Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Electronics Technology Park- Kerala vs United Electrolinks
2024 Latest Caselaw 5704 Ker

Citation : 2024 Latest Caselaw 5704 Ker
Judgement Date : 20 February, 2024

Kerala High Court

Electronics Technology Park- Kerala vs United Electrolinks on 20 February, 2024

Author: Sathish Ninan

Bench: Sathish Ninan

            IN THE HIGH COURT OF KERALA AT ERNAKULAM
                               PRESENT
            THE HONOURABLE MR. JUSTICE SATHISH NINAN
   TUESDAY, THE 20TH DAY OF FEBRUARY 2024 / 1ST PHALGUNA, 1945
                         RFA NO. 545 OF 2015
 AGAINST THE JUDGMENT IN OS 140/2004 OF I ADDITIONAL SUB COURT,
                         THIRUVANANTHAPURAM
                                -----
APPELLANTS/DEFENDANTS:

    1     ELECTRONICS TECHNOLOGY PARK- KERALA,
          TECHNOPARK, REP. BY ITS C.E.O,
          KAZHAKKUTTOM,THIRUVANANTHAPURAM - 695 581.

    2     CHIEF EXECUTIVE OFFICER AND REGISTRAR,
          ELECTRONICS TECHNOLOGY PARK- KERALA, TECHNOPARK,
          KAZHAKKUTTOM, THIRUVANANTHAPURAM - 695 581.

          BY ADVS.
          SRI.M.SREEKUMAR
          SRI.A.ABDUL KHARIM


RESPONDENT/PLAINTIFF:

          UNITED ELECTROLINKS,
          A DIVISION OF ESSJAY ELECTROLINKS PVT.LTD., REP. BY
          MR.SHAJI SEBASTIAN, MD, ESSJAY ELECTROLINKS PVT. LTD.
          MANAPPATT CENTRE, HMT JUNCTION,
          KALAMASSERY,KANAYANNOOR TALUK, ERNAKULAM 683 104.

          BY ADVS.
          ALEX ANTONY SEBASTIAN P.A.
          M.B.VINOD




     THIS REGULAR FIRST APPEAL HAVING COME UP FOR HEARING ON
20.02.2024, ALONG WITH CO.172/2022, THE COURT ON THE SAME DAY
DELIVERED THE FOLLOWING:
             IN THE HIGH COURT OF KERALA AT ERNAKULAM
                               PRESENT
            THE HONOURABLE MR. JUSTICE SATHISH NINAN
   TUESDAY, THE 20TH DAY OF FEBRUARY 2024 / 1ST PHALGUNA, 1945
                          CO NO. 172 OF 2022
 AGAINST THE JUDGMENT IN OS 140/2004 OF I ADDITIONAL SUB COURT,
                          THIRUVANANTHAPURAM
                                -----
CROSS APPELLANT/RESPONDENT:

          UNITED ELECTROLINKS, A DIVISION OF ESSJAY ELECTROLINKS
          (P) LTD., MANAPATTU CENTER, HMT JUNCTION, KALAMASSERY
          COCHIN-682104 REP. BY ITS MANAGING DIRECTOR, SHAJI
          SEBASTIAN.


          PRESENTLY   THE   ENTITY   IS   MERGED   WITH   ESSJAY
          ELECTROLINKS (P) LTD., KALLINGAPARAMBIL, NOCHIMA NAD
          P.O., ALUVA, ERNAKULAM PIN 683563 AND NOW OPERATING AT
          ITS CORPORATE OFFICE AT KALLINGAPARAMBIL, NOCHIMA, NAD
          P.O., ALUVA REP. BY ITS ADDL. DIRECTOR, LISHA JAYAN
          AGED 50 YEARS, W/O LATE SRI. JAYAN K.S., KAKKATIL
          HOUSE, ALATTUCHIRA P.O., KODANAD, PERUMBAVOOR, PIN-
          683544.

          BY ADVS.
          ALEX ANTONY SEBASTIAN P.A.
          M.B.VINOD



RESPONDENTS/APPELLANTS:

    1     ELECTRONICS TECHNOLOGY PARK- KERALA, TECHNOPARK, REP.
          BY ITS CEO, KAZHAKKUTTAM, THIRUVANANTHAPURAM, PIN
          695581.
 CO NO. 172 OF 2022              -2-


    2       CHIEF EXECUTIVE OFFICER & REGISTRAR, ELECTRONICS
            TECHNOLOGY PARK-KERALA, TECHNOPARK, REP. BY ITS CEO
            KAZHASKKUTTAM, THIRUVANANTHAPURAM PIN 695581.


     THIS   CROSS   OBJECTION   HAVING   COME   UP   FOR   HEARING   ON
20.02.2024, ALONG WITH RFA.545/2015, THE COURT ON THE SAME DAY
DELIVERED THE FOLLOWING:
                    SATHISH NINAN, J.
          = = = = = = = = = = = = = = = = = =
                 R.F.A. No.545 of 2015
                            &
            Cross Objection No.172 of 2022
          = = = = = = = = = = = = = = = = = =
       Dated this the 20th day of February, 2024

                    J U D G M E N T

The suit for money under a works contract was

decreed in part. The defendant and the plaintiff are

before this Court through appeal and cross objections

respectively.

2. As per Ext.B2 dated 19.02.2001, the defendant

invited tender for electrification of their building.

The plaintiff was the successful tenderer. Ext.A4 dated

26.04.2001 is the agreement between the parties. The

work was to be completed within four months. However,

the plaintiff failed to complete the work within time.

As per Ext.A20 = Ext.B13 dated 10.07.2002, the contract

was terminated and the work was re-tendered. The suit

was filed for realisation of the balance amounts payable

to the plaintiff, for the works done by him. RFA No.545/2015 &

3. The defendant contended that there was

inordinate delay on the part of the plaintiff in

completing the work which led to the re-tender. The re-

tender was for a higher rate which resulted in loss to

the defendant. So also the tender contained a penalty

clause for recovery of penalty at the rate of 1% of the

probable amount of contract for every week, subject to a

maximum of 10%. The defendants are entitled to realise

the said amount from the plaintiff.

4. The trial court found that the plaintiff was

responsible for the delay in carrying out the work. It

was held that the defendant is entitled to realise the

loss suffered consequent on the re-tender. The claim for

penalty for the delay was declined stating that the

plaintiff was permitted to continue with the work even

after the period stipulated in the contract and that

thereafter penalty clause could not be invoked. It was

also held that the relevant clause enabling recovery of RFA No.545/2015 &

penalty is only during the currency of contract and not

after its termination. Challenging the declining of

penalty, the defendant has preferred the appeal. The

plaintiff is in cross objections challenging the grant

of decree for damages under the head of re-tender.

5. Heard learned counsel on either side.

6. The points that arise for determination are :-

(i) Was the plaintiff responsible for the delay in

completion of the works under the contract ?

(ii) Was the trial court right in having held the plaintiff

liable for the loss/damages consequent on the re-tender ?

(iii) Was the trial court right in having declined the claim

of the defendant for the penalty?

(iv) Without a claim of set-off, is the defendant entitled to

seek for recovery of amounts under the heads of damages

consequent on re-tender and penalty for delay?

7. As per the agreement between the parties, the

work was to be completed within four months. The RFA No.545/2015 &

plaintiff contended that there was delay on the part of

the defendant in handing over the site which contributed

the delay in performance. Ext.A5 communication by the

plaintiff to the District Electrical Inspector would

indicate otherwise. There is no material to the contrary

to suggest that there was delay in handing over of the

site. The trial court found against the contention of

the plaintiff. Ext.A7 is the time schedule suggested by

the plaintiff to the defendant wherein the work was to

be completed by 08.08.2001. Ext.A9 is the revised time

schedule. Therein the date for completion is suggested

as 30.08.2001. Ext.A15 is yet another revised time

schedule submitted by the plaintiff. Therein the date of

completion is given as 30.09.2001. Ext.A16 is the letter

dated 11.10.2001 by the plaintiff seeking for time for

completion. Ext.B12 is the letter dated 18.06.2002 by

the plaintiff to the defendant wherein he has pointed

out his inability to complete the work due to pendency RFA No.545/2015 &

of the proceedings with the Bank at the Debts Recovery

Tribunal. On the materials it is evident that the

plaintiff was responsible for the delay. The trial court

has rightly found so.

8. The trial court has allowed the defendant to

deduct an amount of ` 4,21,531/- towards damages

suffered consequent on the re-tendering of the work. It

is the defendant's contention that the plaintiff's quote

was 17% below the probable amount of contract whereas in

the re-tender the quote was 6% below the probable amount

of contract. This has resulted in damages of 11%. The

defendant quantified the same at ` 4,21,531/-. The

defendant claims that they have the right to recover the

said amount from the plaintiff.

9. Though the defendant claims that the re-

tendering was at 6% below the PAC, curiously no document

in the said regard is produced. When the defendant

claims damages that has allegedly occasioned consequent RFA No.545/2015 &

on the re-tendering, it was for the defendant to produce

the relevant documents to prove the damages. The

documents relating to the re-tendering, including the

quote at 6% below the probable amount of contract, was

available with the defendants. However, the defendant

has not produced the same before the Court. The

contention that there was difference of 11% in the re-

tender, remained unsubstantiated. The finding of damages

by the trial court is without any material. The said

finding is liable to be interfered with.

10. It is the case of the defendant that the trial

court went wrong in not awarding penalty for the delay.

The agreement permits recovery of 1% probable amount of

contract for damages for every week of delay subject to

a maximum of 10%. It is to be noticed that, but for a

claim that the defendant is entitled to realise the

penalty, there is no prayer for set off. Order VIII Rule

6 of the Code of Civil Procedure reads thus:-

RFA No.545/2015 &

"6. Particulars of set-off to be given in written statement.--

(1) Where in a suit for the recovery of money the defendant claims to set-off against the plaintiff's demand any ascertained sum of money legally recoverable by him from the plaintiff, not exceeding the pecuniary limits of the jurisdiction of the Court, and both parties fill the same character as they fill in the plaintiff's suit, the defendant my, at the first hearing of the suit, but not afterwards unless permitted by the Court, present a written statement containing the particulars of the debt sought to be set-off.

(2) Effect of set-off.- The written statement shall have the same effect as a plaint in a cross-suit so as to enable the Court to pronounce a final judgment in respect both of the original claim and of the set-off; but this shall not affect the lien, upon the amount decreed, of any pleader in respect of the costs payable to him under the decree.

(3) The rules relating to a written statement by a defendant apply to a written statement in answer to a claim of set-off."

Section 8 of the Court Fees and Suits Valuation Act

prescribes the fee payable for set off to be the same as

that for a plaint. There is no specific plea of set off RFA No.545/2015 &

and no court fee is paid. At paragraph 26 of the written

statement what is pleaded is that, "The final bill is produced

after the termination of the contract and the said bill could be settled only

after fixing the liabilities, penalties, risk and cost, damages, compensation,

expenses etc." There is no plea that the amounts due to the

defendant were already adjusted. Therefore, in the

absence of a plea of set off there was no occasion for

the trial court to adjudicate on the said claim.

Therefore, though for varying reason from that of the

trial court, the rejection of the claim of the defendant

under the head of penalty by the trial court does not

warrant interference. So also, with regard to the claim

for damages for re-tendering which has been dealt with

earlier, the defendant ought to have raised a plea of

set off.

11. Therefore, while upholding the judgment of the

trial court to the extent it declined the defendant's

claim for penalty, the grant of damages consequent on RFA No.545/2015 &

re-tendering is to be set aside.

12. The trial court had found that the decree

amount due to the plaintiff from the defendant is

` 22,54,621/-. From the said amount the trial court

deducted ` 4,21,531/- towards the claim for damages for

re-tender. Such deduction is not liable to be made.

Plaintiff is entitled to realise ` 22,54,621/-.

13. The trial court has granted interest from

10.07.2002 which is the date of termination of the

contract till date of realisation. It is to be noticed

that, though the termination of the contract was on

10.07.2002 the suit was filed only on 11.03.2004 ie.

after the period of almost two years. Considering the

delay involved, I am of the opinion that the plaintiff

is not entitled for interest during the said period and

the same is declined. Plaintiff is entitled for interest

as granted by the trial court but from the date of suit. RFA No.545/2015 &

14. The learned counsel for the defendants-

appellants would point out that, pursuant to the decree

the defendant has deposited the decree amount before the

trial court on 09.01.2017. Necessarily, the plaintiff

shall not be entitled for interest for such amount from

the date of deposit.

Resultantly, the appeal and cross objection are

allowed and a modified decree is passed as hereunder.

The plaintiff is granted a decree for realisation of an

amount of ` 22,54,621/- with interest at the rate of 6%

per annum from the date of suit till realisation. It is

clarified that the amount deposited by the defendant

pursuant to the decree of the trial court shall be

liable to be deducted therefrom and that the plaintiff

shall not be entitled for interest for such amount, from

the date of deposit. No costs.

Sd/-

                                                    SATHISH NINAN
                                                         JUDGE

kns/-                         //True Copy//               P.S. to Judge
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter