Citation : 2021 Latest Caselaw 10491 Ker
Judgement Date : 29 March, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE BECHU KURIAN THOMAS
MONDAY, THE 29TH DAY OF MARCH 2021 / 8TH CHAITHRA, 1943
WP(C).No.25515 OF 2012(L)
PETITIONERS :
1 L.ARUNKUMAR,
RESIDING AT T.C.13/1365(1), SHALOM,
BURMA ROAD, KUMARAPURAM,
MEDICAL COLLEGE P.O.,
THIRUVANANTHAPURAM.
2 SUSEELA LAWRENCE,
RESIDING AT T.C.13/1365(1),
SHALOM, BURMA ROAD, KUMARAPURAM,
MEDICAL COLLEGE P.O., THIRUVANANTHAPURAM.
BY ADVS.
SRI.M.R.ANANDAKUTTAN
SMT.M.A.ZOHRA
RESPONDENTS :
1 THE CITY CORPORATION,
OF THIRUVANANTHAPURAM - 695 003
2 THE CITY CORPORATION OF THIRUVANANTHAPURAM,
REPRESENTED BY ITS SECRETARY - 695 003.
3 SURENDRAN,
SUBHAGAM, T.C.13/1364(1), BURMA ROAD,
KUMARAPURAM, THIRUVANANTHAPURM - 695 011.
R1 BY ADVS. SRI.P.K.MANOJKUMAR
SRI.P.V.ANIL
SRI.R.CHANDRAPRAVEEN
SRI.N.NANDAKUMARA MENON (SR).
R3 BY ADVS. SRI.A.RAJASIMHAN
SMT.P.USHAKUMARI
SC BY SRI.P.K.MANOJ KUMAR
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON
29.03.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C).No.25515 OF 2012(L)
2
JUDGMENT
Dated this the 29th day of March 2021
A work area having a size of 6.9 X 3.1 X 2 meters
along with a toilet having a size of 1.2 X 1.5 meters with a
concrete roofing was directed to be demolished by Ext.P6 order.
Ext.P6 was challenged by the writ petitioner before the Tribunal
for Local Self Government Department, but by the impugned
order dated 25.09.2012, produced as Ext.P8, the Tribunal
dismissed the appeal, thereby confirming Ext.P6 order of
demolition.
2. Adv.M.A.Zohra appearing for the writ petitioner
vehemently contends that the Tribunal went on a wrong tangent
in dismissing the appeal even after noticing the inspection report
contained in the files of the Corporation, mentioning that the
work area, the staircase and the toilet have been in existence
for years. In spite of such notings, according to the counsel, the
Tribunal wrongly confirmed the order directing demolition. The
learned counsel for the petitioner further pointed out that the
constructions now directed to be demolished have been in WP(C).No.25515 OF 2012(L)
existence for more than several decades and that the Tribunal
has committed an error in confirming the order of demolition.
3. The Standing Counsel for the Corporation
Sri.P.K.Manoj Kumar referring to the statement filed on behalf of
the Corporation submits that, based on the complaint filed by
the 3rd respondent, the Corporation initiated appropriate action
in accordance with law and after issuing a provisional order
under Section 406 of the Municipalities Act (the Act for short),
on 05.07.2011, the final order confirming the provisional order
was issued under Section 406(3) of the Act. It was submitted
that the procedure adopted by the Corporation was in
compliance with the statutory requirements and the same
warrants no interference.
4. Adv.A.Rajasimhan, the learned counsel for the 3 rd
respondent contends that the main house was constructed after
obtaining a building permit and was allotted the building
No.T.C.13/1365/1 in the name of the writ petitioner. Inviting my
attention to the findings of the Tribunal in Ext.P8 that, at the
time when the building plan was submitted and the completion WP(C).No.25515 OF 2012(L)
certificate obtained, the part of the buildings now referred to as
unauthorised constructions, was not shown either in the plan for
obtaining the building permit or for obtaining the completion
certificate and hence the same according to the counsel is
without doubt an unauthorised construction, constructed
certainly after completion of construction of the main building.
He sought for dismissal of the writ petition.
5. I have considered the rival contentions and have
perused the records produced along with the writ petition.
6. The jurisdiction of this Court to interfere with the
order of the Tribunal is limited, and is generally confined to
irregularity, perversity or irrationality in arriving at the
conclusion. This Court in exercise of the power of judicial review
is not concerned with the findings of fact on the basis of which
the orders are made so long as those findings are reasonable
and supported by evidence as held in Lieutenant General
Manomoy Ganguly v. Union of India & Others [(2018) 18
SCC 83].
7. The Tribunal had in arriving at the conclusion that WP(C).No.25515 OF 2012(L)
the order for demolition is only to be affirmed, perused the files
available with the Corporation. It had taken into reckoning the
notings in the inspection file as well as the other records relating
to the grant of building permit and the occupancy certificate.
After considering all the factual aspects in the case, the Tribunal
came to the conclusion that the order impugned before it is only
to be confirmed. I do not find any perversity or irregularity or
irrationality in the order of the Tribunal. The findings recorded
are reasonable and supported by valid reasons.
8. The contention of the learned counsel for the writ
petitioner by referring to the words "for years" noticed in the
inspection file of the Corporation, according to me, does not
advance the case of the writ petitioner since the word "for
years" is a very vague terminology capable of different
meanings, depending upon the context in which it is used. 2
years, 3 years, 5 years or 10 years could all be regarded as "for
years". It is in this context that when a question regarding
unauthorised construction is alleged, the burden falls upon the
owner of the building to disprove that it is not an unauthorised WP(C).No.25515 OF 2012(L)
construction or that the disputed building was constructed or
even before coming into force of the Building Rules. The burden
to prove the afore lies on the owner of the building.
9. The Tribunal has in fact considered even the said
aspects in the following words :
"11. Document No.5 produced by the appellants is the copy of the building plan, site plan and location plan together which were approved in 1996 and the building permit was granted. The proposed building and existing building No.T.C13/1365 are clearly shown in this site plan. It has not been stated in the site plan that annexing the existing T.C.13/1365 there is a work area on the rear side of the proposed construction or that there is a toilet on the western corner. Those constructions if were in existence in 1996 definitely would have been shown in this plan. The non-showing of the said work area and the toilet in this plan produced as document No.5 by the appellants only gives evidence that those buildings were not in existence as canvassed by the appellants at the time of the construction made in 1996. if so those buildings would have come in existence only after 1996, if such a view is permissible the burden is on the appellants to show when exactly those constructions were effected especially when they would admit the existence of those constructions".
"14. Of course there is an inspection report on page 1 of the note file wherein it is stated that the work area, the staircase and the toilet have been in existence "for years". But the site plan which I have already referred and the protographs would not permit me to accept the above version in the inspection report that these have been in existence "for years" and therefore from the said version what can be inferred is that these constructions cannot be treated as a recently made and WP(C).No.25515 OF 2012(L)
would have been made some 5 or 10 years ago. At any rate these constructions could be treated as effected after the coming in force of the Kerala Municipality Building rules 1999".
I am in complete agreement with the findings
rendered by the Tribunal in Ext.P8. As mentioned earlier, the
findings are reasonable and are supported by valid reasons.
There is no cause for interfering with the conclusion of the
Tribunal.
In the aforesaid circumstances, the writ petition is
only to be dismissed and accordingly the same is dismissed.
Sd/-
BECHU KURIAN THOMAS, JUDGE
RKM WP(C).No.25515 OF 2012(L)
APPENDIX PETITIONERS' EXHIBITS:
EXHIBIT P1 TRUE COPY OF THE GIFT DEED NO.OF PATTOM SUB REGISTRY DATED 30.03.1989
EXHIBIT P2 TRUE COPY OF THE PERMIT NO.BAPI/3290/96 OBTAINED FROM THE 1ST RESPONDENT DATED 16.5.1996
EXHIBIT P2A TRUE COPY OF THE PERMIT NO.BAPI/3290/96 DATED 16.5.1996 ISSUED BY TRIDA.
EXHIBIT P3 TRUE COPY OF THE APPROVED BUILDING PLAN.
EXHIBIT P4 TRUE COPY OF THE EXPLANATION DATED 23.7.2011.
EXHIBIT P5 TRUE COPY OF THE ADDITIONAL STATEMENT FILED BY THE 2ND PETITIONER DATED 21.12.2011.
EXHIBIT P6 TRUE COPY OF THE ORDER NO.E11/68779/11 DATED 21/2/2012 ISSUED BY THE 2ND RESPONDENT.
EXHIBIT P7 TRUE COPY OF THE APPEAL MEMORANDUM BEFORE THE HON'BLE TRIBUNAL FOR LOCAL SELF GOVERNMENT INSTITUTION, THRIUVANANTHAPURAM DATED 13.03.2012.
EXHIBIT P8 TRUE COPY OF THE ORDER IN APPEAL
NO.190/2012 OF THE TRIBUNAL DATED
25.09.2012.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!