Friday, 15, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Cochin Municipal Corporation vs M/S.G.J Eco Power Pvt. Ltd
2022 Latest Caselaw 1505 Ker

Citation : 2022 Latest Caselaw 1505 Ker
Judgement Date : 3 February, 2022

Kerala High Court
The Cochin Municipal Corporation vs M/S.G.J Eco Power Pvt. Ltd on 3 February, 2022
W.A. No. 1685/2020 & 1579/2021          :1:




                IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                 PRESENT

            THE HONOURABLE THE CHIEF JUSTICE MR.S.MANIKUMAR

                                    &

                 THE HONOURABLE MR. JUSTICE SHAJI P.CHALY

         THURSDAY, THE 3RD DAY OF FEBRUARY 2022 / 14TH MAGHA, 1943

                           WA NO. 1685 OF 2020

 JUDGMENT DATED 10.11.2020 IN WP(C) 11850/2020 OF HIGH COURT OF KERALA

APPELLANTS/PETITIONER:

             M/S.G.J.ECO POWER PVT.LTD.,
             A COMPANY INCORPORATED UNDER THE COMPANIES ACT
             HAVING ITS REGISTERED OFFICE AT DOOR NO.X/63,SARAYU
             COMPLEX,
             SEAPORT-AIRPORT ROAD,KAKKANAD,COCHIN-682 030,REPRESENTED
             BY ITS DIRECTOR,
             MR.JAMES ADAI,S/O.FR.ADAI JACOB,AGED 36,

             BY ADVS.
             GEORGE VARGHESE(PERUMPALLIKUTTIYIL)
             A.R.DILEEP
             MANU SRINATH
             P.J.JOE PAUL



RESPONDENTS/RESPONDENTS:

     1       THE COCHIN MUNICIPAL CORPORATION
             REPRESENTED BY ITS SECRETARY,
             PARK AVENUE ROAD,COCHIN-682 011.

     2       THE SECRETARY,
             COCHIN MUNICIPAL CORPORATION,
             PARK AVENUE ROAD,COCHIN-682 011.

     3       THE STATE OF KERALA,
             REPRESENTED BY ITS PRINCIPAL SECRETARY,
             LOCAL SELF GOVERNMENT (DC)DEPARTMENT,
             GOVERNMENT SECRETARIAT,
 W.A. No. 1685/2020 & 1579/2021      :2:


          THIRUVANANTHAPURAM-695 001.

    4     THE STATE LEVEL ADVISORY COMMITTEE ON WASTE MANAGEMENT,
          REPRESENTED BY CHIEF SECRETARY,
          STATE OF KERALA,GOVERNMENT SECRETARIAT,
          TRIVANDRUM-695 001.

    5     THE KERALA STATE INDUSTRIAL DEVELOPMENT CORPORATION,
          KOWDIAR,THIRUVANANTHAPURAM,
          KERALA,PIN-695 033.

          BY ADVS.
          SRI. SUDHEESH KUMAR,STANDING COUNSEL(B/O)
          R5 BY SRI. P.U.SHAILAJAN
          SHRI.K.JANARDHANA SHENOY, SC, KOCHI MUNICIPAL CORPORATION
          R1 & R2 BY RENJITH THAMPAN (SR.)
          ADVOCATE GENERAL
          R3 & R4 BY SHRI.S.KANNAN, SENIOR G.P.




     THIS WRIT APPEAL HAVING COME UP FOR ADMISSION ON 03.02.2022,

     ALONG WITH WA.1579/2021, THE COURT ON THE SAME DAY DELIVERED THE

     FOLLOWING:
 W.A. No. 1685/2020 & 1579/2021          :3:



                IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                 PRESENT

            THE HONOURABLE THE CHIEF JUSTICE MR.S.MANIKUMAR

                                    &

                 THE HONOURABLE MR. JUSTICE SHAJI P.CHALY

         THURSDAY, THE 3RD DAY OF FEBRUARY 2022 / 14TH MAGHA, 1943

                           WA NO. 1579 OF 2021

 JUDGMENT DATED 10.11.2020 IN WP(C) 11850/2020 OF HIGH COURT OF KERALA

APPELLANTS/RESPONDENT NOS. 1 & 2:


     1       THE COCHIN MUNICIPAL CORPORATION
             REPRESENTED BY ITS SECRETARY, PARK AVENUE ROAD,
             COCHIN-682 011.

     2       THE SECRETARY
             COCHIN MUNICIPAL CORPORATION, PARK AVENUE ROAD,
             COCHIN-682 011.

             BY ADV SHRI.K.JANARDHANA SHENOY, SC, KOCHI MUNICIPAL
             CORPORATION

RESPONDENTS/PETITIONER & RESPONDENT NOS. 3 TO 5:


     1       M/S.G.J ECO POWER PVT. LTD
             A COMPANY INCORPORATED UNDER THE COMPANIES ACT HAVING ITS
             REGISTERED OFFICE AT DOOR NO.X/63, SARAYU COMPLEX, SEAPORT-
             AIRPORT ROAD, KAKKANAD, COCHIN-682 030, REPRESENTED BY ITS
             DIRECTOR, MR.JAMES ADAI, S/O.FR.ADAI JACOH, AGED 36.

     2       THE STATE OF KERALA
             REPRESENTED BY ITS PRINCIPAL SECRETARY, LOCAL SELF
             GOVERNMENT (DC) DEPARTMENT, GOVERNMENT SECRETARIAT,
             TRIVANDRUM-695 001.

     3       THE STATE LEVEL ADVISORY COMMITTEE ON WASTE MANAGEMENT,
             REPRESENTED BY CHIEF SECRETARY, STATE OF KERALA,
             GOVERNMENT SECRETARIAT, TRIVANDRUM-695 001.

     4       THE KERALA STATE INDUSTRIES DEVELOPMENT CORPORATION,
             KOWDIAR, THIRUVANANTHAPURAM, KERALA, PIN-695 033.
 W.A. No. 1685/2020 & 1579/2021       :4:




     R2 & R3 BY SRI. S. KANNAN SR. GOVERNMENT PLEADER
     R1 BY SRI. P. WILSON (SR.)
     R4 BY SRI. P.U. SHAILAJAN

     THIS WRIT APPEAL HAVING BEEN FINALLY HERD ON 03.02.2022,   ALONG

     WITH WA.1685/2020, THE COURT ON THE SAME DAY DELIVERED THE

     FOLLOWING:
 W.A. No. 1685/2020 & 1579/2021                  :5:



                    Dated this the 3rd day of February, 2022.

                                         JUDGMENT

SHAJI P. CHALY, J.

