD LTD.,
          ELECTRICAL SECTION, EDAYAR,
          ERNAKULAM DISTRICT, PIN - 686 662.

          BY ADVS.
              SRI. K. M. SATHYANATHA MENON
              SMT. KAVERY S. THAMPI


RESPONDENTS:

          ALEX SOHARAB V. F.,
          M/S. SOUTHERN ENGINEERING CORPORATION,
          V/830-A, DEVELOPMENT AREA, EDAYAR,
          MUPPATHADOM, ALUVA - 683 110.

          BY ADVS.
              SRI. C. HARIKUMAR
              SRI. VIZZY GEORGE KOKKAT
              SRI. ANAND GOKULDAS
              SMT. SRUTI RAVINDRANATHAN
              SRI. ABHIRAM T. K.


     THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
06.06.2024, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 WP(C) NO. 3649 OF 2021

                                       2


                         DINESH KUMAR SINGH, J.
                              --------------------------
                           W.P.(C) No. 3649 of 2021
                              -------------------------
                     Dated this the 6th day of June, 2024

                                  JUDGMENT

1. The present writ petition has been filed by the petitioners

impugning the decision of the Consumer Grievance Redressal

Forum (CGRF) in Exhibit P-3 dated 12.01.2017 to the extent of

direction by the CGRF for refund of the expenditure amount taken

from the respondent for enhancement of the capacity of the 100

kVA transformer to 250 kVA transformer.

2. The CGRF having considered the Regulation 36 of the of the

Supply Code, 2014 has held that since the total requirement i.e.

the existing and the enhanced requirement is less than 1MW, the

expenditure for meeting the additional load of the petitioner has

to be borne by the lincencee.

3. The Regulation 36 of Supply Code, 2014 are specific and

categorical which on reproduction read as under;

"36. Expenditure for extension or upgradation or both of the distribution system to be borne by the consumer.- WP(C) NO. 3649 OF 2021

The expenditure for extension or upgradation or both of the distribution system undertaken exclusively for giving new service connection to any person or a collective body of persons or a developer or a builder, or for enhancing the load demand of a consumer or a collective body of consumers or a developer or a builder, shall be borne by the respective applicant or consumer or collective body of consumers or developer or builder, as the case may be, in the following cases:-

(i) for meeting the demand of an applicant with a contract demand above one megawatt (MW);

(ii) for meeting the additional demand of existing consumers, if the aggregate demand including the additional demand applied for, is above one megawatt (MW);

(iii) for meeting the demand of the domestic or commercial or industrial complex or colony constructed by a developer or a builder with a demand above one megawatt (MW);

(iv) for meeting the demand of a high rise building irrespective of its demand;

WP(C) NO. 3649 OF 2021

(v) for meeting the demand of power intensive unit irrespective of its demand;

                 and


                 (vi)    for    meeting       the   demand   of    a

consumer requesting for dedicated feeder or protected load status irrespective of its demand:

Provided that, if due to technical reasons, the extension or upgradation or both to be undertaken by the licensee as per this regulation is more than the requirement of such consumer, the expenditure for such extension or upgradation or both to be realised from the consumer shall be limited to the proportionate expenditure."

4. The existing demand of the respondent was 20KW. The

respondent applied for additional load of 65KW. Thus, the total

load including the additional demand would become 85KW, which

is much lower than the 1MV and, therefore, for meeting the

additional demand of the consumer/respondent under Regulation

36 of the Supply Code, 2014 it is licensee who has to bear the

expenditure, if any, incured for meeting the additional demand of

65KW.

WP(C) NO. 3649 OF 2021

5. The respondent was illegally charged for upgrading the

existing transformer from 100 KVA to 250 KVA. This amount was

not required to be paid by the consumer/respondent and,

therefore, the CGRF has rightly held that for meeting the

additional demand of the respondent, it was the lincencee who

was required to bear the expenditure. Considering the regulation

36 of the Supply Code, 2014, I find no ground to interfere with the

order passed by the CGRF, which is impugned in this writ petition.

Hence the writ petition is hereby dismissed.

Sd/-

DINESH KUMAR SINGH JUDGE Svn WP(C) NO. 3649 OF 2021

APPENDIX OF WP(C) 3649/2021

PETITIONER'S EXHIBITS

EXHIBIT P1 A TRUE COPY OF THE COMPLAINT SUBMITTED BY THE RESPONDENT BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM, CENTRAL REGION AND NUMBERED AS COMPLAINT NO.59/2016-17/531 DATED 26.8.2016.

EXHIBIT P2 A TRUE COPY OF THE THE STATEMENT OF FACTS SUBMITTED BY THE PETITIONERS IN COMPLAINT NO.59/2016-17/531 DATED 22.9.2016 BEFORE THE CHAIRPERSON CONSUMER GRIEVANCE REDRESSAL FORUM, CENTRAL REGION.

EXHIBIT P3 A TRUE COPY OF THE ORDER PASSED BY THE CGRF IN CGRF-CR/COMP. 59/2016-17/531 DATED 12.1.2017.

EXHIBIT P4 A TRUE COPY OF THE JUDGMENT DATED 16.10.2018 IN W.A.NO.1448/2017 OF THIS HON'BLE COURT.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter