Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Musthafa Varodan vs The State Of Kerala
2022 Latest Caselaw 2033 Ker

Citation : 2022 Latest Caselaw 2033 Ker
Judgement Date : 23 February, 2022

Kerala High Court
Musthafa Varodan vs The State Of Kerala on 23 February, 2022
WP(C) NO. 18972 OF 2020              1



                 IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                  PRESENT
              THE HONOURABLE MR. JUSTICE P.V.KUNHIKRISHNAN
  WEDNESDAY, THE 23RD DAY OF FEBRUARY 2022 / 4TH PHALGUNA, 1943
                          WP(C) NO. 18972 OF 2020
PETITIONER/S:

               MUSTHAFA VARODAN
               AGED 48 YEARS
               S/O. HASSAINAR (LATE), VARODAN HOUSE, PAYYANADAM
               P.O., MANNARKKAD, PALAKKAD DISTRICT

               BY ADV BABU S. NAIR



RESPONDENT/S:

      1        THE STATE OF KERALA
               REPRESENTED BY THE SECRETARY TO THE GOVERNMENT,
               DEPARTMENT OF PUBLIC WORKS, GOVERNMENT SECRETARIAT,
               TRIVANDRUM,PIN-695 001

      2        KERALA INFRASTRUCTURE INVERSTMENT FUND BOARD,
               KERALA ROAD FUND BOARD, THIRUVANANTHAPURAM,
               REPRESENTED BY ITS CHIEF EXECUTIVE OFFICER, PIN-695
               001

      3        THE CHIEF ENGINEER,
               PUBIC WORKS DEPARTMENT, THIRUVANANTHAPURAM,PIN-695
               001

      4        THE EXECUTIVE ENGINEER
               PUBLIC WORKS DEPARTMENT (ROADS AND BRIDGES)
               PALAKKAD,PIN-678 001

      5        THE ASSISTANT EXECUTIVE ENGINEER,
               PUBLIC WORKS DEPARTMENT (ROADS AND BRIDGES) ,SUB
               DIVISION, MANNARKKAD, PALAKKAD DISTRICT,PIN-678 582

      6        ADDL R6. MOHAMMED SAGEER.P.M
               AGED 49 YEARS, S/O MOHAMMED ALI.P.A, PARAKATTIL
 WP(C) NO. 18972 OF 2020           2


               HOUSE, PAYYANADAM.P.O, MANNARKKAD, PALAKKAD DISTRICT-
               678 583.

      7        ADDL.R7. JOSE MATHEW,
               S/O E.M.MATHEW, ELAMPLASSERIL HOUSE, POOLACHIRA,
               PAYYANADAM.P.O, MANNARKKAD, PALAKKAD DISTRICT-678
               583.

      8        ADDL.R8.ABDUSSALAM.K
               S/O MOHAMMED.K, KUTTOOTH HOUSE, AKKIPPADAM,
               PAYYANADAM.P.O, MANNARKKAD, PALAKKAD DISTRICT-678
               583.

      9        ADDL.R9.DEEPESH GEORGE,
               S/O C.J.GEORGE, AGED 39 YEARS, CHELAMKOTTU HOUSE,
               PAYYANADAM.P.O, MANNARKKAD, PALAKKAD DISTRICT-678
               583.

               ADDL.R6 TO R9 IMPLEADED AS PER ORDER DATED 07.10.2020
               IN IA 1/2020 IN W.P.(C) 18972/2020.

      10       KERALA ROAD FUND BOARD,
               REPRESENTED BY ITS PROJECT DIRECTOR,
               KESTON ROAD , KOWDIAR,
               THIRUVANANTHAPURAM.
               ADDL R10 IMPLEADED SUO MOTU AS PER ORDER DATED
               16/11/2020 IN WP(C) 18972/2020.

               BY ADVS.
               SRI.K.V.MANOJ KUMAR , GOVERNMENT PLEADER
               U.K.DEVIDAS
               SMT.V.JAYA RAGI
               SRI.NEERAJ NARAYAN
               SRI.R.HARIKRISHNAN (KAMBISSERIL)




       THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
23.02.2022, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 WP(C) NO. 18972 OF 2020            3




                        P.V.KUNHIKRISHNAN, J
                  --------------------------------------------
                      W.P.(C.) No. 18972 of 2020
                     --------------------------------------
              Dated this the 23rd day of February, 2022


                               JUDGMENT

The above writ petition is filed with following prayers :

"i) Issue a writ of mandamus or any other appropriate writs, orders or directions commanding the respondents to restart the work of MES College-Payyanadam Road, forthwith, without any further delay.

ii) Grant such other reliefs as this Hon'ble Court may deem fit and proper in the circumstances of the case."

2. This Court on 23.10.2020 considered the matter and

passed the following order :

"The learned Government Pleader submits that the work is on stand still on account of objection by KIIFB. The learned Standing Counsel for the KIIFB submits that as soon as the reverse project estimate is submitted by the Kerala Road Fund Board, they will permit the work to proceed.

Whatever be the objections, all the respondents shall see that the work is restarted within a period of two weeks. Post on 16.11.2020"

3. When this writ petition came up for consideration on

16.11.2020, this Court passed the following order:

"Kerala Road Fund Board represented by its Project Director, Keston Road, Kowdiar, Thiruvananthapuram, is suo motu impleaded as additional respondent no.10.

Despite the order passed on 23.10.2020, the respondents have not re-commenced the work. According to KIIFB, the Road Fund Board has not submitted the reverse project estimate. At the same time, it is also stated that contractor though had agreed to re-commence the work has not done anything. In these circumstances of the case, one more week's time is granted to see that the road is made traffic worthy. All the official respondents shall see that the work is re-commenced and the road is made motorable at the earliest. Respondents would be free to take appropriate steps for that.

Post on 01.12.2020."

4. Thereafter, this Court passed an order on 1.12.2020,

which is also extracted hereunder :

"The learned counsel appearing for the KIIFB made available a copy of the proceedings dated 23.11.2020 by which the dispute between the KIIFB, KRFB and PWD has been sorted out. Now it is for the KRFB as well as the PWD to continue the work in accordance with the instructions issued by the KIIFB and expedite and complete it at the earliest. The learned Senior Government Pleader as well as the learned Standing Counsel appearing for KRFB submitted that the work has recommenced. Post on 15.12.2020 for reporting progress."

5. Again, the matter came up for consideration before

this Court on 15.12.2020 and on that day, this Court passed the

following order :

"Learned counsel for the petitioner submits that the work is not restarted so far and the contractor has not done anything. It is stated that stop memo is not in so far lifted. At the same time, the learned Standing Counsel for the KIIFB on the strength of Ext.R2(j) produced along with the counter affidavit submits that suspension is already revoked. Ext.R2(j) issued by the Chief Project Examiner-Inspection Authority of KIIFB states that in exercise of his powers under Clause 12 of the tripartie agreement he has accorded approval to revoke the instruction for suspension of work with immediate effect subject to the 5 following conditions:

1. Inspection Authority (Technical), KIIFB shall

inspect the work for ensuring the correctness of compliance report and to monitor the status of pre- compliance report submitted.

2. Modified/corrected PED including strip plans along with revised estimate concurred by TS authority shall be submitted within 15 days from the date of issue of this letter.

3. Close monitoring of the progress and quality of the project shall be ensured by KRFB and fortnight report of same shall be sent to Inspect Authority without fail.

4. Relevant contractual clauses for imposing penalty shall be applied to the contractor for the delay caused due to unjustified delay in the work.

5. The revised time frame for completion of the project shall be prepared and submitted by KRFB.

Therefore respondents 4, 5 and 6 shall see that work is undertaken and the road is made motorable at the earliest.

Post on 22.12.2020."

6. Subsequently, the matter came up for consideration

on 12.1.2021 and on that day, this Court passed the following

order :

"The learned Government Pleader submits that the work is going on. At the same time, the learned counsel for the petitioner submits that in the absence of a plan from KRFB, the work going on is slow pace.

The learned Standing Counsel to get instructions. Post on 3.2.2021."

7. Today, when the matter came up, the learned counsel

for the petitioner submitted that even now, the work of the road

is not completed and the counsel also submitted that there may

be a time limit to complete the work. The learned Government

Pleader after getting instructions, submitted that the BM&BC

work will be completed on or before 31.5.2022. In the light of

the above submission, this writ petition can be disposed of

recording the same.

Therefore, this writ petition is disposed of with a direction

to the additional respondent No. 10 and also respondent No.4 to

complete the road work in question as expeditiously as possible,

at any rate, on or before 31.5.2022.

SD/-

P.V.KUNHIKRISHNAN JUDGE SKS

APPENDIX OF WP(C) 18972/2020

PETITIONER EXHIBITS

EXHIBIT P1 TRUE COPY OF THE ORDER OF THE FIRST RESPONDENT DATED 1.11.2016 AS NO G.O.(RT) 1502/2016/PWD

EXHIBIT P2 TRUE COPY OF THE ORDER DATED, 16.3.2018 NO.APR-1/310/2018/KIIFB ISSUED BY THE 2ND RESPONDENT

EXHIBIT P3 TRUE COPY OF THE ORDER SUSPENDING THE WORKS ISSUED BY THE 2ND RESPONDENT DATED,28.11.2019

EXHIBIT P4 TRUE COPIES OF THE PHOTOGRAPHS OF THE PRESENT CONDITION OF THE ROAD

EXHIBIT P5 TRUE COPY OF THE QUESTION ASKED BY SHRI.SHAMSUDHEEN MLA IN THE FLOOR OF LEGISLATIVE ASSEMBLY DATED 2.3.2020

EXHIBIT P6 TRUE COPY OF THE REPLY GIVEN BY THE HON'BLE MINSTER DATED,5.3.2020

RESPONDENT EXHIBITS

EXHIBIT R6(a) TRUE COPY OF THE COMPLAINT DATED NIL

EXT.R2(A) A TRUE COPY OF THE TRIPARTITE AGREEMENT DATED 17.7.2017 BEARING NO.7 OF 2015 ENTERED BETWEEN KRFB,PWD AND THE 2ND RESPONDENT

EXT.R2(B) A TRUE COPY OF THE PROCEEDINGS NO.APR-

1/310/2018 KIIFB DATED 16.3.2018

EXT.R2(C) A TRUE COPY OF THE PHOTOGRAPHS OF THE PROJECT WORK SITE

EXT.R2(D) A TRUE COPY OF THE ORDER DATED 28.11.2019 ISSUED BY THE CEO OF THE 2ND

RESPONDENT/KIIFB

EXT.R2(E) A TRUE COPY OF THE MINUTES OF THE MEETING HELD IN THE OFFICE OF THE CHIEF PROJECT EXAMINER OF THE KIIFB DATED 26.2.2020

EXR.R2(F) A TRUE COPY OF THE COMMENTS EXPRESSED BY THE TECHNICAL RESOURCE TEAM OF THE KIIFB IN THE PLAN AND PROFILE SUBMITTED BY THE KRFB

EXT.R2(G) A TRUE COPY OF THE DETAILS OF PROJECT INTERVENTION MEETING HELD AT THE OFFICE OF THE CHIEF PROJECT EXAMINER KIIFB ON 29.6.2020

EXT.R2(H) A TRUE COPY OF THE REVISED PLAN AND PROFILE SUBMITTED BY THE TECHNICAL RESOURCE CENTER KIIFB BEFORE THE PWD AND KRFB DATED 15.9.2020

EXT.R2(I) A TRUE COPY OF THE ACTION PLAN FOR REVOKING THE SUSPENSION OF WORK OF THE MES COLLEGE PAYYANADAM ROAD

EXT.R2(J) A TRUE COPY OF THE LETTER ISSUED BY THE CHIEF EXECUTIVE OFFICER REVOKING THE INSTRUCTION FOR SUSPENSION OF THE WORK DATED 23.11.2020 BEARING NO.PWD006-21-TIW- INSP-01

ANNEXURE R4(A) A TRUE COPY OF THE PHOTOGRAPHS CONNECTED WITH THE ONGOING WORKS

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter