Thursday, 14, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sabu Sebastian vs Assistant Engineer
2024 Latest Caselaw 19 Ker

Citation : 2024 Latest Caselaw 19 Ker
Judgement Date : 3 January, 2024

Kerala High Court

Sabu Sebastian vs Assistant Engineer on 3 January, 2024

Author: Bechu Kurian Thomas

Bench: Bechu Kurian Thomas

           IN THE HIGH COURT OF KERALA AT ERNAKULAM
                           PRESENT
        THE HONOURABLE MR. JUSTICE BECHU KURIAN THOMAS
 WEDNESDAY, THE 3RD DAY OF JANUARY 2024 / 13TH POUSHA, 1945
                   WP(C) NO. 40465 OF 2022
PETITIONER:

          SABU SEBASTIAN,
          AGED 56 YEARS
          S/O LATE SEBASTIAN
          RESIDING AT PUTHUPPALLYKUNNEL HOUSE,
          AMAYANOOR PO,
          KOTTAYAM - 686019.
          BY SMT. SUMATHY DANDAPANI (SR)
          ADV. MILLU DANDAPANI


RESPONDENTS:

    1     ASSISTANT ENGINEER,
          OFFICE OF THE ASSISTANT ENGINEER
          LSGD (LID & EW) SECTION
          PUTHUPALLY GRAMA PANCHAYAT
          PUTHUPALLY, KOTTAYAM - 686011.
    2     PUTHUPALLY GRAMA PANCHAYAT
          PUTHUPALLY, KOTTAYAM - 686011
          REPRESENTED BY ITS SECRETARY.
    3     STATE OF KERALA
          REPRESENTED BY SECRETARY TO THE GOVERNMENT,
          FINANCE DEPARTMENT,
          GOVERNMENT SECRETARIAT
          THIRUVANANTHAPURAM - 695001.
    4     RURAL DEVELOPMENT COMMISSIONER
          RURAL DEVELOPMENT COMMISSIONERATE,
          SWARAJ BHAWAN, NANDANKODE,
          KAVIDIYAR P.O.,
          THIRUVANANTHAPURAM 695003.
          BY ADVS.
          SRI.K.S.ARUN KUMAR, SC
 W.P.(C) No.40465/22                 -:2:-


              SMT. K.AMMINIKUTTY SR. GOVT. PLEADER




       THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD
ON   23.11.2023,      THE   COURT   ON      03.01.2024   DELIVERED   THE
FOLLOWING:
 W.P.(C) No.40465/22                      -:3:-




                         BECHU KURIAN THOMAS, J.
                             --------------------------------
                           W.P.(C) No.40465 of 2022
                            ---------------------------------
                      Dated this the 3rd day of January, 2024

                                   JUDGMENT

The writ petition is filed seeking to quash Ext.P8 stop memo and

also to make good the cost incurred by the petitioner for the execution of

work under Ext.P2 tender.

2. A tender was invited by the first respondent on 03-04-2022 for

the construction of the work titled 'Puthuppally Food Processing Unit' to be

completed within 12 months. The project was part of the National Rural

Urban Mission (NRUM). Petitioner submitted his bid, and as per Ext.P3

dated 25-05-2022, he was informed that the contract is awarded to him.

Thereafter, an agreement was executed on 06-06-2022 for the

construction of the food processing unit.

3. While the petitioner was carrying on the construction activities, by

Ext.P8 letter dated 29-07-2022, the first respondent directed the petitioner

to stop all further works pursuant to the agreement. The reason stated in

Ext.P8 is that as per the communication dated 21-07-2022 from the fourth

respondent, new works after 31-03-2022 ought not to be commenced, and

that amounts will not be paid for such works.

4. Immediately on receipt of Ext.P8, stop memo, petitioner issued a

letter dated 01-09-2022 pointing out that he had already commenced the

work pursuant to the agreement and had finished item Nos.I, II, III, and

XVII scheduled to the agreement completely and had also finished 20% of

the work in item No.XII. It was further mentioned that petitioner had

already unloaded M-sand and broken stone at the site, and therefore, he

may be permitted to continue the construction as per the agreement.

5. By another communication dated 18-07-2022, the Panchayat had

informed the first respondent that since information has not been received

from the Central Government regarding the extension of the term of

projects under the National Rural Urban Mission Scheme, the bills, either

in part or in full of ongoing projects, ought to be prepared and submitted. It

is in the above circumstances that the petitioner has approached this

Court seeking directions to permit him to continue the work as well as to

pay the cost incurred by him till the stop memo was issued.

6. Respondents 1 and 2 have filed a counter affidavit pointing out

that the work has been directed to be stopped with the intention of

avoiding any additional loss to the petitioner in the event the Central

Government, which is the funding agency, stops funding the project. It was

further pointed out that since the extension of time is a policy of the

Central Government, it is beyond the control of the first and second

respondents. However, it was pointed out that the Panchayat has already

prepared a valuation for the work which was done by the petitioner till

date, and if the fourth respondent is willing to sanction the fund, the

Panchayat is ready to withdraw the stop memo and allow the petitioner to

finish the work. It was further stated that in respect of another work, a

savings of Rs.50,92,330/- has been returned from the Water Authority in

another project, which amount is kept idle in the Grama Panchayat

account and if the fourth respondent permits, the Panchayat is ready to

utilise the said fund for completing the project. The first respondent has

also stated that a request has already been made to the fourth respondent

for sanctioning the above.

7. A counter affidavit has also been filed by the fourth respondent -

the Rural Development Commissioner stating that the funds for the

National Rurban Mission are shared by the Central Government and the

State Government in the ratio of 60:40 and that the fund for the scheme is

kept in the State nodal account and allocated to the clusters as per

demands. It is also stated that the funds are allocated as and when they

receive the fund request. According to the fourth respondent on

18-07-2022, the State Government received a communication from the

Government of India bearing DO No. K-11011/01/2020-Rurban stating that

funds shall be released only for ongoing projects as critical gap funds, and

the same should be capped as per the committed liabilities as on

31-03-2022, and no funds shall be released for new projects undertaken

after 31-03-2022. It was further stated that this information was

communicated to the clusters by letter dated 21-07-2022. Fourth

respondent further averred that since funds will be provided only for the

works that started before 31-03-2022 and since the agreement for this

particular work was executed on 13-06-2022, it is not possible to give the

CGF fund to the contractor through the MIS platform. It is also stated that,

since the work is not considered as an ongoing work and the Government

of India has given permission only to make payments for works which are

ongoing, it is not possible to make payment for the work from the National

Rurban Mission.

8. I have heard Smt. Sumathy Dandapani, the learned Senior

Counsel, Sri. K.S. Arun Kumar, the learned Standing Counsel for

respondents 1 and 2 and Smt. Amminikutty, the learned Senior

Government Pleader.

9. Admittedly, bids were invited by the respondents for the work

'Puthuppally Food Processing Unit' on 03-04-2022, as is evident from

Ext.P2. The invitation was published by the respondents and the

petitioner had no role in the invitation. Pursuant to the said invitation,

petitioner submitted his tender and was awarded the work and the

agreement was also executed on 06-06-2022. Petitioner had even

commenced his construction activities thereafter. Even then, respondents

had no case that the work will not be funded by the Central Government.

After the work commenced, the first respondent issued Ext.P8 stop memo

on 29-07-2022. The work was directed to be stopped not because of any

default on the part of the petitioner but because the Government had not

agreed to fund the projects after 31-03-2022. These are all internal

matters and the petitioner had no role in it. The default is undoubtedly not

that of the petitioner, and he cannot be subjected to any prejudice.

10. During the course of arguments, it was submitted by the

respondents that whatever work carried out by the petitioner had been

demolished subsequent to Ext.P8 stop memo. In such circumstances, it

may not be conducive to quash Ext.P8 stop memo and permit the

petitioner to continue the work.

11. However, it is admitted in the counter affidavit of the first

respondent that the Panchayat has already assessed the quantum of work

carried out by the petitioner.

12. Since the petitioner cannot be blamed for issuing Ext.P8, and

the default is entirely that of the respondents in issuing an invitation for

tender after 31-03-2022 and also executing the agreement and thereafter

permitting the petitioner to commence work, under no circumstances can

any liability befall the petitioner. It is also evident from the affidavit of the

first respondent that funds are available with the Panchayat to fund almost

the entire project itself, provided the fourth respondent gives appropriate

sanction. However, since the project is no longer feasible, it is not legally

proper to permit the petitioner to continue with the work. However, the

respondents are liable to pay the cost incurred by the petitioner for the

work already carried out, till the issuance of the stop memo.

13. In the result, though Ext.P8 stop memo is not interfered with,

there will be a direction to respondents 1 to 4 to issue appropriate orders

to pay the entire cost of the work carried out by the petitioner under Ext.P4

agreement till Ext.P8 stop memo was issued and as already assessed by

the fourth respondent. The orders as directed above, shall be issued

within three months from the date of receipt of a copy of this judgment.

The writ petition is allowed in part.

Sd/-

BECHU KURIAN THOMAS JUDGE vps

APPENDIX OF WP(C) 40465/2022

PETITIONER'S/S' EXHIBITS EXHIBIT P1 TRUE COPY OF THE REGISTRATION CARD ISSUED TO THE PETITIONER HAVING VALIDITY TILL 31.03.2023.

EXHIBIT P2               TRUE   COPY   E    TENDER  BEARING   NO.
                         IV/AE/ISGD/PLY/2032 23/FIENT INVITED BY
                         THE 1ST RESPONDENT FOR THE CONSTRUCTION
                         OF   A   FOOD   PROCESSING  UNIT   DATED
                         03.04.2022.
EXHIBIT P3               TRUE COPY OF THE SELECTION NOTICE ISSUED
                         TO THE PETITIONER BY THE 1ST RESPONDENT
                         DATED 25.05.2022.
EXHIBIT P4               TRUE   COPY  OF   THE   AGREEMENT  DATED
                         06.06.2022 ENTERED INTO BETWEEN THE
                         PETITIONER AND THE 1ST RESPONDENT.
EXHIBIT P5               TRUE COPY OF THE TERM DEPOSIT (FIXED
                         DEPOSIT) CERTIFICATE DATED 01.06.2022
                         ISSUED BY THE TREASURY SAVINGS BANK IN
                         THE NAME OF THE PETITIONER PLEDGED TO
                         THE 1ST RESPONDENT.
EXHIBIT P6               TRUE COPY OF THE ACKNOWLEDGEMENT FORM OF
                         HANDING OVER THE SITE TO THE PETITIONER
                         DATED 06.06.2022 ISSUED BY THE 1ST
                         RESPONDENT.
EXHIBIT P7               TRUE COPY OF THE POWER OF ATTORNEY
                         EXECUTED BY THE PETITIONER IN FAVOUR OF
                         THE SOUTH INDIA BANK LTD.
EXHIBIT P7(a)            TRUE COPY OF THE ITEM RATE BOQ SHOWING
                         ITEMIZED PRICE AND WORK SCHEDULE.
EXHIBIT P8               TRUE COPY OF THE LETTER BEARING NO.
                         51/AE/PLY/22-23 DATED 29.07.2022 ISSUED
                         BY   THE    1ST   RESPONDENT   TO   THE
                         PETITIONER .



EXHIBIT P9            TRUE COPY OF THE REPRESENTATION DATED
                      01.09.2022 SUBMITTED BY THE PETITIONER
                      TO THE 1ST RESPONDENT.
EXHIBIT P10           TRUE COPY OF LETTER BEARING NO. SC1-
                      1698/2022 DATED 18.07.2022 ISSUED BY THE
                      SECRETARY, PUTHUPPALLY GRAMA PANCHAYAT
                      TO THE 1ST RESPONDENT .
EXHIBIT P11           TRUE COPY OF THE LETTER BEARING NO.
                      3494/R14/2022/CRD    DATED   21.07.2022
                      ISSUED   BY    THE   RURAL  DEVELOPMENT
                      COMMISSIONER TO ALL POVERTY ALLEVIATION
                      SECTION PROJECT DIRECTORS.
EXHIBIT P12           TRUE COPY OF THE DECISION TAKEN DURING
                      THE ORDINARY MEETING OF PUTHUPPALLY
                      GRAMA PANCHAYAT HELD ON 18.05.2022 TO
                      SELECT THE PETITIONER FOR CONSTRUCTION
                      OF PUTHUPPALLY FOOD PROCESSING UNIT.
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter