Citation : 2023 Latest Caselaw 12744 Ker
Judgement Date : 8 December, 2023
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE BECHU KURIAN THOMAS
FRIDAY, THE 8TH DAY OF DECEMBER 2023 / 17TH AGRAHAYANA, 1945
WP(C) NO. 34585 OF 2023
PETITIONER:
M/S JOYS THE BEACH RESORTS PVT LTD,
REP BY ITS DIRECTOR, GEETHA JOSE THOTTAM,
AGED 63 YEARS W/O T C PAUL, HAVING OFFICE AT NO 3
LAKE VIEW ROAD, PUDUKUPPAM,
NALLAVADU POST, PONDICHERRY, PIN - 605 007.
BY ADVS.
BHARATH V GOPAL
INDRAJITH.I
THEJAN RAJ
RESPONDENTS:
1 CORPORATION OF THIRUVANANTHAPURAM
REPRESENTED BY ITS SECRETARY,
OFFICE AT VIKAS BHAVAN P.O PALAYAM
THIRUVANANTHAPURAM, PIN - 695 033.
2 SECRETARY
CORPORATION OF THIRUVANANTHAPURAM,
OFFICE AT VIKAS BHAVAN P.O PALAYAM
THIRUVANANTHAPURAM., PIN - 695 033.
3 DISTRICT TOWN PLANNER
OFFICE OF DISTRICT TOWN PLANNER,
REP BY ITS SECRETARY,
THIRUVANANTHAPURAM, PIN - 695 043.
4 STATE OF KERALA
REP BY SECRETARY LOCAL SELF GOVERNMENT,
URBAN DEPARTMENT ROOM NO 201 A, 2ND FLOOR ANNEX 1
SECRETERIATE, THIRUVANANTHAPURAM., PIN - 695 001.
BY ADV SUMAN CHAKRAVARTHY
SR.GP.K.AMMINIKUTTY
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
08.12.2023, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
W.P.(C) No.34585/23 -:2:-
BECHU KURIAN THOMAS, J
......................................................
W.P.(C).No.34585 of 2023
...................................................
Dated this the 8th day of December, 2023
JUDGMENT
Petitioner is the owner of 8.80 Ares of property in Re-survey
No.100 of Thycaud Village. A commercial building already exists
in the said property bearing building numbers T.C.No.26/908,
T.C No. 26/909 and T.C No. 26/910. Petitioner allegedly
constructed three additional floors over the existing structure
without permission. Thereafter petitioner sought regularization of
the additional constructions. By Ext.P6, the respondents rejected
the application which is challenged in this writ petition.
2. Petitioner's predecessor-in-interest had commenced construction
of a building on the basis of a permit issued prior to 2009.
Later, on 12-05-2009, petitioner's predecessor-in-title was issued
with a permit to construct three additional floors over the
existing structure. The building permit was renewed till 2018.
Subsequently, petitioner purchased the said property in 2019
and continued the construction in accordance with the permit
issued to the prior owner. In the meantime, the Interim
Development Order [for short, IDO] for the Corporation of
Thiruvananthapuram came into force. As per the IDO, a road of
27 mtrs. width is proposed, and hence, the setback required for
the building as per the rules is not available.
3. By the time the IDO came into force, the building was partially
completed with the ground floor and the first floor already
constructed. Even building numbers were allotted for the
completed portion. In the meantime, after completing the entire
structure, petitioner applied for a completion certificate, wherein
few defects were pointed out. Petitioner contends that though
four out of the five defects have already been rectified, the
remaining defect regarding the setback on the basis of the IDO
is a condition that is impossible for compliance or performance.
Petitioner submitted a representation as Ext.P9 requesting to
consider his application for regularization afresh.
4. A statement has been filed by the 2 nd respondent pointing out
that the width of the road proposed in the IDO in front of
petitioner's property is 27 mtrs., while the plan submitted by
the petitioner shows the width of the road as only 25 mtrs. It
was also pointed out that the setback now available from the
proposed road will be only 1.7 mtrs., and hence, setback is not
available as per Rules.
5. I have heard Sri.Thejan Raj, the learned counsel for the
petitioner, Sri.Suman Chakravarthy, the learned Standing
Counsel for the Panchayat and Smt. Amminikutty.K., the learned
Senior Government Pleader.
6. Petitioner's predecessor-in-interest had commenced construction
and had partially completed it. Building numbers had also been
allotted for two floors. The permit issued in 2009 permitted
additional constructions to be carried out. At the time the said
structure was constructed, it was in tune with the building rules
especially regarding the setback. The IDO came into force only
in 2017. The ground floor and first floor of the building had
been in existence from 2009 onwards. If the petitioner satisfied
the requirements of the building permit regarding the setback
for the ground floor and first floor as originally issued, on the
basis of which construction was carried out, then the stipulation
in the IDO regarding setback cannot apply to the constructions
over the existing structure. Subsequent construction over the
existing structure cannot be denied approval on the basis of the
setback stipulated in the IDO notified in 2017. Therefore, I am
of the view that Ext.P9 request for reconsidering the application
for regularization submitted by the petitioner is only to be
considered in a time bound manner.
7. Hence, there will be a direction to the 2 nd respondent to
reconsider and pass appropriate orders on the application for
regularization dated 25-05-2023 and Ext.P9 request dated
23-09-2023 submitted by the petitioner, as expeditiously as
possible, at any rate, within a period of 30 days from the date
of receipt of a copy of this judgment, bearing in mind the
observations made above.
The writ petition is disposed of.
BECHU KURIAN THOMAS JUDGE AMV/08/12/2023
APPENDIX OF WP(C) 34585/2023
PETITIONER EXHIBITS EXHIBIT P1 THE TRUE COPY OF THE REGISTERED SALE DEED NO 696/2019 SUB REGISTRAR CHALAI THIRUVANANTHAPURAM EXECUTED IN FAVOR OF THE PETITIONER EXHIBIT P2 THE TRUE COPY OF THE BUILDING PLAN AND PERMIT EXHIBIT P3 THE TRUE COPIES OF THE TAX PAYMENT RECEIPT DATED 22/3/2023.
EXHIBIT P4 THE TRUE COPY OF THE RECEIPT DATED 25/05/2023 ISSUED BY THE 1ST RESPONDENT ACKNOWLEDGING THE APPLICATION FOR REGULARISATION EXHIBIT P5 THE TRUE COPY OF THE NOC DATED 06/06/2023 EXHIBIT P6 TRUE COPY OF THE 1ST RESPONDENT HAD ISSUED A NOTICE DATED 27.07.2023 IN REPLY TO THE APPLICATION FOR REGULARISATION OF THE BUILDING FILED BY THE PETITIONER.
EXHIBIT P7 THE TRUE COPY OF THE LETTER NO.
E5/36589/23 DATED 11/9/2023
EXHIBIT P7(A) TRUE COPY OF THE NOTICE NO.D6-31/2013
DATED 18/9/2013
EXHIBIT P7(B) TRUE COPY OF THE NOTICE NO
E5/36589/2023 DATED 29/9/2023
EXHIBIT P7(C) TRUE COPY OF THE NOTICE NO 633/2023
DATED 3/10/2023
EXHIBIT P8 THE TRUE COPY OF THE ORDER DATED
11/09/2017 ISSUED BY THE LOCAL SELF
GOVERNMENT DEPARTMENT
EXHIBIT P9 THE TRUE COPY OF THE REPRESENTATION
DATED 23/9/2023 SUBMITTED BY THE
PETITIONER TO THE 2ND RESPONDENT
TRUE COPY
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!