Citation : 2023 Latest Caselaw 9018 Ker
Judgement Date : 23 August, 2023
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE VIJU ABRAHAM
WEDNESDAY, THE 23RD DAY OF AUGUST 2023 / 1ST BHADRA, 1945
WP(C) NO. 17363 OF 2023
PETITIONER:
M/S. RDS PROJECTS LTD.
A COMPANY INCORPORATED UNDER THE COMPANIES ACT, WITH
ITS REGISTERED OFFICE AT HO:427, SOMDUTT CHAMBERS-II,
9, BHIKAJI CAMA PLACE, NEW DELHI-110066 AND REGIONAL
OFFICE AT SHIHAB THANGAL ROAD, PANAMPILLY NAGAR, KOCHI-
682019 REPRESENTED BY ITS DIRECTOR, MR. AMIT VARGHESE
JOSEPH, AGED 32 YEARS, S/O DR. JOSEPH VARGHESE., PIN -
BY ADVS.P.MARTIN JOSE P.,P. PRIJITH,, THOMAS
P.KURUVILLA, R.GITHESH, AJAY BEN JOSE, MANJUNATH MENON,
SACHIN JACOB AMBAT, ANNA LINDA EDEN, HARIKRISHNAN S.
S.SREEKUMAR (SR.)
RESPONDENTS:
1 THE STATE OF KERALA REPRESENTED BY CHIEF SECRETARY
GOVERNMENT SECRETARIAT TRIVANDRUM -, PIN - 695001
2 PRINCIPAL SECRETARY, PWD ROADS DIVISION GOVERNMENT
SECRETARIAT TRIVANDRUM -, PIN - 695001
3 THE SUPERINTENDING ENGINEER,PUBLIC WORKS DEPARTMENT,
OFFICE OF THE SUPERINTENDING ENGINEER, NH( CENTRAL )
CIRCLE, VYTTILA, COCHIN-, PIN - 682019
OTHER PRESENT:
SPL.GP - K.V.MANOJKUMAR
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 23.08.2023,
THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
W.P.(C). No.17363 of 2023
:2:
VIJU ABRAHAM, J.
-- -- -- -- -- -- -- -- -- -- -- -- --
W.P.(C). No.17363 of 2023
-- -- -- -- -- -- -- -- -- -- -- -- --
Dated this the 23rd day of August, 2023
JUDGMENT
The above writ petition is filed challenging Ext.P49 order
whereby the petitioner was blacklisted, barring the petitioner
from quoting for any work for a period of 5 years.
The brief facts necessary for the disposal of the above writ
petition are as follows:
2. The petitioner is a company incorporated under the
Companies Act, 1956 and it is a leading engineering and general
contracting company, offering building solutions for a broad
range of construction and engineering projects since 1992. The
petitioner submits that it has completed over 100 projects
throughout India, out of which 45 projects are in Kerala, of which
23 are construction of bridges. The Petitioner Company has also
received quite a lot of appreciation for its endeavors in the field of
construction and was also awarded for excellence in construction.
It is submitted that the Roads and Bridges Development W.P.(C). No.17363 of 2023
Corporation (hereinafter referred to as RBDCK) invited tenders
for the construction of a flyover in N.H.66 at Palarivattom,
Ernakulam. The petitioner was awarded the said work being the
lowest tenderer and executed Ext.P3 agreement dated
04.03.2014. The site was handed over on 01.06.2014 and the
work has to be completed within 24 months from the date of
agreement. The petitioner submits that the structural work except
the wearing coat was completed by June 2016 before the onset of
the monsoon. The petitioner submits that since the inauguration
of the flyover was scheduled to be held on 12.10.2016, the
petitioner was forced to complete the wearing coats in monsoon
period itself. Therefore, the petitioner completed the work by
20.09.2016. In view of the urgency, bituminous wearing coats
were done in wet conditions and therefore the wearing coat
compaction by maintaining temperature was not possible and this
resulted in developing potholes and the bituminous layer got
damaged progressively due to the increase in traffic. Due to the
development of potholes, water stagnation and dust collection
occurred on the expansion joints, thereby choking the movement W.P.(C). No.17363 of 2023
of deck continuity expansion joints. As deck continuity joints were
not functioning, additional stress developed in girders and pier
caps. The petitioner also submits that there was an error in the
approved drawings in the placement of bearings in 2 spans, P9-
P10, P18-AP2. Since the above said defects happened due to the
formation of the potholes and stagnation of water could be
remedied forthwith, the matter was reported to the structural
consultant, M/s. Nagesh Consultancy for their expert advice. The
consultant inspected the site along with the representatives of
RBDCK and KITCO and forwarded their drawings for the
rectification of joints. A review meeting was held by RBDCK on
16.11.2016 and as per Ext.P5 minutes, it was decided to take
corrective steps to rectify the expansion joints between two strip
seal expansion joints. As per the decision in the meeting held on
16-11-2016, the balance drain works were started on 18.11.2016.
Based on the views of the consultant, Exts.P6 and P7 requests
were made by the petitioner, but the same was not considered
and permission for rehabilitation as suggested in Exts. P6 and P7
at its own costs was never heeded to, but the traffic continued to W.P.(C). No.17363 of 2023
ply. Thereupon, Ext.P8 communication was also sent by the
petitioner. In Ext.P8, it was also intimated that purchase orders
were placed with M/s. Sanfield India Pvt. Ltd. for the supply of
the bearings and the materials were fabricated and ready for
inspection. Later on, the POT bearing and strip seal expansion
joints required for replacement at deck continuity joints were
tested by the manufacturers on 10.10.2017 and 11.10.2017 at the
factory of M/s. Sanfield India Pvt. Ltd., Bhopal in the presence of
the representatives of the Government and RBDCK. It was also
informed that the deck continuity joint is not withstanding the
traffic and it was decided to introduce strip seal expansion joint.
By Ext.P9 the test result of M/s. Sanfield and the mobilization of
specialized agency were also brought to the notice of RBDCK and
KITCO. As requested by the petitioner, Dr. Aravindan, retired
professor of IIT and Head of M/s.Sree Giri Consultants along with
his team inspected the flyover on 07.11.2016 and 29.10.2017 and
prepared a detailed structural design check and submitted
Ext.P11 report before the RBDCK. Even though as per Clause
20.2 of the agreement dated 04.03.2014, it is the responsibility of W.P.(C). No.17363 of 2023
the petitioner to rectify any defects during the defect liability
period at his own cost to the satisfaction of Engineer/KITCO, in
spite of intimation to RBDCK through several communications
regarding the nature of defects and the methodology to rectify the
same, RBDCK never took any action or any steps so as to enable
the petitioner to execute such works at its expense. On the basis
of the same, it is contended by the petitioner that RBDCK has
committed breach of contract and that the petitioner is never
liable to rectify or compensate with regard to any defects which
are the result of blatant violation of provisions of the agreement
executed with RBDCK. Without considering the various proposals
submitted by the petitioner for rehabilitation of the flyover which
was approved by the Engineer, the RBDCK engaged IIT Madras to
carry out the assessment of the condition of the flyover and to
suggest the rehabilitation measures. The IIT Madras after
conducting a scientific study approved the methodology for
bearing replacement for span P18-AP2 submitted by KITCO. By
Ext.P12 letter dated 19.03.2019, IIT Madras informed the RBDCK
about the corrected methodology submitted by the Engineer W.P.(C). No.17363 of 2023
approved by IIT Madras. Thereupon by letter dated 28.03.2019,
RBDCK directed the petitioner to conduct the repairs as per the
methodology suggested by KITCO and approved by IIT Madras in
its letter dated 19.03.2019. The petitioner submits that the
methodology approved by IIT Madras was the same in essence as
the methodology submitted by the petitioner and the inordinate
delay in engaging IIT Madras and approving the methodology was
not attributable to the petitioner. The petitioner contends that
even the report of IIT Madras only recommended for
rehabilitation of the flyover since the flyover was not in such
distress so as to be demolished. RBDCK, despite the long requests
of the petitioner for traffic closure, finally by Ext.P14 letter
intimated the petitioner for the traffic closure with effect from
01.05.2019. The petitioner completed the repairs as instructed by
the IIT as suggested in Ext.P13 under the supervision of IIT and
RBDCK and the expert panel of three Chief Engineers deputed by
the State. The petitioner expended Rs.2.63 Crores for the repair
works. All the repair works as specified by RBDCK were
commenced on 01.05.2019 and completed on 02.06.2019 under W.P.(C). No.17363 of 2023
the supervision of the representatives of the Engineer and Dr. P.
Alagasundaramoorthy of IIT, Madras except for the expansion
joint of the span P18-AP2, since the work was stopped by RBDCK.
The petitioner by Ext.P15 letter informed RBDCK and KITCO that
the site was ready for the replacement of the final bearing in span
P18-AP2 and sought permission for the completion of all the
rectification works by 05.08.2019. The petitioner, again by
Ext.P16 dated 18.09.2019 intimated RBDCK for completion of the
balance work of the expansion joint at span P18-AP2, but no reply
or response has been evoked to the said letters. Petitioner
submits that it appears that being dissatisfied with the inspection
report and remedial measures of IIT Madras, the Government of
Kerala sought clarification from Dr. E Sreedharan, the Principal
Advisor of Delhi Metro Rail Corporation (DMRC) and that Dr. E
Sreedharan without conducting much scientific study and even
without conducting any physical verification submitted reports
dated 03.07.2019, 14.09.2019 and 19.09.2019 contrary to the
report of IIT Madras. Dr. E. Sreedharan, submitted a
recommendation dated 03.07.2019 before the Government of W.P.(C). No.17363 of 2023
Kerala for the rehabilitation of the bridge by dismantling 17 RCC
spans and to replace with PSC girders. Thereby Government of
Kerala constituted a committee to examine the reports of IIT
Madras and Dr. E.Sreedharan and the committee so constituted,
without conducting any scientific study, submitted a report dated
04.10.2019. Without reference to the contractual obligations in
pursuance of the agreement dated 04.03.2014, and especially
Clause 49.2(b), Clause 49.4 and Clause 50.1 of Part I of the
General Conditions of the contract, the Government of Kerala as
per Ext.P17 order dated 25.10.2019 accepted the
recommendation of the technical committee, appointed by the
Government to resolve the dispute in the conflicting reports of IIT
Madras and Dr. E Sreedharan, and further accepted the offer of
DMRC to take over the bridge for rehabilitation and further
directed the RBDCK to realize the loss sustained from the
petitioner in the light of the reports of IIT Madras, Dr.
E.Sreedharan and FIR in vigilance case No.1 of 2019 of the Court
of Vigilance and Anti-Corruption Bureau, Muvattupuzha. The
petitioner has a specific case that if at all any rehabilitation of the W.P.(C). No.17363 of 2023
flyover is required, necessarily RBDCK has to invoke Clause
49.2(b) of Part I of the General Conditions of Contract. As a
matter of fact, after obtaining the report of the Technical
Committee, the Government of Kerala has accepted the offer of
DMRC for rehabilitation of the Flyover, which is in total violation
of the above-stated clause in the agreement executed between the
petitioner and RBDCK. The petitioner challenged Ext.P17 order
by filing W.P.(c) No. 30487 of 2019 and this Court was pleased to
stay all coercive action including the attachment of the bank
account of the petitioner. The petitioner also filed another writ
petition, WP(C) No.26030 of 2019 seeking a direction to conduct
a load test on the bridge. The above writ petition came up for
hearing along with other writ petitions on 21.11.2019 and this
Court as per Ext.P19 common order directed the Government to
conduct load test of the Palarivattom Flyover at the expense of
the petitioner. Aggrieved by Ext.P19, the Government approached
the Apex Court in SLP(Civil) Nos.3008-3015 of 2020. The Apex
Court as per Ext.P20 judgment set aside Ext.P19 common order
passed by this Court directing to conduct load test. Pursuant to W.P.(C). No.17363 of 2023
Ext.P20 judgment by the Apex Court, the Government of Kerala
issued Ext.P21 Order granting administrative sanction for the
rehabilitation of the Palarivattom Flyover through M/s Delhi
Metro Rail Corporation (DMRC) with a further direction to realise
the cost of the rehabilitation from the petitioner. The specific
contention of the petitioner is that the Government has no right
or authority to engage DMRC to do the rehabilitation work,
especially when the contract between the petitioner and RBDCK
was subsisting. Petitioner submits that RBDCK committed several
instances of breach of the agreement and has shown reluctance in
permitting the petitioner to carry out the rectification works.
These aspects were pointed out to RBDCK by the petitioner as per
Ext.P22 letter. Since RBDCK has violated the terms and
conditions envisaged in the agreement, the petitioner has filed a
suit as C.S.No.80 of 2021 before the Commercial Court,
Ernakulam seeking recovery of the amount due to the petitioner
and for a declaration that the Government orders dated
25.10.2019 and 07.10.2020 (Exts.P18 to P21) are illegal, ab initio
void and non-est in law. The petitioner further submits that the W.P.(C). No.17363 of 2023
RBDCK has also instituted a suit as C.S No. 240 of 2022 before
the Commercial Court, Ernakulam for the realization of a sum of
Rs.24,52,22,498/- being the alleged loss incurred in the
demolition and re-construction of the Flyover. Petitioner submits
that in connection with another work tendered by the petitioner,
which was a joint venture, the Government decided to exclude the
L1 bid of the Joint Venture of the petitioner alleging irregularities
and registration of vigilance case in connection with the
construction of the Palarivattom Flyover. Thereupon the
petitioner has approached this Court by filing W.P.(C) No. 31556
of 2019, which was disposed of as per Ext.P31, wherein it was
held that the blacklisting proceedings shall be initiated and
completed within a time limit and if it is found that the petitioner
is liable to be blacklisted, work involved in the said writ petition
shall be re-tendered and if it is found in the proceedings that the
petitioner is not liable to be blacklisted, the work shall be
awarded to the Joint Venture of the petitioner. Despite the said
direction in Ext.P31 judgment, no steps were taken to blacklist
the petitioner and the work was awarded to the Joint Venture of W.P.(C). No.17363 of 2023
the petitioner as is evident from Ext.P32. The petitioner further
submits that subsequently, works have been awarded to the
petitioner, as is evident from Exts.P33 to P40. While so, the 3 rd
respondent issued Ext.P42 notice directing the petitioner to
appear before the 3rd respondent to attend a hearing regarding
the initiation of the process of blacklisting the petitioner in
connection with the irregularities found in the construction of
Palarivattom Flyover. Since Ext.P42 did not state the particular
grounds for the initiation of black listing proceedings, the
petitioner approached this Court in W.P(C) No.5722 of 2023
seeking to quash Ext.P42 and this Court was pleased to dispose of
the writ petition as per Ext.P44 judgment directing the
Superintending Engineer, PWD to provide the details with respect
to the blacklisting procedure adopted by the respondents, so as to
enable the petitioner to file a suitable reply. Pursuant to Ext.P44,
the 3rd respondent issued Ext.P45 notice stating the reasons for
initiating blacklisting proceedings against the petitioner and
giving 3 weeks' time to prefer an appropriate reply to the said
notice. Thereupon, the petitioner submitted Ext.P46 reply to the W.P.(C). No.17363 of 2023
same. Petitioner submits that Ext.P45 notice was issued only to
harass the petitioner and the same is ill-motivated. The 3 rd
respondent has no authority to issue the same when the subject
matter of the dispute is pending consideration before the
competent Civil Court. Ext.P45 is issued only as an eyewash and
to cause hardship to the petitioner. Without considering any of
the contentions in a proper manner, by Ext.P49 order, it was
decided to blacklist the petitioner in connection with the
irregularities in the construction of the Palarivattom Flyover and
the petitioner was barred from quoting for another work for a
period of five years and the "A" class license issued to the
petitioner was also cancelled. The petitioner submits that the
Government acted arbitrarily, and capriciously against the
interest of the public by engaging to demolish the bridge without
any supporting materials. The materials already available on
record eloquently speak of rehabilitation of the bridge and the
decision to demolish flyover is malafide and with sinister motives.
Exts. P45 and P49 are also another move which is politically
motivated and leaving the petitioner a scapegoat to it. The W.P.(C). No.17363 of 2023
petitioner has undertaken various works in the State of Kerala
and the same are in progress and any coercive action by virtue of
Ext.P45, which itself is without any authority, would cause great
hardship and financial loss to the petitioner. Initiation of action as
is evident from Ext.P49, while civil suits in this regard are
pending consideration before the competent court is an arbitrary
action. Ext.49 is a non-speaking order issued without any
application of mind and was passed on compulsion since RBDCK
apparently recommended the blacklisting of the petitioner. There
was no subjective satisfaction on the part of the 3 rd respondent for
blacklisting and the 3rd respondent has just followed the
recommendations of the RBDCK to blacklist the petitioner. None
of the contentions taken by the petitioner in Ext.P46 reply was
taken into consideration while issuing Ext.P49. The 3 rd respondent
did not take into consideration that a substantial portion of the
repair work was carried out by the petitioner and that the balance
work in respect of one expansion work was abruptly stopped by
the RBDCK and therefore the petitioner cannot be held
responsible for the same. The petitioner further submits that in W.P.(C). No.17363 of 2023
Ext.P23 counter affidavit, the consultant KITCO had disowned the
report of Dr. E. Sreedharan and also the decision to forgo the load
test and to demolish the flyover. The petitioner has executed all
the works undertaken so far to the full satisfaction of the
employer and has earned goodwill and reputation throughout the
country. Exhibit P49 is ill-motivated solely to tarnish the
reputation of the petitioner for the illegal gains of the
respondents. In support of the contentions, the petitioner relies
on the judgments in Commissioner of Police, Bombay v.
Gordhandas Bhanji (1952 KHC 291), Mohinder Singh Gill
and Another v. The Chief Election Commissioner, New
Delhi and others (1978 KHC 478), Chairman and Managing
Director, United Commercial Bank and Ors. v. P. C. Kakkar
(2003 KHC 971), U. O. I. and others v. Jai Prakash Singh
and another (2007 KHC 4322), Kulja Industries
Limited(M/s) v. Chief General Manager, W. T. Proj.BSNL
and others (2013 KHC 4798), Tulsi Narayanan Garg v. M. P.
Road Development Authority (2019 SCC online SC 1158),
Ramsons Garments Finishing Equipments Pvt. Ltd(M/s.), W.P.(C). No.17363 of 2023
Bangalore v. Government of India, Ministry of Railways
(2022 KHC 5175) and the decision in Abcon
Engineering(M/s) v. Superintendent of Engineer [2023 (4)
KHC 501].
3. A detailed counter affidavit has been filed on behalf of the
3rd respondent wherein it is stated that Ext.P49 order has been
issued by the licencing authority after properly assessing the
allegations raised by the implementing authority RBDCK and
after hearing the arguments of the petitioner against the
blacklisting as per the directions of this Court and thereupon
arrived at a decision to proceed with the blacklisting and
cancellation of the licence issued by the licence issuing authority.
Ext.P49 was issued considering the irregularities in the
construction of the Palarivattom Flyover and the same was
mentioned in the order itself. The order issued was not to
damage the reputation and goodwill earned by the contractor in
accepting other projects but only as per the terms of prevailing
rules and conditions of the contract. This blacklisting and licence
cancellation need not affect other ongoing works of the petitioner W.P.(C). No.17363 of 2023
and they can continue with the ongoing works to full satisfaction
of the respective agreement authorities. Irregularities in
connection with the work were noticed in the year 2019. The
implementing agency of the work ie., RBDCK reported the
allegations and intimated the recommendation to blacklist the
contractor to the Government on 06.11.2020. The subject work
was awarded under the SPEEID project of the Government of
Kerala and aided by the fund of KRFB. There were defects
noticed in the construction undertaken by the petitioner, but the
petitioner did not turn up to rectify the defects of the project in
time. The vigilance enquiry report submitted to the Government
concluded that the flyover is in a dangerous condition. Even
though rectification works under the supervision of IIT Madras
were done, it was found that there is every chance that the
flyover will become a threat to the life and property of the public
at any time. Therefore, the Government had no other option but
to engage other competent agency to rectify the defects and
recover the cost of rectification from the defaulted contractor,
which is specifically mandated as per the general condition of the W.P.(C). No.17363 of 2023
contract. The Vigilance and Anti-Corruption Bureau has also
reported as per Ext.R3(c) report that there are serious
irregularities on the part of the contractor in the construction of
the project. The Government engaged a technical evaluation
Committee to assess the proposals of rehabilitation submitted by
the IIT Madras and DMRC and the proposal submitted by the
DMRC ensured a guarantee period of 100 years to the bridge,
which was not present in the proposal submitted by IIT Madras.
Thereupon, the Government approved the recommendation of the
technical committee and opted for the proposal of the DMRC. As
per the general conditions of the contract, if the contractor does
not satisfactorily rectify the defects, the executing agency can
depute any other agency and recover the cost of rectification
from the defaulting contractor. The contractor has filed W.P.
(C)No.30487/2019 and the interim order granted in the said case
prevented the Government from taking any coercive steps against
the contractor including blacklisting. Due to the pendency of the
case, Government could not go ahead with the blacklisting
procedure. Later as per the judgment dated 04.02.2022, this W.P.(C). No.17363 of 2023
Court dismissed the said writ petition as withdrawn with liberty
to the petitioner to raise the contentions before the civil court.
Thereupon, proceedings were initiated to blacklist and to cancel
the license of the contractor. Since blacklisting proceedings and
the coercive steps, to be taken against the petitioner were stayed
by this Court, further works tendered by the petitioner were
considered on merits and works were awarded to them. Ext.P49
order has been issued after complying with all the procedures
mandated and following the principle of natural justice. The
petitioner was issued with notice and given sufficient time for
submitting his reply and after considering the reply submitted by
the petitioner, Ext.P49 order has been issued and the contract
licence was cancelled on account of poor workmanship as
reported by RBDCK. Petitioner never turned up to rectify the
damages to the Palarivattom Flyover to the satisfaction of the
agreement authority. The contention of the petitioner that
though they were ready to rectify the defects, RBDCK never
acceded to any of the proposals and committed inordinate delay
is not true to the facts. It is the case of RBDCK that despite notice W.P.(C). No.17363 of 2023
and report submitted by IIT Madras regarding the rectification
works, which is notified to the petitioner, rectification works were
not attended by him, but at the same time under the pretext of
the objection to the report submitted by IIT Madras, petitioner
has not complied with their contractual obligations. It is clear
from the report submitted by the RBDCK and also Ext.R3(c)
report submitted by the Vigilance and Anti Corruption Bureau,
that only by reconstruction of the bridge to the extent required, it
cannot be put to use. Further contention of the petitioner that
clause 2116.2 of the PWD manual does not contemplate
blacklisting of the petitioner/contractor in the above-said
circumstances of the case, cannot be accepted since pursuant to
the directions issued by this Court in W.P.(C) No.21597/2017,
"poor workmanship" also has been incorporated in the Manual as
per Ext.R3(d) Government order, as a reason for blacklisting the
contractors and on the basis of the said contentions raised in the
counter affidavit sought for dismissal of the writ petition.
4. Heard the rival contentions on both sides.
5. The thrust of the contentions raised by the petitioner W.P.(C). No.17363 of 2023
challenging Ext.P49 is that the defects, if any noticed by the
petitioner, were intimated to the RBDCK as per Exts.P6 and P7
and there was no response from them in this regard and that
even the report of IIT Madras only recommended for
rehabilitation of the flyover since the flyover was not in such
distress so as to be demolished. It could be seen that after
obtaining the inspection report and remedial measures suggested
by IIT Madras, the Government of Kerala sought for a
clarification from Dr. E. Sreedharan, the Principal Advisor of
DMRC and he has submitted a report dated 03.07.2019 before
the Government for rehabilitation of the bridge by dismantling 17
RCC spans and to replace with PSC girders. As there were two
conflicting reports, the Government thought it fit to constitute a
committee to examine the reports of IIT Madras and Dr. E.
Sreedharan and a report to that effect was submitted on
04.10.2019. The Government after verifying both the reports,
issued Ext.P17 order, wherein the issues raised in this writ
petition have been elaborately considered. The relevant portion
of the said report is extracted below:
W.P.(C). No.17363 of 2023
"IIT Madras explored the possibility of repairing and strengthening the precast RC girders using (i) Concrete jacketing. (ii) Steel jacketing, (iii) External flexural strengthening using CFRP composite pultruded sheets, (iv) Strengthening of girders by near surface mounting (NSM) technique using CFRP composite pultruded sheets, (v) Strengthening of girders by NSM technique using pultruded CFRP composite rebars and (vi) Shear strengthening using carbon fibre fabric composites. The possibility of repairing and strengthening the Piers using (1) Carbon fibre fabric composites and (2) and Concrete jacketing are also explored.
Considering the durability, cost and time to repair and strengthen the precast RC girders the following repair and strengthening scheme is recommended by IIT Madras:
a) Repairing of cracks in precast RC girders and pier caps by injecting low viscous resin.
b) Flexural strengthening of precast RC girders by concrete jacketing.
W.P.(C). No.17363 of 2023
c) Shear strengthening of precast RC girders using carbon fiber fabric composites.
d) Cross stiffening of precast RC girders using standard steel sections and
e) Repairing of cracks on RC walls in the abutments The total estimated cost for the above mentioned scheme is Rs. 7.31 crores, IIT Madras will issue the execution drawings as per the requirement. Scaffolding, water supply and power supply have to be provided as per the site conditions by RBDCK/RDS.
After repair and strengthening a span and two pier caps, a load test to be conducted and the measured deflection can be checked with the allowable limit to ensure the safety of the bridge. Strict quality control to be ensured during repair and strengthening of the Flyover. All safety procedures for manpower and machines to be ensured by the Applicators"
4.On the basis of press statement made by Dr.E,Sreedharan on the issue, Government have discussed the matter with him. On the basis of discussion he inspected the bridge W.P.(C). No.17363 of 2023
site and examined the IT report and submitted a report to Government as read 5 above. In the report he noted the following points "The cost of repairs appears to be underestimated. For example, repairing the cracks by resin injection is shown to cost only Rs 28.00 lakhs. This would certainly cost much more as 97 out of 102 girders have developed multiple cracks. Drilling for too many holes for resin injection may further weaken the concrete whose strength is already low and uncertain Shear strengthening of RC girders using carbon fibre wrapping may not bring in the expected benefit as such wrapping does not confine the concrete. If the parent material strength is less than the permitted limit, the wrapping may become a failure. In this case, carbon fibre wrapping alone may not give the required shear strength. The technology of carbon fibre wrapping is new to the country and its life expectancy is also uncertain. They have not mentioned anything about the protection needed for the carbon fibre wrapping since the resins are not stable W.P.(C). No.17363 of 2023
against ultra violet exposure.
To make up the deficiency in surface reinforcement, nothing is mentioned in the report.
Only the bottom flanges of the RC girders are strengthened by 100mm micro concrete jacketing. The side concrete has no reinforcement shown. This may spall off after some time due to vibration.
Nearly 16 tonne weight is adding in each span for retrofitting scheme. This extra weight (approx. 3 tonne weight in one single girder) will create additional bending moment and shear force in existing distressed girders. Any increase in dead load is not desirable as the four piles in foundation are at their limits.
The concrete jacketing of pier heads has to be more robust to increase their structural strength.
Since the concrete used in the bridge is generally found weak, the stem of the piers has also to be jacketed by RCC. This has not been indicated nor its cost accounted for IIT scheme has not eliminated the expansion joints over the pier locations. The dynamic W.P.(C). No.17363 of 2023
impact at these joints will therefore continue Dr.Sreedharan has also pointed out that IIT has not indicated what would be the residual life of the bridge after repairs.
Pointing out the above discrepancies
noticed in the IIT report, Dr.E.Sreedharan
suggested to dismantle all the RCC girder spans and replace with pre stressed girders for increased life expectancy of the bridge as indicated in his letter read as 4th above
5. In the light of the above conflicting opinion government decided to constitute a technical committee to examine the reports submitted by IIT Madras and Dr E Sreedharan,and to submit a report to Government. As per government orders read as 2nd above Government have constituted a technical expert committee for this purpose Vide report read as 7th above Technical Expert committee furnished the following recommendations "The tests carried out by IIT Chennai are as per IS codes and IRC recommendations.
IIT Chennai being a premier and reputed institution, their findings can he accepted and relied on. However, a load test as W.P.(C). No.17363 of 2023
specified in IRC 112:2011 has not been proposed by IIT Chennai. The reasons are not mentioned in their report. The Committee feels that since crack width in certain girders have exceeded the allowable limits which is one of the compliance criteria for load test, IIT might have decided that there is no point in doing a load test before strengthening. However, IIT has recommended load test after strengthening the flyover. IIT has suggested its scheme for strengthening the flyover, which again is as per IRC recommendations. But, IIT has not mentioned the service life of the flyover after strengthening. IRC also does not recommend service life of any structure after doing the strengthening works proposed by IIT.
As mentioned by Dr. E.Sreedharan a new construction with proper design, with quality execution of the work with quality materials and strict technical supervision can expect a service life of 100 years.
Construction cost of the proposal of demolishing and replacing of superstructure as proposed by Dr. E.Sreedharan will cost (18.71 crores), more than double the cost W.P.(C). No.17363 of 2023
estimated for the strengthening scheme proposed by IIT (7.31 crores). The required completion time for both cases is almost the same. Normally rehabilitation/ strengthening are required for old as well as distressed bridges having service life of 40 years or more and also strengthening works are normally required for limited members or locations of a flyover/bridge. In the case of Palarivattom flyover as per the findings of IIT Chennai, 97 RCC girders out of 102 girders requires strengthening which is an extensive strengthening work for superstructure.
Based on the all the above factors, Committee is of the opinion that considering the service life assured by Dr. E. Sreedharan for 100 years, it is better to accept the proposal by him."
6. Government have examined the whole matter in detail and have decided to accept the recommendations of the Technical Committee and to proceed accordingly.
It is also decided to accept the letter of offer made by Delhi Metro Rail Corporation to take over the bridge for rehabilitation as per letter read as 6th above. DMRC shall W.P.(C). No.17363 of 2023
submit detailed item wise estimate for approval of Government. On the basis of the detailed estimate, Finance Department shall allot funds in the appropriate Head of Account for the purpose. RBDCK will hand over the bridge site to DMRC free of all encumbrances.
7. RBDCK shall realize the loss sustained to the Government from the contractor in the light of the report of IIT Madras,report of Dr.E Sreedharan and the FIR filed in case No. 1/2019 of Moovattupuzha Vigilance Court and as per the relevant provisions of the agreement. RBDCK shall also initiate action against the contractor for the lapses as per PWD Manual
A perusal of Ext.P17 would reveal that Dr. E. Sreedharan's report
in this regard was on the basis of an inspection conducted by him
at the bridge site and not as contended by the petitioner that the
said report has been submitted without any study or even an
inspection. As per the report of IIT Madras, 97 out of 102 girders
have developed multiple cracks and drilling too many holes for
resin injection may further weaken the concrete whose strength W.P.(C). No.17363 of 2023
is already low and uncertain and thereupon Dr. E. Sreedharan
suggested dismantling all RCC girder spans and to replace with
pre-stressed girders for increased life expectancy of the bridge.
A perusal of Ext.P17 would also reveal that the technical
committee was constituted in the light of the conflicting opinion
by the IIT, Madras and Dr. E. Sreedharan. The technical
committee has found that even though IIT Madras has
recommended certain rectification methods, they have not
suggested for a load test and the committee after examining the
same, opined that since crack width in certain girders has
exceeded the allowable limits which is one of the compliance
criteria for load test, IIT might have decided that there is no point
in doing a load test before strengthening and recommended for a
load test after the strengthening is over. The technical
committee appointed by the Government found that the IIT has
not mentioned the service life of the flyover after strengthening,
whereas in Dr. E.Sreedharan's report, new construction with
proper design with quality execution of the work with quality
materials and strict technical supervision can expect a service life W.P.(C). No.17363 of 2023
of 100 years. The committee further examined that the required
completion time for both rectification work and the demolition
and replacing the superstructure as proposed by Dr. E.
Sreedharan takes almost the very same time limit. The
committee after examining both reports came to the opinion that
normally rehabilitation/strengthening is required for old as well
as distressed bridges having service life of 40 years or more and
also strengthening works are normally required for limited
members or locations of a flyover/bridge and in the case of
Palarivattom flyover as per the findings of IIT Madras, 97 RCC
girders out of 102 girders requires strengthening which is an
extensive strengthening work for a superstructure. Based on all
the above factors, Committee opined that considering the service
life assured by Dr. E. Sreedharan for 100 years, it is better to
accept the proposal by him and the said findings and
recommendations of the technical committee were accepted by
the Government as per Ext.P17. In Ext.P17, there was a further
direction that RBDCK shall initiate action against the contractor
for the lapses as per the PWD manual. A perusal of Ext.P17 W.P.(C). No.17363 of 2023
would reveal that Dr. E. Sreedharan has submitted the report
after conducting a thorough study and after conducting a site
inspection. One crucial aspect is to be noted that even going by
the report of the IIT Madras, 97 RCC girders out of 102 girders
require strengthening. The serious damage affecting to almost
97 RCC girders out of 102 girders, is a very serious aspect to be
taken note of, especially in the case of a bridge the construction
of which was completed only during 2016 and Ext.P17 report is in
2019, almost after a period of three years. The Government
while issuing Ext.P17 did not automatically accept the report of
Dr. E. Sreedharan. It is also to be noted that Ext.P17 was
challenged by the petitioner by filing W.P.(C) No.30487/2019.
Though initially there was a stay of coercive action including
attachment of the bank account of the petitioner, the said writ
petition was disposed of as per judgment dated 04.02.2022,
wherein the petitioner sought dismissal of the writ petition as
withdrawn with liberty to the petitioner to raise all legal and
factual contentions available, before the civil court. Though a
suit has been filed by the petitioner as C.S. No.80/2021 wherein a W.P.(C). No.17363 of 2023
challenge is also made against Ext.P17 and Ext P21 Government
Orders, no interim order has been granted. In view of the above,
the decision of the Government as per Ext.P17 order whereby the
Government has decided to accept the report of Dr. E.
Sreedharan and to take coercive action against the petitioner as
per the PWD manual is after conducting a proper study and in
accordance with the law.
6. Another contention raised by the petitioner is that the
petitioner has been entrusted with the other contract works even
after the defects were noticed by the Government in respect of
the Palarivattom flyover. The specific contention of the learned
Government Pleader in the counter affidavit is that after issuance
of Ext.P17, whereby direction was issued to RBDCK to initiate
action against the contractor/petitioner for lapse as per PWD
manual, further action was stayed as per Ext.P18 interim order
dated 12.11.2019 in W.P.(C) No.30487/2019 and the said writ
petition was disposed of only as per order dated 04.02.2022 and
it is only for the reason that the impugned order has been stayed
by this Court, the petitioner was permitted to undertake another W.P.(C). No.17363 of 2023
works tendered by him. In view of the same, the said contention
raised by the petitioner is only to be rejected.
7. Further contention raised by the petitioner is that if any
defect has been noticed as per the general conditions of the
contract, the petitioner ought to have been entrusted the duty of
remedying the defects and since the same has been entrusted to
the third agency, the petitioner cannot be held liable for any loss
sustained. The learned Government Pleader on the strength of
the counter affidavit would submit that it is informed by the
RBDCK that despite notice and reports submitted by IIT Madras,
regarding the rectification work notified to the petitioner, the
rectification works were not attempted by him, but at the same
time under the pretext of an objection to the report submitted by
IIT Madras, petitioner has not complied with the contractual
obligations and it is in the said circumstance that further
rectification work was entrusted to a third party, which is well
within the power of the Government and the Departmental
authorities to do so. In view of the same, the contention taken by
the petitioner in this regard is only to be repelled. W.P.(C). No.17363 of 2023
8. Yet another contention raised by the petitioner is that
while issuing Ext.P49, there is total non-application of mind and
Ext.P45 show cause notice was issued only based on the decision
of RBDCK to blacklist the petitioner. A perusal of Ext.P45 would
reveal that in the 85th meeting held on 14.10.2020 by the Board of
Directors of RBDCK, the Board decided to furnish certain
recommendations to the Government, which is extracted below.
Blacklisting of Contractor The contractor M/s RDS Projects Ltd is to be blacklisted on grounds of poor workmanship and bar them from taking part in the future tenders of this company and request that Government may issue directions to the concerned license issuing departments /authorities for actions as per PWD Manual to cancel the license of the firm
2. Realisation of Rehabilitation Cost RBDCK intends to recover the costs from the Contractor based on
a) Cost estimated for the strengthening scheme proposed by IIT
b) Construction cost of the proposal of W.P.(C). No.17363 of 2023
demolishing and replacing of superstructure
c) Loss sustained to Government as per the FIR filed in case No.1/2019 of Muvattupuzha Vigilance Court.
It is also pertinent to note that in Ext.P17 the Government while
entrusting rehabilitation works to DMRC has also directed the
RBDCK to initiate action against the contractor for the lapse as
per the PWD Manual and it is based on the same that the RBDCK
has decided to take steps to blacklist the contractor for poor
workmanship. It is pursuant to the said recommendation that the
details of the allegation against the petitioner was submitted by
the 3rd respondent as per Ext.P45, which contains all the details
of the allegations against the petitioner. It is seen that a detailed
reply was also submitted by the petitioner as Ext.P46 and only
after considering the same that Ext.P49 decision was taken,
which is impugned in this writ petition. I am unable to accept the
argument of the learned Senior Counsel appearing for the
petitioner that it is solely based on the decision of the RBDCK
that further proceedings were initiated to blacklist the petitioner.
It is true that RBDCK has recommended for blacklisting the W.P.(C). No.17363 of 2023
contractor but it is for the 3rd respondent who is the licencing
authority to take action for blacklisting and for cancellation of
PWD contractor's licence. Thereafter, it could be seen that 3 rd
respondent has issued show cause notice and details of
allegations against the petitioner and thereafter objections were
called for and it is only considering the objections filed by the
petitioner that Ext.P49 order was issued. Only for the reason
that one of the authorities has recommended for taking action
against the petitioner will not by itself invalidate the proceedings
on the ground that the same was initiated as per the dictation of
another authority and therefore there is total non application of
the mind. As stated above, Ext P49 order was issued by the
competent authority, the 3rd respondent, after complying with all
the procedural formalities. The learned Government Pleader
relies on the judgment in State of Odisha and others v. Panda
Infra Project Ltd [(2022) 4 SCC 393]. Paragraph 17 of the
said judgment reads as follows:
17. Merely because the show-cause notice was issued after the inquiry committee report was considered and thereafter the W.P.(C). No.17363 of 2023
State Government took the decision to initiate proceedings for blacklisting, that by itself cannot be said that the order of blacklisting was pre-determined as observed by the High Court. The communication dated 10-10-2017 by the State Government to the Chief Engineer can be said to be a proposed decision to initiate the proceedings for blacklisting. In the communication dated 10-10-2017, it has been specifically mentioned that the action be taken for blacklisting after following the procedure as per the OPWD Code.
In view of the same, I am not inclined to accept the said
contention of the petitioner that there is no application of mind
before issuance of Ext.P49 and that the 3 rd respondent acted
solely based on the report/recommendation of the RBDCK.
8. Further contention raised by the petitioner is that this is a
disputed question of fact and that civil suits are pending, one filed
by the petitioner and the other by the RBDCK and therefore,
while the suits are pending consideration, the decision taken by
the Government to blacklist the petitioner as per Ext.P49 is W.P.(C). No.17363 of 2023
arbitrary and unjust. In support of the contention, the petitioner
relies on the judgment in Tulsi Narayan Garg's case cited
(Supra). That was a case where the question decided was as to
whether the liquidated damages assessed by the officer could be
recovered when the matter is pending adjudication before the
Arbitral Tribunal and the court held that since once the dispute is
pending adjudication before the Arbitral Tribunal, the respondent
was not justified in raising demand on termination of the
contract, claiming liquidated damages and the respondent cannot
become an arbiter of his own cause and unless the dispute is
settled by a procedure prescribed under the law, the respondent
would not be held to be justified in initiating revenue recovery
proceedings invoking the procedure under the Land Revenue Act.
I am afraid the said judgment cannot apply in the facts and
circumstances of the present case because that was a case where
the court was considering whether any revenue recovery
proceedings could be initiated based on the quantification of
liquidated damages assessed by the officer while the said dispute
was pending consideration before the Arbitral Tribunal. The W.P.(C). No.17363 of 2023
present case is one which where the petitioner was blacklisted
after complying with due procedures as prescribed by law and
therefore, the said judgment is not applicable in the facts and
circumstances of the present case.
9. The petitioner has taken a further contention that Ext.P49
is not a reasoned order and there is no subjective satisfaction on
the part of the 3rd respondent for blacklisting the petitioner.
Petitioner further contended that the punishment imposed is
harsh and therefore, the same is liable to be interfered with. In
support of his contention, the petitioner relies on the judgment in
Gordhandas Bhanji & Mohinder Singh Gill's cases cited
(Supra) which held that reasons should be stated in the order
itself and the same cannot be substituted by way of averments in
the counter affidavit. The petitioner also relies on the judgment
in Chairman and Managing Director, United Commercial
Bank and Others' case cited (Supra) to contend for the position
that if the court feels that the punishment is shockingly
disproportionate, the same is liable to be interfered with. The
petitioner further submits on the basis of the decision in Kulja W.P.(C). No.17363 of 2023
Industries Ltd 's case cited (Supra) that before the authority
passes an order of blacklisting, is required to give a fair hearing
and since none of the contentions raised by the petitioner was
properly considered, Ext.P49 order is liable to be interfered with.
The petitioner also relies on the judgment in Jai Praksh Singh
and another's case cited (Supra) in support of the said
contention. Petitioner also relies on the judgment in Abcon
Engineering's case (Supra) to contend for the position that the
show cause notice should contain the details of the allegation
against which the blacklisting is proposed and since the show
cause notice does not disclose any of the reasons for initiating
blacklisting proceedings against the petitioner, the decision as
per Ext.P49 is liable to be interfered with. Petitioner also relies on
the judgment in Ramson Garment Finishing Equipments Pvt.
Ltd, Bangalore's case (Supra) that due to the severity of the
effects of blacklisting, the law requires strict adherence to the
principle of natural justice and that in an action of blacklisting the
person/entity concerned is required to be duly notified of the
charges levelled against him/it and the consequences that may W.P.(C). No.17363 of 2023
follow if the charges are proved, give adequate opportunity to the
person/entity against whom such allegations are made to put
forth his/its say and the order under which blacklisting is imposed
should disclose adequate reasons for imposing such punishment
after considering/dealing with the various responses/explanations
given by the person/entity against whom the allegation is made. I
am of the opinion that none of the decisions cited supra could
come to the help of the petitioner. Though Ext.P17 order which
recommended RBDCK to initiate action against the petitioner for
the lapses as per PWD manual, was challenged before this Court
in W.P.(C)No.30487/2019, the same was ultimately dismissed as
withdrawn and no interim orders were granted by the civil court
wherein Ext.P17 order was subsequently challenged after the
dismissal of the writ petition. Another important aspect to be
considered is that even though the petitioner approached this
Court seeking for a load test to be conducted and the same was
allowed as per Ext.P19 order of this Court, the Apex Court
interfered in the matter and set aside Ext.P19 as per Ext.P20
judgment and paragraph 8 and 9 of the said judgment reads as W.P.(C). No.17363 of 2023
follows:
8) Having perused the High Court judgment, what is clear is that the High Court, instead of applying the well-established parameters of judicial review and ascertaining whether the decision of the State Government would violate Article 14, went into the matter itself and stated that it is better to have a "load test conducted to avoid any further controversy in the matter".
9) Given the fact that an Expert Committee, which is a High level Committee of five experts was set up to go into the divergent opinions of IIT Madras and Dr. E. Sreedharan, and the experts having come to a particular conclusion, it is very difficult then to say that the Government, in accepting such Expert Committee Report, could be said to have behaved arbitrarily. On this ground alone, we set aside the judgment of the High Court, as also the review judgment.
Therefore, the Apex Court has also accepted the decision of the
Government in Ext.P17 order which is based on a high-level
technical committee report. It is only thereafter that Ext.P29 W.P.(C). No.17363 of 2023
order was issued by the Government whereby administrative
sanction was granted to undertake rehabilitation work of the
Palarivattom flyover at Ernakulam through DMRC and a direction
was issued to RBDCK to initiate proceedings for recovery of the
cost of the rehabilitation work from the petitioner. It is seen that
Ext.P42 notice of hearing was issued to the petitioner. Thereupon,
the petitioner approached this Court filing W.P.(C) No.5722/2023
which was disposed of as per Ext.P44 judgment directing the
respondent licensing authority to provide the details with respect
to the blacklisting procedure adopted by the respondent so as to
enable the petitioner to file a suitable reply and to grant 3 weeks'
time to file a proper reply. Pursuant to the directions in Ext.P44,
Ext.P45 detailed allegations against the petitioner was submitted
by the 3rd respondent and has granted 3 weeks' time to file an
appropriate reply. The petitioner thereafter submitted Ext.P46
reply to the allegations raised in Ext.P45. It is only after
considering the objections submitted by the petitioner that a
decision was taken as per Ext.P49 to blacklist the petitioner on
the ground of 'poor workmanship' and for the reason that the W.P.(C). No.17363 of 2023
petitioner did not rectify the damages that occurred to the
Palarivattom flyover.
10. After considering all these aspects and after hearing
both sides, I am of the opinion that sufficient opportunity has
been granted to the petitioner to explain his case and only
thereafter that Ext.P49 was issued and valid reasons have been
stated by the authority to blacklist the petitioner. It is also
pertinent to note that pursuant to the judgment of this Court in
W.P.(C) No.21597/2017, as per Ext.R3(d) Government Order, the
Government have taken steps to amend the PWD manual to
include 'poor workmanship' as also a reason to blacklist a
contractor. I am of the considered opinion that the said ground is
very much available with the respondents to blacklist the
contractors inasmuch as the damage has been caused to the
bridge within 3 years after its construction. There is a clear
finding in the report of the experts that normally
rehabilitation/strengthening is required for old as well as
distressed bridges having service life of 40 years or more and also
strengthening works are normally required for limited members W.P.(C). No.17363 of 2023
or locations of a flyover/bridge. Going by the report of IIT Madras
itself, 97 RCC girders out of 102 girders require strengthening,
which is an extensive strengthening work for a super structure. It
is taking all these aspects into consideration, the Government
decided to demolish that portion of the bridge and to reconstruct
the same and also to initiate coercive steps against the petitioner.
11. It is pertinent to note that the Government has expended
a huge amount from the state exchequer for the construction of
the bridge which is nothing but the tax payers' money. Damages
of very serious nature have been found by the experts in the said
flyover within a short span of 3 years from its construction.
Ultimately the Government as per the advice of the expert had to
demolish a portion of the bridge and reconstructed the same
again expending a huge amount from the tax payer's money.
Taking all these aspects into consideration and on a finding
that Ext.P49 order has been issued after complying with all
procedural formalities, I am of the opinion that the action
initiated by the Government as per Ext.P49 to blacklist the
petitioner is perfectly in accordance with law and I find no reason W.P.(C). No.17363 of 2023
to interfere with the same and the above writ petition is
accordingly dismissed.
Sd/-
VIJU ABRAHAM JUDGE sm/ W.P.(C). No.17363 of 2023
APPENDIX OF WP(C) 17363/2023 PETITIONER EXHIBITS Exhibit P1 TRUE COPY OF LIST OF BRIDGES CONSTRUCTED BY THE PETITIONER IN KERALA Exhibit P2 TRUE COPY OF COMPLETE PROFILE OF THE PETITIONER Exhibit P3 TRUE COPY OF RELEVANT PORTIONS OF THE AGREEMENT DATED 04-03-2014 EXECUTED BETWEEN THE PETITIONER AND RBDCK Exhibit P4 TRUE COPY OF MINUTES OF PROJECT REVIEW MEETING HELD ON 01-09-2016 WITH RBDCK Exhibit P5 TRUE COPY OF MINUTES OF THE MEETING HELD ON 16-11-2016 BY THE RBDCK Exhibit P6 TRUE COPY OF LETTER DATED 23-11-2016 SUBMITTED BY THE PETITIONER BEFORE KITCO Exhibit P7 TRUE COPY OF LETTER DATED 13-01-2017 ISSUED BY THE PETITIONER TO RBDCK AND KITCO Exhibit P8 TRUE COPY OF COMMUNICATION DATED 27-09-
2017 ISSUED BY THE PETITIONER TO RBDCK AND KITCO Exhibit P9 TRUE COPY OF LETTER DATED 18-10-2017 ISSUED BY THE PETITIONER TO RBDCK AND KITCO Exhibit P10 TRUE COPY OF LETTER DATED 05-12-2017 ISSUED BY THE PETITIONER TO RBDCK AND KITCO Exhibit P11 TRUE COPY OF RECOMMENDATIONS OF M/S.SREE GIRI CONSULTANTS DATED 17-02-2018 Exhibit P12 TRUE COPY OF THE LETTER DATED 19-03-2019 ISSUED BY THE PETITIONER TO RBDCK AND W.P.(C). No.17363 of 2023
KITCO Exhibit P13 TRUE COPY OF LETTER DATED 28-03-2019 ISSUED BY THE RBDCK TO THE PETITIONER Exhibit P14 TRUE COPY OF LETTER DATED 26-04-2019 ISSUED BY THE RBDCK Exhibit P15 TRUE COPY OF LETTER DATED 29-07-2019 ISSUED BY THE PETITIONER TO RBDCK AND KITCO Exhibit P16 TRUE COPY OF LETTER DATED 18-09-2019 ISSUED BY THE PETITIONER TO RBDCK Exhibit P17 TRUE COPY OF GOVERNMENT ORDER G.O.(MS).
NO.52/2019/PWD DATED 25-10-2019 Exhibit P18 TRUE COPY OF ORDER DATED 12-11-2019 IN W.P(C).NO.30487 OF 2019 OF THIS HON'BLE COURT Exhibit P19 TRUE COPY OF COMMON ORDER DATED 21-11-
2019 IN W.P.(C).NO.26030 OF 2019 OF THIS HON'BLE COURT Exhibit P20 TRUE COPY OF JUDGMENT DATED 22-09-2020 IN CIVIL APPEAL NOS.3008-3015 OF 2020 OF HON'BLE SUPREME COURT OF INDIA Exhibit P21 TRUE COPY OF G.O.(RT).NO.815/2020/PWD DATED 07-10-2020 Exhibit P22 TRUE COPY OF LETTER DATED 10-12-2019 ISSUED BY THE PETITIONER TO RBDCK Exhibit P23 TRUE COPY OF COUNTER AFFIDAVIT OF THE KITCO IN W.P.(C).NO.26030 OF 2019 FILED BEFORE THIS HON'BLE COURT Exhibit P24 TRUE COPY OF PLAINT AS C.S.NO.80 OF 2021 FILED BY THE PETITIONER BEFORE THE W.P.(C). No.17363 of 2023
COMMERCIAL COURT, ERNAKULAM.
Exhibit P25 TRUE COPY OF WRITTEN STATEMENT FILED BY THE GOVERNMENT OF KERALA IN C.S.NO.80 OF 2021 BEFORE THE COMMERCIAL COURT, ERNAKULAM.
Exhibit P26 TRUE COPY OF WRITTEN STATEMENT FILED BY THE RBDCK IN C.S.NO.80 OF 2021 BEFORE THE COMMERCIAL COURT, ERNAKULAM.
Exhibit P27 TRUE COPY OF WRITTEN STATEMENT FILED BY THE KITCO IN C.S.NO.80 OF 2021 BEFORE THE COMMERCIAL COURT, ERNAKULAM.
Exhibit P28 TRUE COPY OF I.A.NO.1 OF 2021 IN C.S.NO.80 OF 2021 FILED BY THE PETITIONER BEFORE THE COMMERCIAL COURT , ERNAKULAM.
Exhibit P29 TRUE COPY OF PLAINT AS C.S.NO.240 OF 2022 FILE BY RBDCK BEFORE THE COMMERCIAL COURT,ERNAKULAM.
Exhibit P30 TRUE COPY OF WRITTEN STATEMENT FILED BY THE PETITIONER IN C.S.NO.240 OF 2022 FILED BY RBDCK BEFORE THE COMMERCIAL COURT, ERNAKULAM Exhibit P31 TRUE COPY OF JUDGMENT DATED 04-05-2020 IN W.P.(C).NO.31556 OF 2019 OF THIS HON'BLE COURT Exhibit P32 TRUE COPY OF LOA DATED 28-09-2020 ISSUED BY KSTP Exhibit P33 TRUE COPY OF LETTER OF AWARD DATED 16-09-
2020 ISSUED BY SMART CITY, THIRUVANANTHAPURAM LTD.
Exhibit P34 TRUE COPY OF LETTER OF ACCEPTANCE DATED 21-09-2020 ISSUED ON BEHALF OF KSTP W.P.(C). No.17363 of 2023
Exhibit P35 TRUE COPY OF LETTER OF ACCEPTANCE DATED 01-10-2020 ISSUED BY KSTP Exhibit P36 TRUE COPY OF LETTER OF ACCEPTANCE DATED 30-10-2020 ISSUED BY KSTP Exhibit P37 TRUE COPY OF LETTER OF ACCEPTANCE DATED 17-03-2022 ISSUED BY PETRONET LNG LIMITED Exhibit P38 TRUE COPY OF LETTER OF ACCEPTANCE DATED 08-02-2023 ISSUED BY COCHIN SHIPYARD Exhibit P39 TRUE COPY OF LETTER OF ACCEPTANCE DATED 24-08-2022 ISSUED BY COCHIN PORT AUTHORITY Exhibit P40 TRUE COPY OF LETTER OF ACCEPTANCE DATED 03-03-2022 ISSUED BY NHAI Exhibit P41 TRUE COPY OF CONSOLIDATED LIST OF THE WORKS BEING UNDERTAKEN PRESENTLY BY THE PETITIONER IN THE STATE OF KERALA Exhibit P42 TRUE COPY OF LETTER DATED 08-02-2023 ISSUED BY THE 3RD RESPONDENT Exhibit P43 TRUE COPY OF COVER CONTAINING EXHIBIT.P42 Exhibit P44 TRUE COPY OF JUDGMENT DATED 20-02-2023 IN W.P(C) NO. 5722 OF 2023.
Exhibit P45 TRUE COPY OF NOTICE DATED 05-05-20203 ISSUED BY THE 3RD RESPONDENT ALONG WITH THE ALLEGATIONS AGAINST THE PETITIONER Exhibit P46 TRUE COPY OF REPLY DATED 26-05-2023 ISSUED TO THE 3RD RESPONDENT BY THE PETITIONER.
Exhibit P47 TRUE COPY OF PWD LICENSE RENEWED UPTO 31-
03-2023 Exhibit P48 TRUE COPY OF JUDGMENT DATED 04-02-2022 IN W.P.(C). No.17363 of 2023
W.P.(C).NO.30487 OF 2019 OF THIS HON'BLE COURT Exhibit P49 TRUE COPY OF THE ORDER NO.SECCNH/153/2022-F2-PWD DATED 27-06- 2023 ISSUED BY THE 3RD RESPONDENT RESPONDENT EXHIBITS Exhibit R3(a) True copy of the hearing notice dated 08.02.2023 Exhibit R3(b) True copy of the letter No.RBDCK T 123 Vol.IX/1979 dated 06.11.2020 Exhibit R3(c) A true copy of the report of vigilance and Anti Corruption Bureau Exhibit R3(d) A True copy of the G.O.(Rt) No.552/2020/PWD dated 23.06.2020
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!