Wednesday, 06, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

T.T.Sunny vs The State Of Kerala Represented By
2021 Latest Caselaw 2734 Ker

Citation : 2021 Latest Caselaw 2734 Ker
Judgement Date : 25 January, 2021

Kerala High Court
T.T.Sunny vs The State Of Kerala Represented By on 25 January, 2021
               IN THE HIGH COURT OF KERALA AT ERNAKULAM

                               PRESENT

                 THE HONOURABLE MR.JUSTICE N.NAGARESH

       MONDAY, THE 25TH DAY OF JANUARY 2021/5TH MAGHA, 1942

                      WP(C).No.10192 OF 2017(Y)


PETITIONER:

               T.T.SUNNY, AGED 73 YEARS, S/O. THOMAS,
               P.W.D. CONTRACTOR, THANDAKKATTIL HOUSE,
               MEENANGADI P.O., WAYANAD - 673 591.

               BY ADV. SRI.GEORGE MECHERIL

RESPONDENTS:

      1        THE STATE OF KERALA REPRESENTED BY
               ITS SECRETARY TO GOVERNMENT,
               PUBLIC WORKS DEPARTMENT,
               SECRETARIAT,THIRUVANANTHAPURAM - 695 001.

      2        THE CHIEF ENGINEER,
               PWD ROADS DIVISIONS BRIDGES,
               THIRUVANANTHAPURAM - 695 001.

      3        THE SUPERINTENDING ENGINEER,
               P.W.D. ROADS AND BRIDGES,
               CENTRAL CIRCLE, ALUVA - 683 001.

               BY G.P. SMT. DEEPA NARAYANAN

     THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD       ON
25.01.2021,THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 WP(C)No.10192/2017

                                2




                          JUDGMENT

Dated this the 25th day of January, 2021

The petitioner executed Ext.P2 agreement for the

work 'Vision 2010-Construction of new bye pass road

starting from Thankalam Junction to Kozhippilly crossing

N.H.49 from ch.0/000 to 2/811'.

2. The petitioner states that he could not complete

the entire work due to reasons beyond his control and the

3rd respondent is liable to disburse balance bill amount in

respect of the work already completed by him.

3. From the pleadings it is evident that Ext.P2

agreement was executed on 01.01.2010 and the work had

to be completed within 18 months. `3,87,56,872/- was the

P.A.C. amount. It is stated that certain litigations arose

during the execution of the work and work had to be

stopped. The learned Government Pleader would submit WP(C)No.10192/2017

that the petitioner stopped the work on 26.07.2010.

4. For the work done by the petitioner, a part bill

was raised and the respondents have released

`62,54,155.24 which has been received by the petitioner.

The petitioner's case is that further amounts are due to him.

The petitioner submitted Ext.P12 representation requesting

to settle his bills and not to terminate contract till then. In

Ext.P12, the petitioner also expressed his readiness to

continue and complete the work.

5. From Ext.P7, it can be seen that a review

meeting was convened in respect of the work by the

Superintending Engineer, Aluva R & B and it was decided

to terminate the contract without invoking the 'risk and cost'

clause against the petitioner. It is also submitted by the

learned Government Pleader that the work has already

been re-tendered after issuing Ext.P15 Notice Inviting

Tender.

WP(C)No.10192/2017

6. The learned counsel for the petitioner would

argue that further amounts are due to him and if re-

tendered work is commenced without taking

measurements, the petitioner will be put to hardship and

loss. The learned Government Pleader on the other hand

would state that for the work completed by the petitioner,

amount of `62,54,155.24 has been paid to the petitioner

and no more amounts are due to him.

7. The dispute therefore is on a question of fact.

Whether the petitioner has completed the work for cost

exceeding `62,54,155.24 cannot be decided in this writ

petition under Article 226 of the Constitution of India.

In the circumstances, the writ petition is disposed of

permitting the petitioner to approach the 1st respondent with

a detailed representation. If the 1 st respondent receives

such a representation within a period of one month, the 1 st

respondent shall consider the claims of the petitioner

including his claim for refund of security deposit/bank WP(C)No.10192/2017

guarantee/performance guarantee and take a decision

thereon within a further period of three months.

Sd/-

N. NAGARESH JUDGE ncd WP(C)No.10192/2017

APPENDIX PETITIONER'S EXHIBITS:

EXHIBIT P1 A TRUE COPY OF THE SELECATION NOTICE WAS ISSUED TO THE PETITIONER ON 09.12.2009 BY THE 3RD RESPONDENT.

EXHIBIT P2 A TRUE COY OF THE ORDER NO. D.M.K-

3897/02 DATED 01.1.2010 OF THE 3RD RESPONDENT.`

EXHIBIT P3 A TRUE COPY OF THE LETTER DATED 30.8.2010 ADDRESSED TO THE 3RD RESPONDENT AND COPY OF THE EXECUTIVE ENGINEER, ASSISTANT EXECUTIVE ENGINEER AND THE ASSISTANT ENGINEER.

EXHIBIT P4 A TRUE COPY OF REQUEST DATED 15.1.2011 SUBMITTED BY THE PETITIONER BEFORE THE 3RD RESPONDENT.

EXHIBIT P5 A TRUE COPY OF THE REQUEST DATED 25.9.2012 SUBMITTED BYT HE PETITIONER BEFORE THE 3RD RESPONDENT.

EXHIBIT P6 A TRUE COPY OF THE COMMUNICATION NO.

CER&B/MVA/BW/8813/2009 DATED 31.10.2012 OF THE CHIEF ENGINEER TO 1ST RESPONDENT.

EXHIBIT P7 TRUE COPY OF THE MINUTES DATED 23.9.2010 REFERRED TO IN EXT.P6.

EXHIBIT P8 A TRUE COPY OF THE LAST REPRESENTATION DATED 11.1.2017 SUBMITTED TO THE PETITIONER BEFORE THE 3RD RESPONDENT.

EXHIBIT P9 A TRUE COPY OF THE INTERIM ORDER DATED 07.7.2014 IN WPC NO. 9929/2014 OF THIS HON'BLE COURT.

EXHIBIT P10 A TRUE COPY OF THE G.O. (RT) NO 1243/2019/ PWD DT.26.10.2019

EXHIBIT P11 A TRUE COPY OF THE LETTER NUMBER WP(C)No.10192/2017

A9/1136/2007 DT.19.12.2019

EXHIBIT P12 A TRUE COPY OF THE PETITION SUBMITTED TO THE GOVERNMENT

EXHIBIT P13 A TRUE COPY OF THE COMMUNICATION DATED 1.10.2020 OF THE THIRD RESPONDENT

EXHIBIT P14 TRUE COPY OF THE COMMUNICATION DATED 13/10/2020 ISSUED BY THE THIRD RESPONDENT.

RESPONDENTS' EXHIBITS

EXHIBIT R3(a) REQUISITION GIVEN TO LAND ACQUISITION OFFICER

EXHIBIT R3(b) TRUE COPY OF THE LETTER DATED 15.01.2011.

EXHIBIT R3(c) TRUE COPY OF THE LETTER DATED 25.03.2011.

EXHIBIT R3(d) TRUE COPY OF THE REPORT SUBMITTED BY THE 4TH RESPONDENT TO 3RD RESPONDENT

EXHIBIT R3(e) TRUE COPY OF THE LETTER DATED 10.06.2011.

EXHIBIT R3(f) TRUE COPY OF THE LETTER DATED 30.01.2012.

EXHIBIT R3(g) TRUE COPY OF THE LETTER DATED 23.02.2012.

EXHIBIT R3(h) TRUE COPY OF THE LETTER DATED 19.10.2012.

EXHIBIT R3(i) TRUE COPY OF THE LETTER DATED 04.06.20.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter