Citation : 2022 Latest Caselaw 1445 Ker
Judgement Date : 2 February, 2022
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE P.V.KUNHIKRISHNAN
WEDNESDAY, THE 2ND DAY OF FEBRUARY 2022 / 13TH MAGHA, 1943
WP(C) NO. 22912 OF 2018
PETITIONER/S:
K.M.KUNHIKRISHNAN, AGED 65 YEARS
MAVILA VALAPPIL HOUSE,CHIRAKKAL P.O.,KANNUR
DISTRICT-670 011
BY ADVS.
SRI.T.R.HARIKUMAR
SRI.ARJUN RAGHAVAN
SRI.ADITHYA RAJEEV
RESPONDENT/S:
1 THE KANNUR MUNICIPAL CORPORATION
REPRESENTED BY ITS SECRETARY,KANNUR-670 001
2 THE SECRETARY
KANNUR MUNICIPAL CORPORATION,REPRESENTED BY ITS
SECRETARY, KANNUR-670 001
BY ADVS.
SMT.S.AMBILY
SMT.M.MEENA JOHN, SC, KANNUR MUNICIPAL
CORPORATION
SMT.NAMITHA NAMBIAR
SRI.SAJI THOMAS
OTHER PRESENT:
ADV MEENA M -SC
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR
ADMISSION ON 02.02.2022, THE COURT ON THE SAME DAY
DELIVERED THE FOLLOWING:
-2-
W.P.(C). No. 22912 of 2018
P.V.KUNHIKRISHNAN, J.
=================================================
W.P. (C) No. 22912 of 2018
=============================================================
Dated this the 2nd day of February, 2022
JUDGMENT
The above writ petition is filed with following prayers:
"i) to issue a writ of mandamus or any other writ, direction or order, directing the respondents to forthwith disburse the amounts payable to the petitioner as per Ext.P3.
ii) to grant such other relief's as this Honourable Court may deem fit in the circumstances of this case."
2. The petitioner is a registered 'B' class contractor,
who had undertaken various civil contract works for the 1 st
respondent Corporation. One such contract was for the
reconstruction of Kakkathodu side wall and covering slab II
stage. The estimate cost for the work awarded as per Ext.P2
was Rs.18,50,000/- for which provision was made in the budget
of the 1st respondent Corporation. Immediately after award of
contract the petitioner commenced the work and completed the
W.P.(C). No. 22912 of 2018
same on 31.03.2015. It is the case of the petitioner that the
work was completed by expending an amount of Rs.18,90,156/-
and as per the contract certificate, an amount of Rs.17,76,745/-
is payable to the petitioner. It is the definite case of the
petitioner that in spite of more than several years elapsed, the
amount due to the petitioner under the contract work executed
by him has so far not been paid. Hence, this writ petition is
filed.
3. Heard the learned counsel for the petitioner and the
learned Standing counsel appearing for the 1st respondent.
4. The counsel for the petitioner reiterates his
contentions in the writ petition. The counsel submitted that the
work is satisfactorily completed and even now the admitted
amount is not paid to the petitioner. There is absolutely no
justification for the same.
5. On the other hand, the learned Standing Counsel for
W.P.(C). No. 22912 of 2018
the 1st respondent takes me through paragraph 5 of the
Statement filed by the 1st respondent, in which it is stated that
some irregularities are noted by the concerned officer and
enquiry is necessary. But the counsel for the petitioner takes
me through paragraph 5 of the reply affidavit, in which it is
stated that no such enquiry was conducted so far.
6. I considered the contentions of the petitioner and the
respondents. It is an admitted fact that the work was completed
in the year 2015 itself. The petitioner is entitled to the amount
due to him. But the Standing Counsel for the 1 st respondent
takes me through paragraph 5 of its statement, which reads thus:
"5. Since the work is extended, the petitioner is liable to pay fine as per the PWD Manual. He is liable to pay fine for the delayed signing of the agreement also. All these things are to be considered before the bill can be approved and passed for payment. Some of the irregularities are noted by the concerned officer and on detailed verification, the above irregularities/illegalities are detected and found out.
Unless the above are considered and appropriate
W.P.(C). No. 22912 of 2018
decision is taken by the appropriate authorities/forum, the petitioner cannot claim payment of any amount on the basis of Ext.P3 or on the basis of the work done by him. He has joined with the above mentioned Officers of the Municipality (Corporation) to perpetrate the irregularity and therefore, before the Municipality (present Corporation) can take a decision, the petitioner is to be given notice of the above and he has to explain the above defects/irregularities. The corporation also is to consider whether any action is to be taken against the erring officers. The petitioner will be definitely given notice and he will be given opportunity to explain his position. Thereafter appropriate decision will be taken and the amount as found eligible to be paid to the petitioner will be paid after completing the formalities and procedure."
7. In paragraph 5, it is stated that the Corporation has to
consider whether any action is to be taken against the erring
officers. It is also stated that the petitioner will be given notice
and he will be given an opportunity to explain his contentions
and thereafter only the decision will be taken. The statement is
filed on 13.09.2018. The petitioner filed reply affidavit in July
2021. As on that date also, the Corporation has not conducted
W.P.(C). No. 22912 of 2018
any enquiry or proceedings in connection with this work. This
cannot be go on like this because the petitioner contended
before this Court that he is entitled to the amount due to him
and a finality is necessary. If any amount is due to the
petitioner that should be disbursed to him forthwith, the counsel
submits.
Therefore, this writ petition is disposed of in the following
manner:
1. The 1st respondent is directed to conduct the enquiry or any other proceedings, which is mentioned in paragraph 5 of the statement dated 13.09.2018, as expeditiously as possible, at any rate, within two months from the date of receipt of a copy of this judgment.
2. Before passing orders as directed above, an opportunity of hearing, either virtually or physically, should be given to the petitioner.
3. Based on the decision taken by the 1st respondent in
W.P.(C). No. 22912 of 2018
the enquiry, the amount due to the petitioner should be disbursed to him within three weeks from the date on which the decision is taken, as directed above.
sd/-
P.V.KUNHIKRISHNAN JUDGE das
W.P.(C). No. 22912 of 2018
APPENDIX OF WP(C) 22912/2018
PETITIONER EXHIBITS EXHIBIT P1 A TRUE COPY OF THE IDENTITY CARD ISSUED TO THE PETITIONER IN MAY, 2007 EXHIBIT P2 A TRUE COPY OF THE RELEVANT PAGES OF THE AGREEMENT NO.7/13-14 DATED 27-04- 2013, ENTERED INTO BETWEEN THE PETITIONER AND THE 1ST RESPONDENT CORPORATION EXHIBIT P3 A TRUE COPY OF THE RELEVANT PAGES OF THE CONTRACT CERTIFICATE ISSUED AFTER COMPLETION OF WORK AS PER EXT-P2 AGREEMENT.
EXHIBIT P4 A TRUE COPY OF THE REPRESENTATION SUBMITTED BY THE PETITIONER DATED 13- 01-2016 EXHIBIT P5 A TRUE COPY OF THE POWER OF ATTORNEY DATED 15.11.2017 ALONG WITH THE COVERING LETTER DATED 20.11.2017 ISSUED BY THE KANNUR CORPORATION EXHIBIT P6 A TRUE COPY OF THE COMMUNICATION DATED 28.03.2018 FORWARDED BY THE DIRECTOR KANNUR JILLA CONTRACTORS COOPERATIVE SOCIETY LTD. NO.C 1430 EXHIBIT P7 TRUE COPY OF THE JUDGMENT DATED 20.07.2018 IN WP(C) 22785 OF 2018 EXHIBIT P8 A TRUE COPY OF THE JUDGMENT DATED 23.07.2018 IN WPC NO.23106 OF 2018.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!