The captioned writ appeals are filed challenging the judgment of

the learned single Judge dated 10.11.2020 in W.P.(C) No. 11850 of

2020. W.A. No. 1685 of 2020 is filed by the writ petitioner; whereas,

W.A. No. 1579 of 2021 is filed by the Kochi Municipal Corporation, the

third respondent in the writ petition, basically contending that the

issues raised by the Municipal Corporation were not properly

appreciated by the learned single Judge. W.A. No. 1685 of 2020 is

treated as the lead case and the parties and exhibits are referred to as

in the said writ appeal.

2. The subject issue relates to the cancellation of a contract

awarded to the appellant, a company incorporated under the

Companies Act, by the Corporation of Kochi. The State Government

has cancelled the approval given for executing the contract, for the

implementation of the Waste-to-Energy Project at Brahmapuram,

Ernakulam District as per Ext. P28 Government Order dated

30.04.2020. Thereafter, the Secretary, Kochi Municipal Corporation-

2nd respondent, issued Ext. P29 notice dated 04.05.2020, terminating

the concession agreement executed by and between the appellant and W.A. No. 1685/2020 & 1579/2021 :6:

the Kochi Municipal Corporation. Even though representation was

made requesting to cancel Ext.P28 and to protect the project, the

State Government, as per Ext.P34 order dated 05.06.2020, passed a

fresh order on the basis of a direction issued by a learned single Judge

of this Court as per Exhibit P32 Judgment in W.P.(C) No.9872 of 2020

dated 30th May 2020, reiterating the order in Ext.P28, having found

that the concessionaire i.e. the appellant, is unable to implement the

project even if more time is allowed. It was, thus, challenging the

legality and correctness of the aforesaid proceedings, the writ petition

was filed.

3. The paramount contentions advanced by the appellant in the

writ petition as well as the appeal are that; Exts. P28, P29 and P34

impugned orders/notice are illegal, arbitrary and violative of principles

of natural justice and the same were issued without any authority;

that even though a letter of award was issued on 08.01.2016 and the

concession agreement was executed on 17.02.2016, the site was not

handed over; that the first respondent, in its decision dated

25.07.2016, only resolved to hand over 8 Hectares of land in

Puthencruz village, Ernakulam District, to the appellant; and that the

sketch of the site was forwarded to the appellant as per Ext. P3

proceedings dated 24.06.2017, and the appellant has received the

same only on 26.02.2018.

W.A. No. 1685/2020 & 1579/2021 :7:

4. It is also contended that out of the total extent of the land

allotted measuring 809.4 Ares, only an extent of 257.6 Ares alone was

dry land and the rest was paddy/wetland covered under the Kerala

Conservation of Paddy land and Wetland Act, 2008 ('Act, 2008' for

short) and therefore, it was impossible and impracticable to implement

the project in the land identified by the Kochi Municipal Corporation;

that only after much discussion and deliberations, and after the

Amendment Ordinance of 2017, the State Government issued Ext. P4

order dated 03.02.2018 exempting the land from the provisions of the

Act, 2008. It was further contended that even in Ext. P4, there was a

condition to construct a Water Conservation Area (pond) in an extent

of 55.18 Ares of land, and further directed not to obstruct the natural

flow of water, and since the entire land was essential for the project

the land exempted for the construction of the water conservation area

has to be compensated.

5. It was further submitted that it was only as per Ext. P6 dated

09.08.2018, the State of Kerala permitted the Kochi Municipal

Corporation to hand over another extent of 3.44 acres of land after

exempting from the provisions of the Act, 2008 and that even though

the concession agreement was executed on 17.02.2016, the extent of

the land to be allotted was finalised only on 09.08.2018 as per Ext. P6

order of the State Government, and when the sketch was handed over W.A. No. 1685/2020 & 1579/2021 :8:

on 19.11.2018. According to the appellant, by virtue of Article 5 of the

concession agreement, an independent Engineer has to be appointed

to monitor the entire work, and the procedure for appointment of an

independent Engineer is provided in Article 5.1(a) of the Concession

agreement; however, the Kochi Municipal Corporation has not

communicated the list of Engineers to the appellant as contemplated

under Article 5.1(a); that there was no financial bid called for the

selection of the independent Engineer till date and therefore, there was

total violation of Article 5 of the concession agreement. That apart, it

is submitted that though by virtue of Article 3.1(a)(vii), the appellant

has to furnish a financing plan, and financing documents for the

project and thereby demonstrate the financial close, it could not be

achieved due to the recalcitrant attitude of the respondents in handing

over the land in contemplation of the agreement which was the

essence of the contract.

6. According to the appellant, even though various financial

institutions/investors were interested in the project and ready to

finance, the collateral security can only be from the income generated

from the energy and by virtue of a licence/agreement/ concession

agreement, the financiers were not willing to part with the money and

all the financial institutions insisted that the licence agreement shall be

converted into a lease agreement so as to enable them to provide W.A. No. 1685/2020 & 1579/2021 :9:

necessary finance and therefore, the appellant approached the Kochi

Municipal Corporation and the State Government for conversion of the

concession agreement into a lease agreement.

7. It is also the case of the appellant that the State Level

Advisory Committee on Waste Management, represented by the Chief

Secretary, State of Kerala, the 4th respondent, having been satisfied

with the necessity of converting the concession agreement into a lease

agreement, requested the State Government to take necessary steps

to execute a lease agreement, evident from Exts.P9 and P10 minutes

dated 12.12.2018 and 29.04.2019 respectively; that even though the

Kochi Municipal Corporation, in its meeting held on 29.04.2019,

resolved to reject the request for the execution of lease agreement,

the State Government accepted Exts.P9 and P10 recommendations of

the 4th respondent, the State Level Advisory Committee, and issued

Ext. P22 order dated 16.01.2020 cancelling Ext. P10 resolution of the

Kochi Municipal Corporation dated 29.04.2019 and directing it to

execute the lease agreement.

8. Therefore, the contention advanced by the appellant is that

the State Government as well as the State Level Advisory Committee

understood the necessity of executing a lease agreement and that the

Government was not satisfied with the rejection of the request for the

execution of the lease agreement by the Kochi Municipal Corporation.

W.A. No. 1685/2020 & 1579/2021 : 10 :

Therefore, the contention advanced is that the bona fides of the

appellant in implementing the project is very well reflected from the

conduct of the State Government as well as the State Level Advisory

Committee.

9. The sum and substance of the contentions, relying upon the

stand of the Government and the State Level Advisory Committee, is

that had the Kochi Municipal Corporation complied with Ext. P22

Government Order dated 16.01.2020 and executed the lease

agreement, without any delay, the appellant could have initiated the

activities of financial close immediately; and that it was because of the

recalcitrant attitude of the Kochi Municipal Corporation, having not

executed the lease agreement, the appellant was virtually prevented

from achieving the financial close.

10. The further case of the appellant is that, a major factor

attributed for the delay is the non formulation of the mechanism for

payment of energy charges beyond what is fixed by the Kerala State

Electricity Regulatory Commission, and even though by Ext. P23 order

dated 31.01.2020 the State Government ordered that 25% of the

expenses over and above the average power tariff fixed by the Kerala

State Electricity Regulatory Commission for the energy produced from

the Waste to Energy plant at Brahmapuram should be paid to the

concessionaire by the Government from the major infrastructure W.A. No. 1685/2020 & 1579/2021 : 11 :

development scheme and that the remaining 75% by Kochi Municipal

Corporation by way of collection of user fee from

households/institutions/participating LSGIs/utilising 15% of the plan

fund to be set apart compulsorily for waste management/by locating

other means etc., no decision has been taken by the Kochi Municipal

Corporation with regard to the payment of 75% of the energy charges

and therefore, there was utter confusion with regard to the payment of

the energy charges by the first respondent.

11. Therefore, it is the predominant contention that, under the

aforesaid circumstances the demand in Ext. P23 Government Order

dated 31.01.2020 to achieve the financial close within 30 days, was

illegal and beyond perception of the agreement executed by and

between the parties.

12. It is also contended by the appellant that the direction of

the Kochi Municipal Corporation to execute the lease agreement was

on 16.01.2020 and therefore, Ext. P23 order of the Government dated

31.01.2020 calling upon the appellant to achieve the financial close

within 30 days is illegal and arbitrary. That apart, it is submitted that

the appellant has submitted Ext. P25 reply dated 27.02.2020

explaining the delay in achieving the financial close. But, even after

receipt of Ext. P25, the State Government has not taken any steps to

see that the first respondent executes a lease agreement enabling the W.A. No. 1685/2020 & 1579/2021 : 12 :

appellant to satisfy the financial institution with regard to its

repayment capacity. It was in the aforesaid background the appellant

had submitted Ext. P25 representation dated 27.02.2020 to the State

Government which passed Ext. P34 order declining the request made

therein. These are the basic background facts available before us to

consider the case put forth by the appellant.

13. The State Government has filed a detailed counter affidavit

in the appeal disputing the allegations and the claims and demands

raised by the appellant. According to the State Government, it was by

virtue of the Government Order, G.O. (Ms.) No. 260/2013/LSGD dated

20.07.2013 that the State Government accorded sanction to instal the

solid waste management plant at Brahmapuram based on the Thermal

Technologies (Waste to Energy Project) and thereupon, the Kerala

Industrial and Technical Consultancy Organization Ltd. (KITCO) was

appointed as the transaction advisor for the implementation of the

project. Consequent thereto, the appellant had participated in the

tender process and by Ext. P1 Government Order dated 04.01.2016,

the Government of Kerala approved the project of the appellant,

submitted by the KITCO for a total cost of Rs.295 Crores, subject to

the conditions enumerated therein. It is also submitted that

consequently, orders and agreements were executed by and between

the Kochi Municipal Corporation and the appellant. The paramount W.A. No. 1685/2020 & 1579/2021 : 13 :

contention advanced by the State Government is that as per Article 3

of the concession agreement executed on 17.02.2016, the award of

the concession shall be subject to the satisfaction of the waiver of the

conditions precedent, enumerated in the agreement, and going by

Article 3.1(a)(vii) of the concession agreement, the concessionaire

shall furnish its financing plan and financing documents for the project

and demonstrate financial close. Further, it is stated that as per clause

3.1(b) of the concession agreement, the authority shall hand over

physical possession of the project site for the purpose of the project

and that as per Article 3.2 of the concession agreement, the conditions

precedent shall be complied within 180 days of the date of agreement

i.e., 17.02.2016, wherein it is stipulated that each party shall promptly

inform the other party, in writing, as to when the conditions precedent

for which it is responsible, have been satisfied.

14. It is pertinently pointed out that by virtue of Article 3.3. of the

concession agreement, any conditions precedent as contemplated in

Articles 3.1(a) and 3.1(b) of the concession agreement may be waived

by the authority at any point of time in its sole discretion. Relying upon

Article 21.8 of the concession agreement, it is submitted that no

waiver of any term or condition or breach thereof by any party thereto

shall be valid, unless expressed in writing and is signed by such party

and communicated to the other. Therefore, according to the State W.A. No. 1685/2020 & 1579/2021 : 14 :

Government, there is no implied waiver or any waiver by way of

conduct, and to the knowledge of the State Government, the Kochi

Municipal Corporation has not waived any of the conditions precedent

as contemplated under Article 21.8 of the concession agreement.

15. Relying upon Article 3.6 of the concession agreement, it is

contended that if the conditions precedent are not complied with within

the time, including the extended time, if at all any, the concession

agreement shall be liable to be terminated, and by virtue of the

provisions of Article 3 of the concession agreement, the party in

default has to compensate the other party of the agreement by way of

liquidated damages at the rate mentioned therein.

16. Therefore, it is submitted that in the event of termination of

the agreement, a remedy is clearly prescribed as per the terms of the

concession agreement and the parties, therefore, have to adhere to

the terms and conditions of the agreement executed by and between

the parties. That apart, it is pointed out that as is evident from Ext. P3

order of the Kochi Municipal Corporation dated 24.06.2017 and Exts.

P4 and P6 orders of the State Government dated 03.02.2018 and

09.08.2018 respectively, the project site having an extent of 8

Hectares of land comprised in Survey Nos. 30,35, 36, 37, 45 and 56 of

Block No. 37 of Puthencruz Village was handed over to the appellant.

Therefore, it is contended that the authority has satisfactorily complied W.A. No. 1685/2020 & 1579/2021 : 15 :

with its condition precedent as is contemplated under Article 3.1(b) of

the concession agreement and has intimated the same to the

concessionaire.

17. So much so, it is submitted that, even though Exhibit P8 request

of the appellant dated 29.02.2016 to execute the lease agreement in

respect of the concession agreement was declined by the Kochi

Municipal Corporation, since the implementation of the project is of

utmost public importance in pursuance to the policy of the State

Government, the State Government, by Ext. P22 order dated

16.01.2020 directed the Kochi Municipal Corporation to execute the

lease agreement as is sought for by the appellant. But, the appellant

and the first respondent, Kochi Municipal Corporation, has not acted

upon Ext. P22 Government Order and no lease agreement or deed

was executed by and between the said parties.

18. It is also contended that as on the date of Ext. P22

Government Order, though substantial time has elapsed, the appellant

did not inform the authority in writing as to whether the appellant had

satisfied or complied with the conditions precedent, in contemplation

of Article 3.1(a) of the Concession agreement, more particularly those

contained under Article 3.1(a)(vii). Instead, the appellant had

approached the State Government and informed that the appellant

requires the mechanism for payment to meet the expenses over and W.A. No. 1685/2020 & 1579/2021 : 16 :

above the tariff fixed by the Kerala State Electricity Regulatory

Commission to overcome the hurdles for achieving the financial close

and it was based on the said request, the State Government, by Ext.

P23 dated 31.03.2020, formulated a mechanism for payment to meet

the expenses over and above the power tariff to the appellant.

19. That apart, it is pointed out that since the appellant had not

attained the financial close, the State Government directed the

appellant to achieve the financial close within 30 days from the date of

Ext. P23, however, with a rider that necessary action shall be initiated

to terminate the concession agreement, on the concessionaire failing

to do so. Anyhow, on receipt of Ext. P23, the appellant submitted Ext.

P25 representation before the Government inter alia informing that the

appellant requires 100% State Government Guarantee for debt fund

approval of NABARD, so as to achieve the financial close.

20. Apart from the same, the appellant has also sought for a

further relaxation of time, which are outside the scope, ambit and

purview of the concession agreement and that the matter was

considered by the State Level Advisory Committee, in its meeting held

on 13.03.2020, and observed that since the appellant has not achieved

the financial close, the concession agreement cannot be converted to

lease agreement. Therefore, it is submitted that it was in the above

background that the State Government has issued Ext. P28 order W.A. No. 1685/2020 & 1579/2021 : 17 :

dated 30.04.2020 cancelling Ext. P1 approval granted to the project

and thereby, directing the Kochi Municipal Corporation to terminate the

concession agreement with a further direction to float a RFP for

Brahmapuram project. Other contentions are also raised by the State

Government justifying its stand adopted in Ext. P28 order impugned in

the writ petition.

21. W.A.No. 1579 of 2020 is filed by the Kochi Municipal

Corporation basically contending that the learned single Judge was not

correct in finding that the writ petition itself is not maintainable, since

the subject matter is in regard to the contractual aspects and disputed

questions of facts and no public interest is involved in the matter. That

apart, it is also contended that the writ petition is barred by the

principles of res judicata and the appellant company is estopped from

filing a writ petition, since it has filed W.P.(C) No. 9872 of 2020

seeking the similar reliefs; however, the same was disposed of by this

Court without granting the reliefs sought for and directing the State

Government to take a decision in the representations submitted by the

appellant. Therefore, it is submitted that the reliefs sought for in the

said writ petition are deemed to be declined, and they cannot be

resurrected by filing a fresh writ petition.

22. We have heard learned Senior Counsel for the appellant Sri. W.A. No. 1685/2020 & 1579/2021 : 18 :

P. Wilson assisted by Adv. George Varghese Perumpallikuttiyil, learned

Senior Advocate Sri. Ranjit Thampan for the Corporation of Kochi and

the learned Senior Government Pleader Sri. S. Kannan for the State

Government, and perused the pleadings and materials on record.

23. The paramount contention advanced by the learned Senior

Counsel for the appellant is that since the project site agreed upon as

per Article 1.1 of the concession agreement was not physically handed

over to the appellant, it cannot be found fault with for not attaining the

financial close in contemplation of Article 3.1(a)(vii). It is also

contended that in order to secure financial assistance from the

financial institutions, a lease has to be executed by the Kochi Municipal

Corporation with the approval of the State Government, which

situation was realised by the State Government evident from Ext. P22

order. However, the Government, later, resiled from the same, without

assigning any reasons. It is also the case of the appellant that the

purpose of Article 3.1(b) is a condition precedent to be performed by

the Corporation so as to compel the appellant to comply with the

conditions precedent under clause 3.1(a)(vii) of the concession

agreement; that as per Ext. P3 dated 24.06.2017, the Corporation

only forwarded the boundary fixed survey sketch to the appellant and

out of the total land measuring 809.4 Ares allotted, only 257.6 Ares W.A. No. 1685/2020 & 1579/2021 : 19 :

was dry land and the balance was wet land guided by the provisions of

the Act, 2008; and therefore, exemption from the Government was

necessary even for taking possession of the land for the project. It is

further argued that the Government has issued Ext. P4 order dated

03.02.2018 exempting the land from the purview of the Act, 2008 with

a deduction of 55.18 Ares.

24. It is further contended that the above aspects would show

that the Kochi Municipal Corporation has not complied with Article

3.1(b) by handing over the possession of the land and hence, financial

close has been deemed to be achieved. That apart, it is submitted that

when the State Government, as per Ext. P22 Government Order,

cancelled the decision of the Kochi Municipal Corporation in regard to

the request made by the appellant for the execution of the lease

agreement and directed to execute a lease agreement in respect of

the concession agreement, according to the learned Senior Counsel,

the concession agreement has become redundant and unenforceable.

25. It is further submitted that the State Level Advisory

Committee, the 4th respondent, was satisfied with the necessity of

executing the lease agreement for the implementation of the project

and recommended to the Government to that effect as per Exts. P9

and P10 decisions, in which the Secretary of the Kochi Municipal W.A. No. 1685/2020 & 1579/2021 : 20 :

Corporation was a party and therefore, the Municipal Council was not

entitled to retract from the decision taken by the State Level Advisory

Committee; and in fact, the Government has acted upon the decisions

taken by the State Level Advisory Committee and after understanding

the intrinsic aspects preventing the appellant from proceeding with the

project alone, Ext. P22 order was issued cancelling the decision taken

by the Kochi Municipal Corporation declining the request for the

execution of a lease agreement.

26. It is also contended that Ext. P28 order issued by the State

Government and Ext. P29 notice issued by the Kochi Municipal

Corporation withdrawing the approval and cancelling the contract is in

violation of Article 16 of the concession agreement, in view of the

covenants contained under Article 16.1 providing a methodology for

the termination procedure by issuing notice in writing of at least not

less than 90 days and not more than 180 days. Therefore, it is

submitted that in the instant case, there was lack of compliance of the

procedure by the State Government as well as the Kochi Municipal

Corporation and therefore, the entire action of the State Government

as well as the Kochi Municipal Corporation are arbitrary, illegal and

violative of the principles of natural justice, liable to be interfered with

by this Court under Article 226 of the Constitution of India.

W.A. No. 1685/2020 & 1579/2021 : 21 :

27. In that regard, the learned Senior Counsel has relied upon

the judgment of the Apex Court in Vice-Chairman & Managing

Director, City and Industrial Corporation of Maharashtra Ltd.

vs. Shirir Realty Pvt. Ltd. (2022 (1) KHC SN 4 (SC), wherein it is

held that providing effective natural justice to parties to a contract or

awardee of tender is necessary to maintain Rule of Law. He has also

relied upon the decision of the Hon'ble Apex Court in ABL

International Ltd. v. Export Credit Guarantee Corporation of

India (2004) 3 SCC 553, wherein it is held that in an appropriate

case, a writ petition as against a State or an instrumentality of a State

arising out of a contractual obligation is maintainable.

28. In regard to the contentions raised by the respondents that

the writ petition in question is barred by the principles of res judicata,

it is submitted that the learned single Judge, as per Ext. P32 judgment

in W.P.(C) No. 9872 of 2020, has made an open remand of the issues

at dispute, while directing the State Government to pass orders on

Ext.P31 representation, in which a review of all the impugned orders

were sought for. Therefore, it is contended that when the State

Government has passed a fresh order, acting upon the representation,

a fresh cause of action arose and therefore, the principles of res

judicata would not be attracted. In that regard, the learned Senior W.A. No. 1685/2020 & 1579/2021 : 22 :

Counsel has relied upon the judgment of the Apex Court in Asgar and

others v. Mohan Varma and Others [2020 (16) SCC 230],

wherein it is held that in deciding as to whether a matter might have

been urged in the earlier proceedings, the court must ask itself as to

whether it could have been urged and in deciding whether the matter

ought to have been urged in the earlier proceedings, the court will

have due regard to the ambit of the earlier proceedings and the nexus

which the matter bears to the nature of the controversy. Other

contentions are also raised to canvas the proposition that the

impugned orders are not sustainable under law, justifying interference

of the writ court.

29. On the other hand, the learned Senior Counsel for the

Corporation of Kochi addressed arguments basically relying upon

clause 3 of the concession agreement. It is also pointed out that the

contention advanced by the learned Senior Counsel for the appellant

that the termination procedure was not followed in contemplation of

clause 16, is not sustainable for the reason that it is applicable when a

termination is made otherwise than in accordance with the other

provisions of the agreement, but shall not include expiry of agreement

due to efflux of time in a normal course. That apart, it is pointed out

that the said clause clearly specifies various methods in regard to the W.A. No. 1685/2020 & 1579/2021 : 23 :

termination of the agreement, especially the termination of the

agreement due to efflux of time in a normal course. It is also pointed

out by the learned Senior Counsel for the Kochi Municipal Corporation

that the mandatory requirement of financial close contained under

clause 3.1(a)(vii) is an independent covenant from the other

provisions of the agreement and also a condition precedent and

therefore, the appellant is not entitled to advance arguments by

making it adaptable to other provisions of the agreement.

30. It is also the contention of the learned Senior Counsel that

the appellant company has failed to achieve the milestones in

accordance with the provisions of the concession agreement and in

spite of an opportunity given to the appellant, it has not made any

earnest efforts to make the project of State Government as well as the

Municipal Corporation a reality. That apart, it is contended that there

was no agreement entered into by and between the parties for the

execution of the lease agreement in order to secure financial support

from the financial institutions by mortgaging the leasehold rights and

therefore, the contention advanced by the learned Senior Counsel for

the appellant, relying upon the orders passed by the State

Government in regard to the lease agreement, cannot be sustained

under law.

W.A. No. 1685/2020 & 1579/2021 : 24 :

31. It is further pointed out that the benefits under the

electricity tariff were offered by the Government as per Ext. P23

Government Order dated 31.01.2020 on condition that, appellant

achieves the financial close within 30 days from the aforesaid date and

therefore, the appellant is not entitled to make out a case relying upon

such benefits offered by the State Government. Arguments were

advanced by the learned Senior Counsel that the present writ petition

is barred by the principles of res judicata, relying upon various

judgments of the Apex Court.

32. The State has also filed an argument note, basically

supporting the contentions advanced by the Kochi Municipal

Corporation and relying upon the relevant clauses of the concession

agreement.

33. We have evaluated the rival submissions made across the

Bar. In fact, along with the writ appeal, the entire concession

agreement is produced: whereas, in the writ petition only the material

portion of the concession agreement was produced. Since the

predominant contention advanced by the learned Senior Counsel for

the appellant is that the impugned orders are violative of the principles

of natural justice and arbitrary and illegal, our primary endeavour is to

find out as to whether the learned single Judge has committed any W.A. No. 1685/2020 & 1579/2021 : 25 :

jurisdictional error in the matter of considering the aforesaid legal

position.

34. Before going into the intricacies of the concession

agreement executed by and between the parties, we are of the

considered opinion that the circumstances leading to the issuance of

Ext. P28 Government Order dated 30.04.2020 is required. The

Government has taken note of the factual circumstances leading to

the execution of the concession agreement and other aspects and it is

stated therein that the Director of the appellant, as per letter dated

11.10.2018, requested that the company requires the balance of

payment mechanism to meet the expenses over and above the power

tariff fixed by the Kerala State Regulatory Commission to overcome

the hurdles for achieving the financial close.

35. Therefore, it is stated that, it was accordingly that the State

Government issued an order dated 31.01.2020 satisfying the mode of

payment of the expenses over and above the power tariff fixed by the

Kerala State Electricity Regulatory Commission. But, it is clearly

specified that it was ordered so on condition that the appellant

achieves the financial close within 30 days from the date of order and

failing which it was strictly cautioned that action will be initiated to

terminate the concession agreement in accordance with the terms and

conditions of the agreement. The Government has also noted that in W.A. No. 1685/2020 & 1579/2021 : 26 :

spite of the due consideration shown and further time granted to

achieve the financial close, the appellant Company did not make any

offer to comply with the directions issued by the Government.

36. It was thereupon that the Government verified the relevant

covenants contained in the concession agreement and arrived at the

conclusion that the approval granted to the project is required to be

cancelled and the Secretary of the Kochi Municipal Corporation was

directed to terminate the concession agreement following the

procedure laid down in Article 16 of the agreement. Therefore, on a

deep seated analysis of Ext. P28 impugned Government Order, it is

unequivocal that the Government has considered every minute

aspects before taking a decision, and at present there was no other

alternative for the Government than to withdraw the approval granted

to the project submitted by the appellant.

37. Now coming to Ext. P29 notice of termination dated

04.05.2020 issued by the Kochi Municipal Corporation, what we could

gather is that even after 1400 days of execution of the agreement, the

concessionaire i.e., the appellant, could neither submit the financial

close, nor specify the source of funds required for the completion of

the project. Therefore, the Cochin Municipal Corporation doubted the

capacity of the appellant to complete the project. The Corporation was

also of the opinion that relaxation and additional support like W.A. No. 1685/2020 & 1579/2021 : 27 :

conversion of agreement and Government guarantee etc., which are

not part of the concession agreement, show that the appellant is not

having sufficient financial resources in order to carry on with the

project. Therefore, the Corporation found that since the appellant

failed to achieve the financial close as per Article 3.3. of the concession

agreement within 180 days from the date of agreement or within the

extended period, Article 3.6 will automatically apply as the conditions

therein are not waived by the authority and therefore, the agreement

stand cancelled by virtue of the imperative nature of Article 3.6 of the

concession agreement.

38. Therefore, relying upon the procedure prescribed under

Article 3 of the agreement, it is contended that the termination

procedure contemplated under Article 16 of the concession agreement

is not at all required.

39. Now coming to Ext. P34 order dated 05.06.2020 passed by

the State Government on the basis of the directions issued by a

learned single Judge of this Court in Ext. P32 judgment dated 13th May,

2020 in W.P.(C) No. 9872 of 2020, the Government considered the

entire aspects put forth by the appellant, relying upon the terms and

conditions of the concession agreement. However, it was found that

the concessionaire i.e. the appellant, cannot implement the project

even if more time is allowed and it was accordingly that the W.A. No. 1685/2020 & 1579/2021 : 28 :

Government declined the review of its Ext. P28 order.

40. Therefore, on an analysis of the orders impugned by the

appellant in the writ petition, it is clear that the Government has

taken into consideration the entire aspects under the concession

agreement and the circumstances leading to the withdrawal of the

approval, and cancellation of the contract by the respective authority.

It is also evident from Ext. P23 order dated 31.01.2020 that the

Government has granted a further 30 days' time from the date of the

said order to the appellant to achieve the financial close and on failure

of the same only, the termination of the concession agreement was

proposed.

41. It is an admitted fact that the appellant failed to achieve the

financial close within the extended period and it was thereupon that

Ext. P28 order was passed by the State Government withdrawing the

approval and consequently, termination order was passed by the Kochi

Municipal Corporation.

42. Insofar as the concession agreement executed by and

between the parties is concerned, it is executed by and between the

Kochi Municipal Corporation and the appellant in order to satiety the

requirement of the Municipal Solid Waste (Management and Handling)

Rules, 2000, whereby it is made mandatory; for every municipal

authority to implement a Scientific Solid Waste Management System, W.A. No. 1685/2020 & 1579/2021 : 29 :

wherein the Municipal solid waste is duly processed and only inorganic

waste and processed residues are disposed in a landfill.

43. Therefore, the introductory clause of Annexure A concession

agreement shows that the timely completion of the project was a vital

requirement. 'Financial close' is defined under the agreement to

mean, the date on which the Financing Documents providing for

Financial Assistance by the Lenders, Equity Documents and the

documents in respect of debt, if any, committed by the Consortium

have become effective and the concessionaire has access to such

financial assistance. 'Financing Documents' are defined under the

agreement to mean, collectively, the documents executed in favour of

or entered into with the lenders, by the Concessionaire in respect of

the Financial Assistance relating to the financing (including any re-

financing) of the Actual Project Cost and includes any document

providing security for the Financial Assistance.

44. 'Conditions precedent' is defined to mean the conditions

prescribed in Article 3 of the agreement.

45. Therefore, on an analysis of the terminologies employed

under the agreement as to the financial close, financial documents and

the conditions precedent, it is clear that the entire responsibility in the

matter of achieving the financial close as a condition precedent is upon

the appellant .

W.A. No. 1685/2020 & 1579/2021 : 30 :

46. Now we proceed to consider the impact of Article 3 of the

concession agreement dealing with the conditions precedent. Article

3.1 clearly specifies that the award of the concession shall be subject

to the satisfaction or waiver of the conditions precedent delineated

therein. Article 3.1(a)(vii) clearly specifies that; furnishing its

Financing Plan and Financing Documents for the Project and

demonstrating financial close is upon the appellant; however provided

that financial close shall be deemed to be achieved, if the only

conditions pending for achieving financial close are those which are

required to be fulfilled by the Authority under Article 3.1(b)

thereunder.

47. Article 3.1(b) clearly specifies a condition precedent, which

shall be satisfied by the authority by handing over the physical

possession of the project site for the purpose of the project.

'Authority' is defined under the concession agreement to mean, Kochi

Municipal Corporation. Therefore, subject to the handing over the

physical possession of the project site for the purpose of the project,

the financial close had to be achieved by the appellant within 180 days

of the date of agreement. 'Project site' is defined under the

concession agreement to mean the land handed over to the

concessionaire by the authority for the project, out of the 8 (eight)

Hectares of land earmarked at Brahmapuram as shown in the Drawing W.A. No. 1685/2020 & 1579/2021 : 31 :

No.TS-35SP DRG 01 001 for the processing and disposal of MSW

(more fully described in Schedule-I).

48. Therefore, it is clear from the description of project site

that; it is the handing over to the concessionaire ie. the appellant by

the Kochi Municipal Corporation the land from and out of 8 Hectares of

land earmarked at Brahmapuram as shown specifically in the drawing.

49. On a perusal of Schedule 1 attached to the concession

agreement, it is clear that the project is proposed to be developed at

Brahmapuram, wherein the Kochi Municipal Corporation owns about

110 acres of land lying adjacent to the Brahmapuram Diesel Power

Plant and the site area is 8 Hectares of land earmarked at

Brahmapuram as shown therein specified above and attached in Article

9 dealing with 'payments to the authority'.

50. Therefore, it is clear that the obligation created as per

Article 3.1(b)(i) is satisfied by the authority i.e., the Kochi Municipal

Corporation at the time of execution of the concession agreement

itself. Therefore, the contention advanced by the appellant that only a

portion of the land remained as dry was alone handed over, and the

major portion of the land coming under the provisions of the Act, 2008

was not handed over, and it was actually handed over after the

exemption order issued by the Government cannot be sustained. We

do not find much force in the said contention, because no such issue W.A. No. 1685/2020 & 1579/2021 : 32 :

was raised and pursued by the appellant any time before the

cancellation of the approval and termination of the agreement .

51. On a perusal of Section 10(1) of the Act, 2008, it is clear

that notwithstanding anything contained in Section 3, the Government

may grant exemption as per the provisions of the Act, only if such

conversion or reclamation is essential for any public purpose and shall

notify in the official Gazette. It is true that a procedure is

contemplated to exempt the paddy field for conversion or reclamation.

However, when the authority had handed over the land with the

approval of the State Government to the appellant, the appellant is not

entitled to turn around and contend that the land handed over has

adverse consequences to utilise or convert the same for the purpose of

the project.

52. Moreover, the Government, the authority or the public have

not raised any manner of objection with respect to the hand over of

the land by the Kochi Municipal Corporation to the appellant, much less

an objection against utilisation of a paddy field for other purposes.

Above all, it is clear from Schedule 1 of the agreement that the project

site is a portion of the larger extent of land already in the possession

of the Kochi Municipal Corporation .

53. Therefore, in our considered opinion, merely because the

exemption order was handed over by the Government after W.A. No. 1685/2020 & 1579/2021 : 33 :

completing the formalities prescribed under Section 10 of the Act,

2008 at a later point of time, that did not detain the appellant from

utilising the land for the implementation of the project in any manner

of, whatsoever, nature added to the fact that the land was handed over

with the approval of the State Government .

54. Now, coming to Article 3.6 of the concession agreement

dealing with the compliance of the conditions precedent, it is clear that

in the event of the conditions precedent are not complied with within

the time (including the extended time, if any) in terms of Articles 3.2

to 3.5, the agreement shall be liable to be terminated and if such

termination is on account of the failure of the concessionaire to comply

with the conditions precedent, the Bid security shall stand forfeited;

however if such termination is on account of failure of the authority,

the authority shall be obliged to return the Bid Security/Performance

Security; but it is clarified that except for the payment as stipulated in

the foregoing Articles 3.4 and 3.5 and forfeiture in Article 3.6, each

party thereto shall have no claims against the other for costs,

damages, compensation or otherwise. Articles 3.3 to 3.5 are relevant

to the context and they read thus:

"3.3 Any of the Conditions Precedent set forth in Articles 3. l(a) may be waived fully or partially by the Authority at any time in its sole discretion or the Authority may grant additional time for compliance with these conditions and the Concessionaire shall be bound to ensure W.A. No. 1685/2020 & 1579/2021 : 34 :

compliance within such additional time as may be specified by the Authority. Any of the Conditions Precedent set forth in Articles 3.1 (b) may be waived fully or partially by the Concessionaire at any time in its sole discretion.

3.4 If the Concessionaire has fulfilled all the Conditions Precedent under Article 3.1(a) including the furnishing of the Bank Guarantee and has not waived or extended the time under Clause 3.3 above, and if the Authority has failed to fulfill the conditions Precedent to be fulfilled by it under Article 3.1(b) and which are within the power of the Authority, the Authority shall be liable to pay liquidated damages in a sum calculated at the rate of 0.1% (zero point one percent) of the Performance Security for each day's delay until fulfillment of the Conditions Precedent subject to a maximum of 5% (five percent) of the figure mentioned in the Performance Security furnished by the Concessionaire. In such event, having regard to the quantum of damages, the time for the performance shall be deemed to have been extended by the number of days for which the liquidated damages is paid and if, after the extended period the Authority is still not in a position to comply with the Conditions Precedent, then the agreement shall be liable to be terminated as provided for in Clause 3.6 below;

3.5. If the Authority has fulfilled all the Conditions Precedent under Article 3.1(b) and has not waived or extended the time under Clause 3.3 above, and if the Concessionaire has failed to fulfil the Conditions Precedent to be fulfilled by it under Article 3.1(a) and which are within the powers of the Concessionaire, the Concessionaire shall be liable to pay liquidated damages in a sum calculated at the rate of 0.1% (zero point one percent) of the Performance Security for each day's delay until fulfillment of the Conditions Precedent subject to a maximum of 5% (five percent) of the figure mentioned in the Performance Security furnished by the Concessionaire. In such event, having regard to the quantum of damages, the time for the performance shall be deemed to have been extended by the number of days for which the liquidated damages is paid and if, after the extended period the Concessionaire is still not in a position to comply with the Conditions Precedent, then the W.A. No. 1685/2020 & 1579/2021 : 35 :

agreement shall be liable to be terminated as provided for in Clause 3.6 below,"

55. Therefore, on a conjoint reading of the definition given in the

concession agreement, the significant provisions discussed above and

Article 3 of the concession agreement, it is clear that the liability cast

upon the appellant as well as the Kochi Municipal Corporation under

Article 3 of the agreement is independent of the other provisions of the

concession agreement and the parties were duty bound to attain the

targets fixed therein, irrespective of the other covenants agreed upon

by and between the parties.

56. Yet another feature that is significant to be discussed is

Article 6, dealing with the project implementation. Article 6.3 dealing

with construction phase, stipulates that the concessionaire shall

promptly commence and complete the works, including installation of

equipment in accordance with the Project Schedule and shall also

obtain from the independent Engineer a certificate as to the

completion of the construction of Project Facilities and Services in

accordance with the provisions of the agreement not later than 18

months from the date of commencement of the concession period.

Concession agreement is dated 17th day of February, 2016.

57. Therefore, it is clear that a time bound action from the part

of the concessionaire was an essential condition of the contract by and W.A. No. 1685/2020 & 1579/2021 : 36 :

between the parties, failing which termination was axiomatic in terms

of the termination clause contained under Article 16 of the agreement,

due to efflux of time. Article 6.4 deals with obligations of the

concessionaire and Article 6.4(b) makes it clear that the

concessionaire shall, at its cost, expenses and risk make such

financing arrangements as would be necessary to implement the

project and to meet all of its obligations under the agreement, in a

timely manner.

58. Article 6.4(c) makes it clear that the concessionaire shall

give notice to the authority within 7 days of any material modification

or change to any of the Financing Documents and or any equity

documents and shall simultaneously therewith also furnish copies of

such modified/amended documents to the authority. The proviso

thereto makes it clear that no such modification/amendment will be

made if it in any manner, whatsoever, has the effect of imposing an

additional financial obligation or increasing the financial obligation of

the authority in addition to that contemplated under the financing

document provided on financial close, without the prior written

consent of the authority. It was further made clear thereunder that

any such modifications/amendments made without the prior written

consent of the authority will not be enforceable against the authority.

59. We are relying upon the said Article for the basic reason W.A. No. 1685/2020 & 1579/2021 : 37 :

that the concession agreement as it remains, is a licence deed, and

there is no covenant executed by and between the parties that in

future a lease agreement would be executed by and between the

parties so as to enable the appellant to mortgage the leasehold rights

and secure the financial facilities from any financial institution.

Therefore, the contention advanced by the appellant that it was due to

the failure on the part of the Kochi Municipal Corporation that the

property could not be mortgaged and finance secured from willing

financial institutions, has no force of law in absentia of any such

imperatives in the agreement. Such a contention, in our view, is also

clearly outside the spirit of the agreement executed by and between

the parties, and therefore the attempt of the appellant to make out a

case from a totally strange resource cannot be sustained at all legally

and factually.

60. Again, coming to Article 15 dealing with events of default,

Article 15.1 specifies that the event of default shall mean either

concessionaire event of default or the authority event of default or

both as the context may admit or require. Clause (a) thereto

describes the concessionaire event of default, which stipulates that the

concessionaire shall not be considered to be in breach of its obligations

under the agreement, nor shall it incur or suffer any liability if and to

the extent performance of any of its obligations under the agreement W.A. No. 1685/2020 & 1579/2021 : 38 :

is affected by or on account of (I) force majeure event, subject to

Article 14.7; (ii) the Authority Event of Default; (iii) compliance with

the instructions of the independent Engineer/the authority or the

directions of any Government Authority other than instructions issued

to a consequence of a breach by the concessionaire of any of its

obligations thereunder; and (iv) closure of the Project Facilities or part

thereof with the approval of the Independent Engineer/the authority.

61. Therefore, it can be seen that the appellant cannot be heard

to say that there was any such intervening event to hold that the

concessionaire shall not be considered to be in breach of its obligations

under the agreement. So much so, under the sub-head thereto, the

events that constitute an event of default by the concessionaire are

delineated and they read thus:

a) the Concessionaire's failure to perform or discharge any of its obligations in accordance with the provisions of this Agreement.

b) the Performance Security is not maintained in terms of the provisions thereof.

c) construction at the Project site is abandoned for a period more than 90 (ninety) days during the Construction Phase:

(i) The Concessionaire has failed to adhere to the Construction Requirements and such failure, in the reasonable estimation of the Independent Engineer, is likely to delay achievement of Date of Commercial Operations beyond 90 (ninety) days of the Scheduled W.A. No. 1685/2020 & 1579/2021 : 39 :

project Completion Date... "

62. On a consideration of the specifications made thereto, it is

clear that the concessionaire's failure to perform or discharge any of

its obligations in accordance with the provisions of the agreement shall

be treated as an event of default. Therefore, there are clear provisions

contained under the concession agreement to deal with and tackle the

situations that occur during the currency of the agreement executed

by and between the parties.

63. Now coming to Article 16 dealing with termination of the

concession agreement, it enables the parties entitled to terminate the

agreement on account of a Force Majeure Event or on account of an

event of default shall do so by issue of a notice in writing ("Termination

Notice") to the other party and simultaneously deliver a copy thereof

to the lenders. Therefore, it is clear that under the aforesaid two

circumstances alone, Article 16 comes into play and thereby, the

procedure mandated thereunder would operate in the matter of

termination of the agreement. This we say because, the paramount

contention advanced by the Kochi Municipal Corporation is that the

termination procedure contained under the said article of the

concession agreement would not come into operation for the basic

reason that the appellant has not attained the financial close as is W.A. No. 1685/2020 & 1579/2021 : 40 :

undertaken under the agreement.

64. Taking into account the aforesaid factual and legal aspects,

and the specific contractual terms and conditions entered into by and

between the parties, we are of the opinion that since the appellant has

not achieved the financial close, the Government was at liberty to

withdraw the approval given to the Kochi Municipal Corporation to

execute the concession agreement and the Kochi Municipal Corporation

consequently was at liberty to take a decision with respect to the

termination of the agreement. It is clear from the impugned

Government Order as well as the notice of the Kochi Municipal

Corporation that the termination was made due to the failure on the

part of the appellant to achieve the financial close in contemplation of

the concession agreement executed by and between the parties which

is a condition precedent. Therefore, we have no doubt in our mind to

hold that when there are specific, imperative and mandatory

conditions in a contract obligating a party to discharge a condition

precedent to proceed with the contract, the said consenting party has

to discharge the said essential condition which is the essence of

contract.

65. We are also of the view that even the Government has

extended the period to achieve the financial close as per Ext. P23

order dated 31.01.2020 by a period of 30 days and had rendered an W.A. No. 1685/2020 & 1579/2021 : 41 :

opportunity to achieve the financial close. But, in spite of the same,

the appellant has not made any effort. It is also clear from the

concession agreement that the appellant was liable to pay the

electricity tariff in accordance with the tariff fixed by the Kerala State

Electricity Regulatory Commission. However, the concession was

extended as per Ext. P23 order, subject to the condition that the

appellant achieves the financial close within 30 days prescribed under

the said order. Admittedly, the appellant was unable to attain the

financial close and therefore, the arguments advanced by the appellant

relying upon the concession made in Ext. P23 order cannot be

sustained under law., especially due to the fact that it was not at all a

part of the concession agreement.

66. The contention advanced by the appellant that no

opportunity was provided to the appellant before the withdrawal of the

approval and termination of the agreement, also cannot be sustained

for the reason that the representation submitted by the appellant

before the Government was considered elaborately by the

Government and Exhibit P23 order was passed by the Government

after taking into account the entire pros and cons involved in the

subject matter and also granting adequate time to achieve the

'Financial Close'.

67. Moreover, as per the direction issued by a learned single W.A. No. 1685/2020 & 1579/2021 : 42 :

Judge in Ext. P32 judgment , the Government reconsidered the

matter and has issued Ext. P34 order impugned, after providing an

opportunity of hearing in the representation of the appellant, and also

hearing the Kochi Municipal Corporation.

68. Therefore, we find that the conclusion arrived at by the

learned single Judge in the impugned Judgment to decline the prayers

sought for by the appellant to quash the impugned orders/notice is in

accordance with law and require no interference, since we find that

there was no manner of illegality, arbitrariness or other legal infirmities

justifying interference in a writ proceeding under Article 226 of the

Constitution of India.

69. Now coming to the appeal filed by the Kochi Municipal

Corporation, we are of the considered opinion that the learned single

Judge had to enter into the findings contained thereunder in the

process of identifying as to whether there was any illegality,

arbitrariness or violation of the principles of natural justice, thus

creating cause of action for filing a writ petition. We are also of the

view that, in so far as the contention that Ext. P32 judgment rendered

by the learned single Judge would create res judicata in the filing of

the writ petition in question, the same cannot be sustained for the

basic reason that the learned single Judge directed the State

Government to reconsider the withdrawal of the approval by taking W.A. No. 1685/2020 & 1579/2021 : 43 :

into account the representation submitted by the appellant and it was

after hearing the parties and re-appreciating the entire documents and

the terms and conditions of the concession agreement, it has arrived

at the independent findings in Exhibit P34, and therefore, the

appellant, if aggrieved, was at liberty to challenge the said

Government Order as of right, since it creates a new cause of action

and in that process, the previous order of the State Government ie.,

Exts. P28 order and Ext. P29 termination notice of the Kochi Municipal

Corporation, were also liable to be challenged. Therefore, we do not

find any merit in the appeal filed by the Kochi Municipal Corporation.

Upshot of the above discussion is that both the appeals are

dismissed.

sd/-

S. MANIKUMAR, CHIEF JUSTICE.

sd/-

SHAJI P. CHALY, JUDGE.

Rv
 W.A. No. 1685/2020 & 1579/2021        : 44 :




                 APPENDIX of W.A. NO. 1685/2020

APPELLANT'S ANNEXURES:

ANNEXURE A: TRUE COPY OF CONCESSION AGREEMENT DATED 17.02.2016.

ANNEXURE b: TRUE COPY OF REQUEST FOR PROPOSAL ISSUED BY THE 5TH RESPONDENT.

ANNEXURE 1: TRUE COPY OF THE GOVERNMENT ORDER GO(RT.) NO. 1754/2021/LSGD DATED 14.09.2021 ISSUED BY THE THIRD RESPONDENT.

ANNEXURE 2: TRUE COPY OF THE NOTICE NO. CML-EE1-AEEVI/WTE- BRAHMAPURAM/2021-22-207 DT. 07.10.2021 ISSUED BY THE KERALA ELECTRICITY BOARD LIMITED.

ANNEXURE 3: TRUE COPY OF REPLY DATED 28.10.2021 ISSUED BY THE WRIT APPELLANT TO THE KERALA STATE ELECTRICITY BOARD LIMITED.

RESPONDENTS' ANNEXURES: NIL

/True Copy/

PS To Judge

rv

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter