Wednesday, 06, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Imperial Rngineering Company vs Technopark
2021 Latest Caselaw 15285 Ker

Citation : 2021 Latest Caselaw 15285 Ker
Judgement Date : 22 July, 2021

Kerala High Court
Imperial Rngineering Company vs Technopark on 22 July, 2021
             IN THE HIGH COURT OF KERALA AT ERNAKULAM
                              PRESENT
                THE HONOURABLE MR. JUSTICE T.R.RAVI
     THURSDAY, THE 22ND DAY OF JULY 2021 / 31ST ASHADHA, 1943
                      WP(C) NO. 2084 OF 2017
PETITIONER:

             IMPERIAL ENGINEERING COMPANY
             37/1634, IMPERIAL HOUSE, KALOOR-KATHRIKADAVU ROAD,
             COCHIN -682017, REPRESENTED BY ITS MANAGING
             PARTNER EASO JOHN.
             BY ADVS.
             SRI.M.A.ABDUL HAKHIM
             SRI.JAGAN ABRAHAM M.GEORGE


RESPONDENTS:

      1      TECHNOPARK
             PARK CENTRE, TECHNO PARK CAMPUS,
             THIRUVANANTHAPURAM-695 581, REPRESENTED BY ITS
             CHIEF EXECUTIVE OFFICER.
      2      CHIEF EXECUTIVE OFFICER
             TECHNO PARK, PARK CENTRE, TECHNO PARK CAMPUS,
             THIRUVANANTHAPURAM-695 581.
             BY ADV SMT.K.V.RASHMI, SC, TECHNOPARK




       THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION
ON    07.07.2021,   THE   COURT   ON    22.07.2021   DELIVERED   THE
FOLLOWING:
 WP(C) No.2084/2017                     2


                              JUDGMENT

(Dated this the 22nd day of July, 2021)

This writ petition is filed challenging Ext.P16 order, whereby

the petitioner has been blacklisted from participating in tenders

floated by the 1st respondent for a period of one year with effect

from 05.01.2017 and the EMD of Rs.50,000/- has been forfeited.

2. Heard Sri M.A.Abdul Hakhim on behalf of the petitioner

and Smt.K.V.Rashmi, Standing Counsel for respondents 1 and 2.

3. The petitioner, which is a registered firm, is involved in

undertaking electrical works from Governmental and semi-

Governmental institutions. The petitioner had undertaken the

electrical contract of the building named "Thejaswini" situated in

the 1st respondent Techno Park and the same was completed

during 2006-2009, as can be seen from Ext.P1. As part of

expansion, the respondents wanted to install two additional diesel

generators in the said building. The 2 nd respondent issued Ext.P6

dated 29.06.2016 inviting tenders for supply, installation, testing

and commission of two numbers of diesel generator sets and

modification of electrical panel, etc. Ext.P6 shows that the period

of completion was three months and earnest money deposit of

Rs.50,000/- was to be deposited and Rs.5,000/- plus tax at 5%

was to be deposited towards cost of tender documents. The last

date for submission of the e-tender was 20.07.2016. A pre-bid

meeting was scheduled on 05.07.2016 at Park Centre Building,

Technopark. The date of opening of the techno-commercial bid

was 25.07.2016 and the tenderers were expected to give a firm

period of 120 days for the tender from the date of opening of the

bid. The petitioner participated in the tender process. The

petitioner who submitted a bid for Rs.1,62,59,440/- was the

lowest tenderer. On 17.11.2016, the 1st respondent sent Ext.P9

mail to the petitioner, requesting them to submit an additional

bank guarantee for Rs.35,20,000/- (16% of Rs.2.2 crores) within

10 days to enable them to issue the work order. Respondents had

relied on clause 4.6 of the instructions to the tenderer. On

18.11.2016, the petitioner sent Ext.P10 reply stating that they

had already pointed out during discussions that rates were quoted

without taking into account the requirement for additional

performance guarantee. It was stated that since the notice

inviting tender did not specify the PAC, there was no way in which

they could have known whether the offer that they are making

was 25 % less than the PAC and that they would be liable to

provide an additional performance guarantee. On 28.11.2016 the

respondents wrote to the petitioner stating that they are yet to

receive a response regarding the submission of additional

performance guarantee for Rs.35,20,000/- and granting them 10

more days for submission of such guarantee. On 01.12.2016, the

petitioner informed that they had already sent a letter on

18.11.2016 explaining their position with regard to performance

guarantee. Thereafter the respondents issued Ext.P13, wherein

they informed the petitioner that the EMD for Rs.50,000/-

submitted along with the e-tender will be forfeited and further

action shall be taken regarding the tender, as per the procedure.

On 20.12.2016, the petitioners wrote Ext.P14 letter in reply to

Ext.P13 objecting to the decision to forfeit the EMD, pointing out

that clause 4.4 of tender conditions does not permit such an

action. It was also pointed out that the respondents had

intimated the PAC as Rs.2.2 Crores only in Ext.P9 e-mail and that

prior to the notice inviting tender and at the time of submitting

the tender, there was no way in which the petitioner could have

known the PAC. It was also pointed out that this vital information

regarding the tender was concealed, which is against the CPWD

norms. In Ext.P14, the petitioner had also made a suggestion

that since the major item of the tender is the DG set, they will

construct the necessary foundation and unload the DG set in the

site within 15-20 days thereby assuring that the major item is

already at site, which is a sufficient guarantee and that the

balance value of the work would only be Rs.69,84,580/-. It was

pointed out that such a course of action will assure a guaranteed

completion. It was again requested that if the above suggestion

was not agreeable, the EMD may be refunded. On 03.01.2017,

the respondents sent Ext.P15 letter to the petitioner stating that

even though the respondents had arranged a pre-bid meeting, the

petitioner failed to attend the same and if he had attended, he

could have sought clarification regarding the PAC even before the

submission of the bid. Thereafter, on 10.01.2017, the

respondents issued Ext.P16 to the petitioner, whereby the

petitioner was informed of the decision to forfeit the EMD and to

blacklist the petitioner from participating in the tenders floated by

the Technopark, for a period of one year with effect from

05.01.2017. The petitioner challenges Ext.P16 in this writ

petition.

4. The Standing Counsel for the respondents has filed a

statement wherein it is stated that the petitioner did not choose to

attend the pre-bid meeting and that it was his fault that he did not

seek any clarification regarding the PAC from the respondents. It

is stated that normally respondents do not specify the PAC, since

they want to get more competent rates and that no bidder has

asked any clarification regarding the PAC during the pre-bid

meeting. According to the respondents, the petitioner had quoted

the work at the rate of 26% below the estimated value and hence

under clause 4.6 of the tender conditions, the petitioner was

bound to provide additional performance guarantee. It is stated

that the additional performance guarantee is to ensure that a

person does not underquote the work and would ensure

completion of the work.

5. The petitioner has submitted a reply affidavit producing

Ext.P17 tender notice dated 18.01.2017, which was issued within

six months after Ext.P6 tender notice, in which the respondents

had specified the PAC. Exts.P7 and P8 issued during 2014 are

also instances where the respondents had specified the PAC in the

notice of tender. The petitioner has thereafter produced Ext.P18

along with I.A.No.1 of 2021, which is the copy of the notice

inviting tender for the very same work covered by Ext.P6. It can

be seen therefrom that the respondents had specified the PAC.

The respondents have produced Annexure R1(A) containing the

relevant pages of the conditions of tender, which was notified as

per Ext.P6. Reference is made to clauses 4.4 and 4.6, which are

extracted below, to justify the actions taken by the respondents.

4.4 EMD/SECURITY DEPOSIT/RETENTION MONEY

Earnest Money Deposit prescribed shall be remitted in line with the online payment feature stipulated. EMD of the unsuccessful tenderer will be refunded without any interest on finalisation of contract. E.M.D may be forfeited I. If a bidder withdraws his bid during the period of validity specified.

II. If the successful bidder fails within the time limit to sign the contract document or fails to furnish the required security deposit.

4.6 ADDITIONAL PERFORMANCE GUARANTEE

Additional performance guarantee will be required to be submitted by the successful contractor if the works are quoted between 11% to 25 % below the estimated rate. This additional performance guarantee shall be equal to the unbalanced price in the estimate PAC and quoted PAC. This will be released only after satisfactory completion of the work without any interest."

6. A Learned Single Judge of this Court in M/s

K.V.Joseph & Sons Private Ltd., Kochi and another vs

Principal Secretary to Government, Thiruvananthapuram

and others reported in 2017 KHC 170, considered the

requirement to provide additional performance guarantee. On the

facts of that case, the learned judge held that the bidder was

bound to provide additional performance security and that as long

as the grievance of the bidder was addressed, he cannot challenge

an action for not providing additional performance guarantee on

the ground of violation of any principles of natural justice. The

counsel for the petitioner pointed out that the facts on which the

above judgment was rendered are totally different from the facts

involved in the case on hand. It can be seen from paragraph 19 of

K.V.Joseph(supra) that there is a specific clause in the contract

between the parties, which provided that the failure to provide the

additional performance guarantee would result in forfeiture of the

EMD as well as an annulment of the award. It is pointed out that

there is no such clause available in the contract involved in this

case. It is further pointed out that in K.V.Joseph(supra), the

estimate PAC was known to the bidders and hence the bidders

knew whether the quoted PAC is falling between the range of 11%

and 25%, warranting the provision of additional performance

guarantee. Since the estimate PAC was not revealed in the tender

document, it is the contention of the Counsel that there is no

justification for either blacklisting the petitioner or for forfeiture of

EMD. A reading of the above judgment would clearly show that

many of the clauses which were available in the contract between

the parties, on an interpretation of which the judgment was

delivered, are not available in the contract involved in the case on

hand. I am hence of the opinion that the judgment in K.V.Joseph

(supra) cannot be applied to the facts of this case.

7. The counsel for the petitioner relied on the decision of

the Hon'ble Supreme Court in Suresh Kumar Wadhwa v. State

of M.P., reported in (2017) 16 SCC 757 and contended that a

forfeiture of the EMD could have been resorted to only if there is a

specific clause in the agreement between the parties, which

permitted the same. The Hon'ble Supreme Court has in the above

said judgment held that as per Section 74 of the Contract Act,

1872, if there is no stipulation in the contract for forfeiture, there

is no such right available to the party to forfeit the EMD. On the

question of publishing the material aspects relating to the

contract, the Hon'ble Supreme Court held in the above said

judgment that the object behind publishing all material terms is to

make the same known to the contracting parties/bidders, so that

they can be aware of their rights, obligations and liabilities qua

each other and also of the consequences in the event of their non-

compliances and also to empower the State to enforce any such

term against the bidder in the event of any breach committed by

the bidder and to bind the bidder to the express terms in the

contract/public notice. A similar view was taken by the Hon'ble

Supreme Court in the decision in Union of India v. Vertex

Broadcasting Co. (P) Ltd., reported in (2015) 16 SCC 198.

In the absence of disclosure of estimate PAC in the tender

document, the demand for additional performance guarantee

cannot hence bind the petitioner. The circumstances in which EMD

can be forfeited has been specified in clause 4.4 extracted above.

Failure to provide Additional performance guarantee is not a

reason stipulated in the said clause. Moreover, since the estimate

PAC was not revealed in the notice calling for tender, the

petitioner cannot be found fault with for not being aware that his

bid was 26 % below the estimate PAC. As such, there is no

justification whatsoever, to withhold the EMD provided by the

petitioner.

8. Coming to the question of blacklisting of the petitioner,

the Hon'ble Supreme Court has in Erusian Equipment &

Chemicals Ltd. v. State of W.B. Reported in (1975) 1 SCC

70 held that the blacklisting order involves civil consequences and

casts a slur and that it creates a barrier between the persons

blacklisted and the Government in the matter of transactions. It

was held that the blacklists are "instruments of coercion" and it

has the effect of preventing a person from the privilege and

advantage of entering into lawful relationship with the

Government for purposes of gains. The Hon'ble Supreme Court

held that fundamentals of fair play require that the person

concerned should be given an opportunity to represent his case

before he is put on the blacklist. In Patel Engg. Ltd. v. Union

of India, reported in (2012) 11 SCC 257, the Hon'ble Supreme

Court held that the authority of the State to blacklist a person is a

necessary concomitant to the executive power of the State to

carry on the trade or the business and making of contracts for any

purpose and that the only legal limitation upon the exercise of

such an authority is that the State is to act fairly and rationally

without in any way being arbitrary. The Hon'ble Supreme Court

further held that the bid document is not a statutory instrument

and that the failure to mention blacklisting to be one of the

probable actions that could be taken against the delinquent bidder

does not, by itself, disable the State from blacklisting a delinquent

bidder, if it is otherwise justified. However, Patel (supra) was a

case in which the person who was blacklisted was put on notice

and given an opportunity of hearing. Admittedly, in the case on

hand the petitioner was not put on notice regarding the

blacklisting nor was he heard. The period of blacklisting was for

one year. This Court had stayed the operation of the order of

blacklisting. The period for which the petitioner was blacklisted

has expired. It is fairly submitted by the counsel for the

respondents that the petitioner had been permitted to enter into

contracts with the respondents during the period when this writ

petition has been pending consideration of this Court. Even

though there is no consequence to follow after the passage of four

years, nevertheless, it has to be held that the blacklisting of the

petitioner without putting him on notice is bad in law. The

Standing Counsel for the respondents submitted that the

petitioner was granted sufficient time to comply with the

requirement to furnish additional performance guarantee. Since I

have already held that the demand for additional performance

guarantee cannot bind the petitioner, the fact of granting sufficient

time is not relevant.

In the result, the Writ petition is allowed. Exhibit P16

order issued by the Respondents is quashed. It is declared that

the blacklisting of the petitioner as per Exhibit P16 is not in

accordance with law. The Respondents were directed to release

the EMD which has been forfeited by the Respondents, within one

month from the receipt of a copy of the judgment. The parties

shall bear their respective costs.

Sd/-

T.R.RAVI, JUDGE.

dsn



                     APPENDIX OF WP(C) 2084/2017

PETITIONER EXHIBITS
EXT.P1                 A PHOTOSTAT COPY OF THE CERTIFICATE
                       ISSUED BY THE 1ST RESPONDENT IN FAVOUR OF
                       THE PETITIONER DATED 29.1.2014
EXT.P2                 A PHOTOSTAT COPY OF THE CERTIFICATE
                       ISSUED BY THE 1ST RESPONDENT IN FAVOUR OF
                       THE PETITIONER DATED 20.7.2016
EXT.P3                 A PHOTOSTAT COPY OF THE WORK ORDER ISSUED
                       BY THE 1ST RESPONDENT TO THE PETITIONER
                       DATED 2.1.2009
EXT.P4                 A PHOTOSTAT COPY OF THE WORK ORDER ISSUED
                       BY THE 1ST RESPONDENT TO THE PETITIONER
                       DATED 2.1.2009.
EXT.P5                 A PHOTOSTAT COPY OF THE LETTER ISSUED BY
                       THE 2ND RESPONDENT TO THE PETITIONER WITH
                       THE ANNEXED CERTIFICATE ISSUED BY THE
                       GREEN BUILDING COUNCIL DATED 04.11.2016
EXT.P6                 A PHOTOSTAT COPY OF THE NOTICE INVITING
                       TENDER ISSUED BY THE 2ND RESPONDENT DATED
                       29.6.2016
EXT.P7                 A PHOTOSTAT COPY OF THE NOTICE INVITING
                       TENDERS ISSUED BY KINFRA DATED NIL.
EXT.P8                 A PHOTOSTAT COPY OF THE NOTICE INVITING
                       TENDERS ISSUED BY KINFRA DATED NIL
EXT.P9                 A PHOTOSTAT COPY OF THE EMAIL SENT BY THE
                       1ST RESPONDENT TO THE PETITIONER DATED
                       17.11.2016
EXT.P10                A PHOTOSTAT COPY OF THE REPLY EMAIL SENT
                       BY THE PETITIONER TO THE 1ST RESPONDENT
                       DATED 18.11.2016
EXT.P11                A PHOTOSTAT COPY OF THE COMMUNICATION
                       SENT BY THE 1ST RESPONDENT TO THE
                       PETIITONER DATED 28.11.2016
EXT.P12                A PHOTOSTAT COPY OF THE REPLY EMAIL SENT
                       BY THE PETITIONER TO THE 1ST RESPONDENT
                       DATED 1.12.2016



EXT.P13              A PHOTOSTAT COPY OF THE COMMUNICATION
                     SENT BY THE 1ST RESPONDENT TO THE
                     PETITIONER DATED 15.12.2016
EXT.P14              A PHOTOSTAT COPY OF THE REPLY SENT BY THE
                     PETITIONER TO THE 1ST RESPONDENT DATED
                     20.12.2016
EXT.P15              A PHOTOSTAT COPY OF THE COMMUNICATION
                     SENT BY THE 1ST RESPONDENT TO THE
                     PETITIONER DATED 3.1.2017
EXT.P16              A PHOTOSTAT COPY OF THE ORDER PASSED BY
                     THE 2ND RESPONDENT DATED 10.1.2017
EXT.P17              TRUE COPY OF THE NOTICE INVITING TENDER
                     DATED 08.01.17


EXT.P18              TRUE COPY OF THE NOTICE INVITING TENDER
                     (NIT)DATED 20.03.17 ISSUED BY THE
                     RESPONDENT



RESPONDENTS' EXHIBITS
ANNEXURE R1(A)       TRUE COPY OF THE RELEVANT PAGES OF THE
                     TENDER CONDITIONS BEARING NO.TENDER
                     NO.ETPK/PH-1/2016-17/E-03 DATED NIL
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter