Citation : 2024 Latest Caselaw 5406 Ker
Judgement Date : 16 February, 2024
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE V.G.ARUN
FRIDAY, THE 16TH DAY OF FEBRUARY 2024 / 27TH MAGHA, 1945
CRP NO. 405 OF 2021
AGAINST THE ORDER/JUDGMENT OPELE 632/2013 OF VI
ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:
GOPINATHAN NAIR
AGED 56 YEARS
ILLIKATHARA HOUSE,MATTATHURKUNNU P.O., MATTATHUR
VILLAGE,MUKUNDAPURAM TALUK - 680 684 REP. BY POWER OF
ATTORNEY HOLDER, HIS WIFE SOJA, AGED 56 YEARS.
BY ADV P.T.JOSE
RESPONDENT/S:
1 POWER GRID CORPORATION OF INDIA LTD
CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY,
KAKKANAD, COCHIN - 682 030 NOW IN PAO/400, 220KV
SUBSTATION, KUMARAPURAM P.O., PALLIKARA, KOCHI - 682
303, REP. BY DEPUTY MANAGER.
2 THE SPECIAL TAHSILDAR (L.A.)
POWERGRID CORPORATION OF INDIA LTD., THRIKKKARA
VILLAGE, KANAYANNOOR TALUK, KAKKANAD P.O. - 682 030.
3 STATE OF KERALA
REPRESENTED BY DISTRICT COLLECTOR, ERNAKULAM, KOCHI -
682 030.
4 KERALA STATE ELECTRICITY BOARD
REPRESENTED BY CHAIRMAN AND MANAGING DIRECTOR, KSEB
LTD., THIRUVANANTHAPURAM - 695 001.
BY ADV R.HARISHANKAR
OTHER PRESENT:
SC FOR KSEB A. ARUNKUMAR; SR.GP.K.P.HARISH
THIS CIVIL REVISION PETITION HAVING BEEN FINALLY
HEARD ON 04.12.2023, ALONG WITH CRP.140/2023, THE COURT
ON 16.02.2024 DELIVERED THE FOLLOWING:
CRP Nos.405/21 & 140/23
-2-
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE V.G.ARUN
FRIDAY, THE 16TH DAY OF FEBRUARY 2024 / 27TH MAGHA, 1945
CRP NO. 140 OF 2023
AGAINST THE ORDER/JUDGMENT OPELE 632/2013 OF VI
ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:
POWER GRID CORPORATION OF INDIA
POWER GRID CORPORATION OF INDIA LTD.,
CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY,
KAKKANAD, COCHIN - 682 030, PRESENTLY AT
CONSTRUCTION AREA OFFICE, 400/220, KV SUB
STATION, KUMARAPURAM P.O, PALLIKKARA, ERNAKULAM
REPRESENTED BY ITS SENIOR GENERAL MANAGER, PIN -
683565
BY ADV MILLU DANDAPANI
RESPONDENT/S:
1 GOPINATHAN NAIR
ILLIKKATHARA HOUSE, MATTATHURKUNNU P.O ,
MATTATHUR VILLAGE, MUKUNDAPURAM TALUK. REP. BY
POWER OF ATTORNEY HOLDER, HIS WIFE SOJA, PIN -
680684
2 THE SPECIAL TAHSILDAR (LA)
POWER GRID CORPORATION OF INDIA LTD.
CHEVARAMBALAM, KOZHIKODE, PIN - 673017
3 STATE OF KERALA
REPRESENTED BY DISTRICT COLLECTOR, ERNAKULAM,
KOCHI, PIN - 682030
4 KERALA STATE ELECTRICITY BOARD - KSEB
REPRESENTED BY CHAIRMAN & MANAGING DIRECTOR KSEB
LTD., THIRUVANANTHAPURAM, PIN - 695001
5 SOJA K.K ( SOUGHT TO BE IMPLEADED )
W/O. LATE GOPINATHAN NAIR, AGED 58 YEARS,
ELLIKKATHARA, KAVANADU, MATTATHUR VILLAGE,
CRP Nos.405/21 & 140/23
-3-
MUKUNDAPURAM TALUK, THRISSUR ( SOUGHT TO BE
IMPLEADED )
6 DEVIKA SANGHAMITHRA ( SOUGHT TO BE IMPLEADED )
D/O LATE GOPINATHAN NAIR, AGED 31 YEARS,
ELLIKKATHARA, KAVANADU, MATTATHUR VILLAGE,
MUKUNDAPURAM TALUK, THRISSUR ( SOUGHT TO BE
IMPLEADED )
BY ADV P.T.JOSE
THIS CIVIL REVISION PETITION HAVING BEEN FINALLY
HEARD ON 04.12.2023, ALONG WITH CRP.405/2021, THE COURT
ON 16.02.2024 DELIVERED THE FOLLOWING:
CRP Nos.405/21 & 140/23
-4-
ORDER
Dated this the 16th day of February, 2024
These revision petitions are filed
challenging the common order passed by the
Additional District Judge-VI, Ernakulam in O.P.
(Electricity) No.632 of 2013. The original
petition was filed by the revision petitioner in
CRP No.405 of 2021 (hereinafter called 'the
claimant'), being dissatisfied with the
compensation awarded towards the damage and loss
sustained due to the drawing of 400 KV lines
across his property by the Power Grid Corporation
of India Ltd (hereinafter called 'the
Corporation'). The essential facts are as under;
The claimant is in ownership and possession
of landed property having an extent of 55 cents
comprised in Sy.No.1492/1 of Mattathur Village in
Mukundapuram Taluk. The land was cultivated with
various yielding and non-yielding trees. CRP Nos.405/21 & 140/23
According to the claimant, to facilitate drawing
of the lines and smooth transmission of power,
large number of trees were cut from his property.
The drawing of high tension lines rendered the
land underneath and adjacent to the lines
useless, resulting in diminution of the value of
the property. In spite of the huge loss suffered
by the claimant, only an amount of Rs.61,133/-
was paid as compensation towards the value of
yielding and non-yielding trees cut.
Surprisingly, no compensation was granted for
diminution in land value. Hence, the original
petition was filed, seeking enhanced compensation
towards the value of trees cut and diminution in
land value.
2. The court below rejected the claim for
enhanced compensation for the value of trees cut
since no evidence in support of the claim was
produced. As far as the claim for enhanced
compensation towards diminution in land value is CRP Nos.405/21 & 140/23
concerned, the court below relied on Ext.A5
document as well as Exts.C5 and C5(a) commission
report and plan. The Advocate Commissioner
reported that a double-storied house is situated
in the northern side of the claimant's property
which lies 750 metres away from the Vellappady
Junction and is in close proximity to important
places of worship and pilgrim centres. Based on
these factors, the court below fixed the land
value of the claimant's property by deducting 10%
of the value shown in Ext.A5 property. Relying on
Ext.C5(a) sketch, the extent of central corridor
was held to be 18.115 cents and of the outer
corridors, 17.743 cents. For the central
corridor, 40% of the land value was granted as
compensation and for the outer corridors, 20% of
the land value. Accordingly, the claimant was
found entitled to compensation of Rs.21,86,672/-.
Dissatisfied with the quantum of enhancement, the
claimant has filed CRP No.405 of 2021, whereas CRP Nos.405/21 & 140/23
the Corporation has filed CRP No.140 of 2023
contending that the enhancement ordered is far in
excess of the actual damage sustained.
3. Heard Adv.P.T.Jose for the claimant and
Adv.Millu Dandapani for the Corporation.
4. Learned Counsel for the claimant
contended that the court below committed gross
illegality in refusing to grant enhanced
compensation for the loss sustained due to the
cutting of valuable trees, in spite of the
Advocate Commissioner assessing and reporting the
loss. The findings in the Commissioner's report
were not relied on by the court below for the
reason that the property was inspected much after
the trees were cut. The said reasoning is flawed
since the trees were cut much after issuance of
notification by the Corporation and the cause of
action for filing the original petition arose
only on payment of the initial compensation, even
later. It is submitted that the claimant's CRP Nos.405/21 & 140/23
property is situated at the eastern side of
Vellappady-Kavanadu road and only 750 metres away
from the Vellappady junction. Moreover, the
Kanakamala pilgrim centre is just 3 kms away from
the property and Kodakara junction, only 2.5 Kms
away. Without considering these crucial factors,
10% deduction was made from the value of the
property involved in Ext.A5 document.
5. It is submitted that the court below
grossly erred in granting only 40% of the land
value fixed for the central corridor and 20% for
the outer corridors. Considering the extent of
damage sustained and the diminution in land value
consequent to the drawing of lines, the court
below ought to have granted compensation as
claimed.
6. Learned Counsel for the Corporation
contended that, compensation towards diminution
in land value granted is exorbitant and there is
no rationale in granting 9% interest on that CRP Nos.405/21 & 140/23
amount. The court below also erred in relying on
Ext.A5 for fixing the land value of the
claimant's property. As the drawing of electric
lines does not prohibit the landowner from
conducting agricultural activities and putting up
small structures, 40% of the land value granted
for the central corridor and 20% for the outer
corridors are exorbitant.
7. A careful scrutiny of the impugned order
reveals that the claim for enhancement of
compensation towards the value of trees cut was
rightly rejected since no supporting material,
other than the findings in the Advocate
Commissioner's report, was made available. As
found by the court below, apart from the
interested testimony of a solitary witness, who
is the claimant in some of the connected cases,
no other independent witness was examined to
prove the claim. It is also not in dispute that
the trees were cut in the year 2011 and the CRP Nos.405/21 & 140/23
commissioner inspected the property in the year
2015 and assessed the value of the trees on a
comparison with the trees standing in the nearby
properties. Such comparison, having no scientific
basis, is not sufficient to discard the
contemporaneous valuation statement prepared by
the Corporation.
8. As far as the diminution in land value
is concerned, the factors to be taken into
consideration, as laid down in KSEB v. Livisha
[(2007) 6 SCC 792] are as under;
"10. The situs of the land, the distance between the high voltage electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small tract of land or through the middle of the land and other similar relevant factors in our opinion would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the CRP Nos.405/21 & 140/23
purpose for which the same was meant to be used."
On careful scrutiny of the impugned order, it is
seen that the compensation was enhanced after
taking all the above factors into consideration.
The nature of the land, the cultivation therein,
the commercial importance of the area and the
manner in which the land was affected by drawing
of the lines have all been considered for fixing
the land value as well as the percentage of
diminution. The court below has deducted only 10%
of the land value in Ext.A5, which according to
me, is a reasonable deduction. For the central
corridor, 40% of the land value is granted as
compensation and for the outer corridors, 20% is
granted, which I find to be just and proper. As
such, there is no illegality or material
irregularity in the impugned order, warranting
intervention by this Court in exercise of the
revisional power under Section 115 of the Code of CRP Nos.405/21 & 140/23
Civil Procedure.
For the aforementioned reasons, the civil
revision petitions filed by the claimant as well
as the Corporation are dismissed. The Power Grid
Corporation shall pay the enhanced compensation
fixed by the court below within three months of
receipt of a copy of this order.
Sd/-
V.G.ARUN JUDGE Scl/ CRP Nos.405/21 & 140/23
PETITIONER ANNEXURES Annexure A COURT PROCEEDINGS OF VITH ADDITIONAL DISTRICT COURT ERNAKULAM DATED 24.08.2023
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!