Citation : 2023 Latest Caselaw 4740 Ker
Judgement Date : 12 April, 2023
CRP No.559/2018 1/1
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE C.S.DIAS
Wednesday, the 12th day of April 2023 / 22nd Chaithra, 1945
IA.NO.2/2018(IA-1602/2018) IN CRP NO. 559 OF 2018
OP(ELE) 225/2010 OF ADDITIONAL DISTRICT COURT-I, KOZHIKODE
PETITIONER/PETITIONER:
POWER GRID CORPORATION OF INDIA LTD., REP BY ITS ADDITIONAL GENERAL
MANAGER, UGRAPURAM, AREACODE P.O, ERNAD TALUK, MALAPPURAM.
RESPONDENT/RESPONDENT:
ABDUL BASHEER, S/O. T.P AHAMMED KOYA, THUMBANPARAMBIL HOUSE,
PUTHUPPADI P.O, PUTHUPPADI VILLAGE, KOZHIKODE TALUK, KOZHIKODE
DISTRICT.
Application praying that in the circumstances stated in the
affidavit filed therewith the High Court be pleased to stay the execution
of the judgment dated 23.02.2018 passed in OP(Ele) 225/2010, on the files
of the Addl. District Judge I, Kozhikode till the disposal of the above
case in the interest of justice.
This Application again coming on for orders upon perusing the
application and the affidavit filed in support thereof, and this court's
order dated 17.03.2023 and upon hearing the arguments of SRI.E.M.MURUGAN,
Advocate for the petitioner and of M/S.V.V.SURENDRAN & P.A.HARISH,
Advocates for the respondent, the court passed the following:
ORDER
The interim order dated 17.03.2023 is extended by three months.
Sd/- C.S.DIAS, JUDGE
12-04-2023 /True Copy/ Assistant Registrar
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!