Monday, 11, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

D.Johny vs The State Of Kerala
2024 Latest Caselaw 5719 Ker

Citation : 2024 Latest Caselaw 5719 Ker
Judgement Date : 20 February, 2024

Kerala High Court

D.Johny vs The State Of Kerala on 20 February, 2024

Author: P Gopinath

Bench: P Gopinath

               IN THE HIGH COURT OF KERALA AT ERNAKULAM
                               PRESENT
                THE HONOURABLE MR. JUSTICE GOPINATH P.
    TUESDAY, THE 20TH DAY OF FEBRUARY 2024 / 1ST PHALGUNA, 1945
                       WP(C) NO. 20242 OF 2019
PETITIONER:

          D.JOHNY,
          AGED 58 YEARS
          S/O. DASAN NADAR, PWD CONTRACTOR, KAITHARA,
          VELLAPPALLY, NARUVAMOOD P.O., NEYYATTINKARA - 695 528.

          BY ADVS.
          T.T.MUHAMOOD
          SRI.A.RENJIT
          SRI.V.E.ABDUL GAFOOR
          SRI.A.MOHAMMED SAVAD
          SRI.C.Y.VINOD KUMAR



RESPONDENTS:

    1     THE STATE OF KERALA,
          REPRESENTED BY THE SECRETARY TO GOVERNMENT,
          PUBLIC WORKS DEPARTMENT, GOVERNMENT SECRETARIAT,
          THIRUVANANTHAPURAM - 695 001.

    2     THE CHIEF ENGINEER,
          OFFICE OF THE CHIEF ENGINEER, PWD ROADS & BRIDGES,
          THIRUVANANTHAPURAM - 695 001.

    3     THE SUPERINTENDING ENGINEER,
          PWD ROADS & BRIDGES, SOUTH CIRCLE,
          THIRUVANANTHAPURAM - 695 001.

    4     THE EXECUTIVE ENGINEER,
          OFFICE OF THE EXECUTIVE ENGINEER, PWD ROADS DIVISION,
          THIRUVANANTHAPURAM - 695 001.

          BY SRI.VENUGPAL V, GOVERNMENT PLEADER


     THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
20.02.2024, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 WP(C) NO. 20242 OF 2019
                                   2

                             JUDGMENT

The petitioner was a PWD contractor. During the year 1999,

the petitioner was awarded with the work of reconstruction of

Vizhinjam Bridge situated on Thiruvananthapuram - Vizhinjam

Road. According to the petitioner, due to gross delay in handing over

the site, the petitioner was entitled to a revision of the quoted rates.

The petitioner had sought a revision of 54% above the 1999 Schedule

of Rates. However, through Ext.P2 proceedings while granting

enhancement of rates (considering the delay in handing over the

site) the enhancement granted was only 35% above the 1999

Schedule of Rates and only for the work done after 31.12.2002. The

petitioner approached this Court by filing W.P.(C)No.11926 of 2015,

which was disposed of by Ext.P3 judgment setting aside Ext.P2

order and directing reconsideration of the matter. This Court had

interfered with Ext.P2 order specifically on the ground that the case

of the petitioner that certain other contractors similarly situated had

been granted 65% enhancement over the 1999 Schedule of Rates had

not been considered and the reason for declining the enhancement

as sought for by the petitioner is not discernible from Ext.P2 and on

the ground that Ext.P2 proceeds only the basis of the

recommendation made by the Chief Engineer. In compliance with WP(C) NO. 20242 OF 2019

the directions contained in Ext.P3 judgment of this Court in W.P.

(C)No.11926 of 2015, the Government passed Ext.P4 order which

was again challenged by the petitioner by filing W.P.(C)No.7493 of

2018. This Court through Ext.P6 judgment dated 30.07.2018 set

aside Ext.P4 order upon the finding that the matter was not

considered in terms of the directions issued by this Court in Ext.P3

judgment. Thereafter, the Government has passed Ext.P7 order

considering all contentions taken by the petitioner and finding that

the petitioner is entitled to 35% above the 1999 Schedule of Rates in

respect of all the works without restricting it in any manner as was

originally done through Ext.P2 order. Therefore, in addition to the

amount sanctioned earlier i.e. Rs.22,55,655/-, an additional amount

of Rs.3,54,367/- was sanctioned to be paid to the petitioner.

