Citation : 2021 Latest Caselaw 21891 Ker
Judgement Date : 3 November, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
WEDNESDAY, THE 3RD DAY OF NOVEMBER 2021/12TH KARTHIKA, 1943
WP(C) NO. 12243 OF 2021
PETITIONER:
OJASVI'S CONSTRUCTION SOLUTIONS,
A PARTNERSHIP FIRM,
REGISTERED UNDER THE INDIAN PARTNERSHIP ACT,
REP. BY ITS MANAGING PARTNER,
ARUN P.,
S/O.P.PURUSHOTHAMAN,
PARASKHTHI BUILDING,
SHORANUR, PALAKKAD DISTRICT, 679 122
BY ADV BINOY VASUDEVAN
SRI.SREEJITH SREENATH
RESPONDENTS:
1 STATE OF KERALA,
REP. BY ITS PRINCIPAL SECRETARY TO THE
GOVERNMENT,
PUBLIC WORKS DEPARTMENT,
GOVERNMENT SECRETARIAT,
THIRUVANANTHAPURAM 695 001
2 THE CHIEF ENGINEER (ROADS),
PUBLIC WORKS DEPARTMENT,
GOVERNMENT SECRETARIAT,
THIRUVANANTHAPURAM 695 001.
3 THE SUPERINTENDING ENGINEER,
PUBLIC WORKS DEPARTMENT (ROADS AND BRIDGES),
CENTRAL CIRCLE,
ALUVA 683 101
4 THE EXECUTIVE ENGINEER,
PUBLIC WORKS DEPARTMENT (ROADS DIVISION),
THRISSUR - 680 001
WP(C) No.12243/2021
:2 :
5 THE ASSISTANT EXECUTIVE ENGINEER,
PUBLIC WORKS DEPARTMENT (ROADS SUB DIVISION),
CHAVAKKAD - 680 506
SRI.K.V.MANOJKUMAR, SR.GOVERNMENT PLEADER
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR
ADMISSION ON 03.11.2021, THE COURT ON THE SAME DAY
DELIVERED THE FOLLOWING:
WP(C) No.12243/2021
:3 :
JUDGMENT
~~~~~~~~~
Dated this the 3rd day of November, 2021
The petitioner-Firm, which is an A-class Contractor
under the Public Works Department, has approached this
Court seeking to command the 2nd respondent to relieve the
petitioner from the contract by considering Ext.P14
representation forwarded by the 3rd respondent as
expeditiously as possible.
2. The petitioner states that the Firm of the petitioner
participated in a tender floated by the 3 rd respondent. The
tender was for improvement of a road under the jurisdiction of
respondents 4 and 5. Agreement was executed on
20.04.2018 and the site was handed over to the petitioner on
30.04.2018.
3. The petitioner was directed not to start the work
since the Kerala Water Authority was proposing to lay WP(C) No.12243/2021
pipelines through the road. It is the case of the petitioner that
though the petitioner approached the officers many times to
sort out the issue, no action was taken for nearly one year.
The Kerala Water Authority finally informed that they are not
proposing to lay pipeline through the portion where the
contract work is proposed to be done.
4. The petitioner would state that by this time, the
price of materials was escalated and the petitioner submitted
an application for revision of rates. No decision was taken on
the application of the petitioner for the next six months. But,
at the same time, the respondents were forcing the petitioner
to start and complete the work. As the petitioner was not in a
position to undertake the work without revision of rates, the
petitioner submitted Ext.P14 application before the 3 rd
respondent seeking to relieve him from the work and pay the
bills for the work already done.
5. As no action was taken on Ext.P14, the petitioner
filed W.P.(C) No.1895/2021 wherein this Court directed the 2 nd
respondent to consider Ext.P14 and take a decision thereon. WP(C) No.12243/2021
As it was not the 3rd respondent's jurisdiction to terminate the
contract work without risk and cost, the 3 rd respondent
forwarded the matter to the 2nd respondent as can be seen
from Ext.P16. However, no action was taken on the request
of the petitioner. Therefore, the petitioner is before this Court.
6. During the pendency of this writ petition, the
petitioner produced Ext.P18, which is a minutes of the hearing
held by the Chief Engineer, PWD (Roads) on 25.08.2021. In
the said meeting, it was recorded that the Superintending
Engineer, Roads Central Circle, Aluva pointed out that the
condition of the road in question is becoming worse and in
order to make the road traffic worthy, rearrangement of work
after terminating the petitioner's contract is inevitable.
Accordingly, the Chief Engineer informed that the proposal for
terminating the Contractor without risk and cost was already
submitted to the Government on 18.07.2021 and considering
the damaged condition of the road and contractor's request,
reminders shall be submitted to the Government regarding
the relieving of the Contractor from the work. WP(C) No.12243/2021
7. I have heard the learned counsel for the petitioner
and the learned Government Pleader representing the
respondents.
8. As the request of the petitioner for termination of
contract without risk and cost is now pending consideration
before the Government, it would be only just and proper that
the writ petition is disposed of directing the 1 st respondent to
take a final decision in the matter within a stipulated period.
Accordingly, the writ petition is disposed of directing
the 1st respondent to take a final decision on the issue of
termination of the contract with the petitioner taking into
consideration Ext.P18 minutes of the hearing held by the Chief
Engineer, PWD (Roads), within a period of one month.
Sd/-
N. NAGARESH, JUDGE
aks/05.11.2021 WP(C) No.12243/2021
APPENDIX OF WP(C) 12243/2021
PETITIONER'S EXHIBITS:
Exhibit P1 TRUE COPY OF THE PWD LICENSE OF THE PETITIONER Exhibit P2 TRUE COPY OF THE LETTER NO.DTC-
4071/2017 DATED 4.4.2018 ISSUED BY THE 3RD RESPONDENT Exhibit P3 TRUE COPY OF THE TENDER QUOTED BY THE PETITIONER Exhibit P4 TRUE COPY OF THE ACKNOWLEDGEMENT FORM OF HANDING OVER OF THE SITE DATED 30.4.2018 Exhibit P5 TRUE COPY OF THE LETTER DATED 23.9.2018 SUBMITTED BY THE PETITIONER BEFORE THE 4TH AND 5TH RESPONDENTS Exhibit P6 TRUE COPY OF THE LETTER DATED 31.10.2018 SUBMITTED BY THE PETITIONER BEFORE THE 3RD RESPONDENT.
Exhibit P7 TRUE COPY OF THE LETTER DATED 12.3.2019 SENT BY THE EXECUTIVE ENGINEER, KERALA WATER AUTHORITY TO THE 5TH RESPONDENT. Exhibit P8 TRUE COPY OF THE LETTER DATED 1.4.2019 SENT BY THE 5TH RESPONDENT TO THE PETITIONER Exhibit P9 TRUE COPY OF THE LETTER DATED 12.7.2019 SENT BY THE 5TH RESPONDENT TO THE 4TH RESPONDENT.
Exhibit P10 TRUE COPY OF THE LETTER DATED 1.9.2019 SUBMITTED BY THE PETITIONER BEFORE THE 3RD RESPONDENT.
Exhibit P11 TRUE COPY OF THE LETTER DATED 30.9.2019 SENT BY THE 5TH RESPONDENT TO THE PETITIONER Exhibit P12 TRUE COPY OF THE LETTER DATED 8.11.2019 SENT BY THE 4TH RESPONDENT TO THE 5TH RESPONDENT Exhibit P13 TRUE COPY OF THE LETTER DATED 9.12.2019 SENT BY THE 5TH RESPONDENT WP(C) No.12243/2021
Exhibit P14 TRUE COPY OF THE REQUEST DATED 3.2.2020 SUBMITTED BY THE PETITIONER TO THE 3RD RESPONDENT.
Exhibit P15 TRUE COPY OF THE JUDGMENT DATED 12.2.2021 IN W.P.(C) NO.1895/2021 Exhibit P16 TRUE COPY OF THE COMMUNICATION DATED 8.3.2021 FORWARDED BY THE 3RD RESPONDENT TO THE 2ND RESPONDENT.
Exhibit P17 TRUE COPY OF THE COMMUNICATION DATED 31.5.2021 SENT BY THE 3RD RESPONDENT TO THE PETITIONER.
Exhibit P18 TRUE COPY OF THE MINUTES OF THE MEETING DATED 25/08/2021 CONVENED BY THE 2ND RESPONDENT.
SR
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!