2. The learned Government Pleader would submit with

reference to the statement filed in this case that the Government

have considered the entire matter in Ext.P7 and has found that the

petitioner is entitled only to 35% above the 1999 Schedule of Rates

for the entire work done by the petitioner. It is submitted that the

said decision is not illegal or arbitrary warranting interference at the

hands of this Court under Article 226 of the Constitution of India. It

is also submitted that the question as to whether the petitioner is WP(C) NO. 20242 OF 2019

entitled to any further amount is essentially a disputed question of

fact, which cannot be adjudicated in proceedings under Article 226

of the Constitution of India.

3. Having considered the contentions raised and having

perused Ext.P7 order dated 24.05.2019, I am of the view that the

petitioner has not made out any case for grant of relief. It is clear

from Ext.P7 that the Government decided to restrict the claim of the

petitioner for enhancement to 35% above the 1999 Schedule of

Rates, after taking into consideration of the fact that in almost

identical circumstances for the Thrikkannapuram Bridge, 35% above

the 1999 Schedule of Rates alone was granted to the contractor.

Ext.P7 order also records that for works tendered by the PWD Roads

& Bridges, South Circle, Thiruvananthapuram, the enhancements

awarded ranged from 30 to 35% above the estimate rate and hence,

the claim of the petitioner for enhancement can be fixed at 35%

above the 1999 Schedule of Rates. It is also found that the contractor

has already been awarded a sum of Rs.1,38,31,058/- which was

Rs.33,23,335/- more than the estimate rate based on the 1999

Schedule of Rates. In other words, Ext.P7 has sanctioned

enhancement at the rate of 35% for all the work completed by the

petitioner above the 1999 Schedule of Rates, while the claim of the WP(C) NO. 20242 OF 2019

petitioner was for 54%. In the facts and circumstances of the case, I

find no ground made out for interference with Ext.P7 order. A

question as to whether the petitioner must be granted further

enhancement is not a claim that can be adjudicated in proceedings

under Article 226 of the Constitution of India. Ext.P2 order was set

aside by this Court only on the ground that there was no proper

consideration of the contentions taken by the petitioner. Ext.P4

order was set aside on the ground that on reconsideration, the

matter had not been considered as directed by this Court in Ext.P3

judgment. There is no finding on the merits of the petitioner's claim

for enhancement at the rate of 54% above the 1999 Schedule of

Rates. All the claims of the petitioner have been considered in Ext.P7

order and the Government have decided to grant enhancement at

35% above the 1999 Schedule of Rates for all the work done by the

petitioner. There is no illegality, irrationality or impropriety in

Ext.P7 warranting interference with it in exercise of jurisdiction

vested in this Court under Article 226 of the Constitution of India.

The writ petition fails and it is accordingly dismissed.

Sd/-

GOPINATH P. JUDGE DK WP(C) NO. 20242 OF 2019

APPENDIX OF WP(C) 20242/2019

PETITIONER EXHIBITS

EXHIBIT P1 TRUE COPY OF RECOMMENDATION DATED 06.06.06 OF THE 2ND RESPONDENT.

EXHIBIT P2 TRUE COPY OF G.O. (RT) NO. 942/14/PWD DATED 04.07.2014.


EXHIBIT P3        TRUE COPY OF JUDGMENT DATED 28.11.2016


EXHIBIT P4        TRUE COPY OF G.O. (RT) NO.
                  1814/2017/PWD DATED 4.12.2017

EXHIBIT P5        TRUE COPY OF HEARING NOTE RECEIVED
                  UNDER RTI ACT.

EXHIBIT P6        TRUE COPY OF JUDGMENT DATED 30.7.2018 I
                  WPC NO.7493/2018 PASSED BY THIS HONBLE
                  COURT.

EXHIBIT P7        TRUE COPY OF GO (RT) NO.606/2019/PWD
                  DATED 24.5.2019

EXHIBIT P8        TRUE COPY OF RELEVANT EXTRACT OF THE
                  HEARING NOTE

EXHIBIT P9        TRUE COPY OF SALE DEED EXECUTED BY THE
                  PETITIONER WITH THE SECRETARY KERALA
                  GOVERNMENT SECRETARIAT STAFF HOUSING
                  CO-OPERATIVE SOCIETY LTD ON 12.06.2008

EXHIBIT P10       TRUE COPY OF THE CERTIFICATE ISSUED BY
                  THE CHIEF MANAGER, THE FEDERAL BANK
                  LTD. PAPPANAM CODE BRANCH ON 07.04.2017
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter