Wednesday, 15, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

K.Abdul Rehiman vs Kerala Police Housing And ...
2021 Latest Caselaw 20 Ker

Citation : 2021 Latest Caselaw 20 Ker
Judgement Date : 4 January, 2021

Kerala High Court
K.Abdul Rehiman vs Kerala Police Housing And ... on 4 January, 2021
         IN THE HIGH COURT OF KERALA AT ERNAKULAM

                           PRESENT

           THE HONOURABLE MR.JUSTICE N.NAGARESH

 MONDAY, THE 4TH DAY OF JANUARY 2021/14TH POUSHA, 1942

                  WP(C).No.14903 OF 2020(K)


PETITIONER:

              K.ABDUL REHIMAN,THOTTARIKIL PURAYIDOM,
              KALANJOOR P.O., PATHANAMTHITTA.

              BY ADVS.
              SRI.R.JAIKRISHNA
              KUM.NARAYANI HARIKRISHNAN

RESPONDENTS:

     1        KERALA POLICE HOUSING AND CONSTRUCTION
              CORPORATION LTD,CHANDRASEKHARAN NAIR
              STADIUM, PALAYAM, VIKAS BHAVAN P.O.,
              THIRUVANANTHAPURAM - 695 033,
              REPRESENTED BY ITS MANAGING DIRECTOR.

     2        CHIEF ENGINEER, KERALA POLICE HOUSING AND
              CONSTRUCTION CORPORATION LTD.,
              CHANDRASEKHARAN NAIR STADIUM,
              PALAYAM, VIKAS BHAVAN P.O.,
              THIRUVANANTHAPURAM -695 033.

     3        PROJECT ENGINEER, KERALA POLICE HOUSING AND
              CONSTRUCTION CORPORATION LTD.,
              OFFICE OF THE SUPERINTENDENT OF POLICE,
              NEAR RAILWAY STATION, KOLLAM H.P.O.,
              KOLLAM - 691 001.

              R1-R3 BY ADV. SRI.C.K.GOVINDAN
              R1-R3 BY ADV. SRI.L.P.ARAVINDAKSHAN

     THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY
HEARD ON 04-01-2021, THE COURT ON THE SAME DAY DELIVERED
THE FOLLOWING:
 WPC No.14903/2020
                                        :2:




                            N. NAGARESH, J.

           `````````````````````````````````````````````````````````````
                       W.P.(C) No.14903 of 2020

           `````````````````````````````````````````````````````````````
                Dated this the 4th day of January, 2021


                             JUDGMENT

~~~~~~~~~

Petitioner, a Class-B Contractor, has filed this writ

petition seeking to quash Ext.P12 revised estimate, Ext.P13

termination notice and Ext.P15 termination order and to

permit the petitioner to carry out the balance contract work of

construction of new Police Station at Sooranadu, Kollam

Rural (DSOR 2016 with new cost index).

2. The petitioner states that he is a Class-B

Contractor who has successfully undertaken and completed

various works of the 1st respondent-Kerala Police Housing

and Construction Corporation Limited, Local Self

Government Department (LSGD) and Public Works

Department (PWD). The petitioner participated in Ext.P1 WPC No.14903/2020

Notice Inviting Tender with respect to the work "Construction

of new Police Station at Sooranad, Kollam Rural (DSOR

2016 with new cost index)". The PAC for the tender was

₹93,87,277/-. The petitioner quoted 7.72% below the

estimate rate. The tender of the petitioner was accepted on

19.10.2019. Ext.P4 agreement was also executed on

21.11.2019.

3. However, the 1st respondent did not issue work

order immediately. Ext.P5 selection notice/work order was

issued on 14.01.2020. The work site was handed over to the

petitioner only on 15.01.2020. The time for completion of

work was 11 months from the date of handing over of the

site. Since the site was handed over on 15.01.2020, the time

for completion of work would expire only on 15.12.2020.

4. The petitioner states that on getting the site

handed over, the petitioner commenced the work and within

two months, by 13.03.2020, the petitioner had completed the

work of foundation, column and plinth beam. Completion of

such work was much in advance than the work schedule. WPC No.14903/2020

After completion of the work, the petitioner noticed certain

inadequacies in Ext.P3-BOQ as well as with respect to

plastering work. The earth work for filling the foundation was

fixed as 63.5430 m³. The said quantity was inadequate to fill

the foundation. At least 170 m³ of earth was required.

Similarly, plastering of the walls suggested by the 3rd

respondent would have led to cracks in the wall in future. The

petitioner suggested that roof and the pillars shall be

concreted along with the construction of the walls. The

petitioner made these suggestions as per Ext.P7 on

15.04.2020 to the 1st respondent.

5. After substantial completion of the work on

13.03.2020, Covid-19 pandemic broke out across India and

nationwide lock down was declared. The petitioner therefore

could not carry on with the work. However, on 25.05.2020,

the 3rd respondent-Project Engineer issued Ext.P8 letter

stating that the Government of Kerala has granted relaxation

and the petitioner has not still commenced the work. The

petitioner submitted Ext.P9 reply to Ext.P8 letter, on WPC No.14903/2020

05.06.2020, wherein the petitioner specifically pointed out the

progress of the work already achieved and that further work

can be carried out only on the respondents approving

sufficient quantities of earth for filling the foundation.

6. Without regard to Ext.P9, the 1 st respondent

issued Ext.P10 letter dated 08.06.2020 directing the

petitioner to restart the work urgently. Ext.P10 contained a

direction to the 3rd respondent to submit a revised estimate

for the work including required alteration/addition, if any, for

the satisfactory completion of work. However, there was no

reference in Ext.P10 as to the inadequacies pointed out by

the petitioner. The 3rd respondent thereupon issued Ext.P11

letter dated 11.06.2020 stating that all the inadequacies

highlighted by the petitioner were addressed in the revised

estimate and directed the petitioner to commence the work.

7. Exts.P10 and P11 referred to a "revised estimate".

The petitioner was kept in dark about the revision. On

enquiry, the petitioner was informed by the 3 rd respondent

that the BOQ was revised and the petitioner was required to WPC No.14903/2020

proceed the work as per the revised estimate. The petitioner

had not received any official communication in respect of the

revised estimate. The revised estimate was forwarded by the

3rd respondent to the petitioner by email only on 19.06.2020,

as per Ext.P12.

8. Ext.P12 revised estimate was without prior

concurrence of the petitioner. The petitioner had accepted

the tender based on Ext.P1 tender notice and Ext.P3-BOQ,

which was for a sum of ₹93,87,277/-. The revised estimate

of ₹1,26,78,519/- was not fixed with the concurrence of the

petitioner. To the surprise and predicament of the petitioner,

the 2nd respondent issued Ext.P13 termination notice on

17.06.2020 stating that the petitioner has failed to complete

the work within the time and failed to maintain the required

progress so as to complete the work in time.

9. The petitioner submitted Ext.P14 letter to the 1 st

respondent. In Ext.P14 also, the petitioner pointed out that

the revised estimate prepared by the respondents is

inadequate. The petitioner requested that he be given 12% WPC No.14903/2020

of the amount cut from the bill relating to the GST. The

petitioner also pointed out that deduction of ₹25,000/-

consequent to the alleged delay in work, is unsustainable.

The petitioner again pointed out the necessity to revise the

quantity of earth filling work. The petitioner requested the

respondents to permit him to continue and complete the

work.

10. The 2nd respondent, however, without adverting to

the contentions of the petitioner, issued Ext.P15 termination

order. Ext.P15 termination order dated 02.07.2020 was

communicated to the petitioner be by email on 13.07.2020.

The petitioner would submit that the hasty termination

proceedings initiated and concluded by the respondents are

with ulterior motives and malafide intentions.

11. The 1st respondent filed a counter affidavit in the

writ petition. The 1st respondent pointed out that stipulated

time of contract of work was 11 months from the date of

handing over the site. The site was handed over on

15.01.2020. There was a slight delay in settling part bill of the WPC No.14903/2020

petitioner due to technical issues. The petitioner as per his

letter dated 15.04.2020 informed that he has completed the

work up to plinth beam before the first lock down. The 3 rd

respondent has reported that as per the schedule, the

structure of the new Police Station, Sooranadu is to be

constructed as framed structure. But, the petitioner is

suggesting to construct the building as load-bearing

structure. The petitioner is responsible for the defects, if any,

occurred in the construction.

12. The 1st respondent further stated that by Ext.P10

letter dated 08.06.2020, the petitioner was required to

resume the work urgently as per the agreed plan. However,

the petitioner informed that it is not possible to restart the

work without getting permission for filling earth and has

requested to inform the decision urgently. A meeting was

arranged by the District Police Chief, Kollam Rural for

discussing the issue in the construction. The petitioner did

not attend the meeting or restart the work. Accordingly, the

termination notice was issued to the petitioner. WPC No.14903/2020

13. The 1st respondent further stated that structural

design of the work was prepared by an outside agency and

the same was approved by the Chief Engineer. Revised

estimates for the above work by incorporating the earth filling

and other additional items were already prepared. Since the

petitioner delayed execution of agreement, a penalty of

₹25,000/- was imposed. The Police Department had given

direction to complete the work before 14.12.2021 (sic). The

petitioner completed only 15% of the work. The lapses and

failure on the part of the petitioner to maintain the required

progress in the work was the reason for termination of the

contract.

14. I have heard the arguments raised by the counsel

for the petitioner and the arguments of the counsel for

respondents 1 to 3.

15. The work site was handed over to the petitioner

only on 15.01.2020. Therefore, the time for completion of

work will be up to 14.12.2020. There is no dispute as regards

the fact that the petitioner completed the work of foundation, WPC No.14903/2020

column and plinth beam within two months by 13.03.2020.

Even according to the counter affidavit filed by the 1 st

respondent, 15% work had been completed by the petitioner.

The nationwide lock down was declared across the country

soon thereafter.

16. On 15.04.2020, during the lock down period, the

petitioner sent Ext.P7 letter to the 1st respondent pointing out

that requisite quantity of earth filling has not been provided in

the schedule of work and sought changes in that regard.

According to the petitioner, he held a discussion with the

then Project Engineer and suggested that above the plinth,

brickwork and filler work should be done together before

concreting the top which would reduce the possibility of

appearing cracks in the construction. However, the new

Project Engineer did not accept the said suggestion and

directed to proceed with the pillar work and concreting the

top and to carry out brickwork subsequently. The petitioner

informed the 1st respondent as per Ext.P7 that if work is

carried out in that manner, there is a strong possibility of WPC No.14903/2020

cracks occurring and that the security period being five

years, the petitioner may not be able to secure the work for

five years.

17. Ext.P7 was submitted on 15.04.2020. On

25.05.2020, the Project Engineer, without referring to Ext.P7,

directed the petitioner to restart the work. Without getting

any approval for the larger quantum of earth filling work and

without getting further answer to the issues pointed out by

the petitioner as regards carrying out brickwork and pillar

work together, the petitioner could not have been expected to

restart the work. By Ext.P9 dated 05.06.2020, the petitioner

sent letter to the Project Engineer again reminding him that

no permission has been granted in respect of the filling work.

18. However, the 2nd respondent again issued Ext.P10

letter dated 08.06.2020, requiring the petitioner to restart the

work urgently. Though Ext.P10 letter of the 2 nd respondent

referred to Ext.P7 request made by the petitioner, no

decision in that regard was communicated to the petitioner in

Ext.P10.

WPC No.14903/2020

19. By by Ext.P11 letter dated 11.06.2020, the Project

Engineer informed the petitioner that he should construct the

structure as framed only. In between RCC and Masonary

joints Chicken Mesh were considered in Revised Estimate for

avoiding the cracks. The plinth filling earth quantity may

deviate and that also is considered in the revised estimate.

The petitioner would submit that Ext.P11 was the first

communication intimating about the revision of estimate.

Ext.P12 revised estimate was prepared without consulting

the petitioner.

20. A perusal of Clause 1.17 of Ext.P3 schedule and

the additional specification at serial No.16 of Ext.P12 would

show that the concern and requirement made by the

petitioner as regards earth filling work was genuine and the

respondents have increased the quantity of earth filling from

63.5430 m³ to 160.947 m³. The revised estimate was

communicated to the petitioner only on 19.06.2020. The

delay in executing the work from 13.03.2020 till Ext.P12

revised estimate was communicated on 19.06.2020, cannot WPC No.14903/2020

be attributed to the petitioner. However, it is seen that even

before Ext.P12 revised estimates was communicated to the

petitioner, the 2nd respondent issued Ext.P13 termination

notice holding that the petitioner has failed to maintain the

required progress in work. Going by the sequence of events

including the lock down consequent to pandemic and going

by the sequence of communications between the petitioner

and the respondents, this Court is of the definite opinion that

Ext.P13 termination notice issued to the petitioner even

before communicating Ext.P12 revised estimates, is highly

arbitrary and cannot be justified on any grounds.

21. The petitioner, however, offered to complete the

work in his Ext.P14 letter addressed to the 1 st respondent on

condition that the respondents release certain amounts

unnecessarily retained from his bill amounts. In this regard,

it is to be noted that an amount of ₹25,000/- was deducted

from the bill amount due to the petitioner. The reason for

deduction given in the counter affidavit is that as per the

agreement condition, the selected contractor shall execute WPC No.14903/2020

an agreement within a maximum period of 14 days from the

date of acceptance of the tender and fine at the rate of 1% of

contract amount subject to a minimum amount of ₹1,000/-

and a maximum of ₹25,000/- shall be levied if agreement is

not executed within 10 days after the notified period of 14

days.

22. In this regard, it has to be noted that a selection

notice/work order was issued to the petitioner as per Ext.P5

dated 14.01.2020. Paragraph 3 of Ext.P5 selection notice

required the petitioner to execute necessary agreements in

non-judicial stamp paper within 14 days of receipt of Ext.P5

letter. Paragraph 3 of Ext.P5 would show that the

respondents expected the petitioner to execute the

agreement within 14 days of issuance of selection

notice/work order. In fact, the petitioner had executed the

agreement on 20.11.2019 even before the issuance of

Ext.P5 selection notice/work order. In the circumstances, the

action of the respondents in deducting amounts from the

payment due to the petitioner for delayed execution of WPC No.14903/2020

agreement, cannot also stand the scrutiny of law.

23. All the above facts would show that the petitioner

was not provided with sanctions and help which are expected

to be provided by the 1 st respondent. The work could not

have been completed without there being a revision in the

quantum of earth filling work. The petitioner had pointed out

this fact as early on 15.04.2020, as per Ext.P7. The

respondents communicated to the petitioner about revision of

the quantum of earth filling work only on 19.06.2020 as per

Ext.P12. Ext.P12 would show that the requirements made by

the petitioner was genuine. However, the respondents sat

on the requirement till 19.06.2020. Even before

communicating the revised estimates, the 2nd respondent

issued Ext.P13 termination order on 17.06.2020. Exts.P13

and P15 therefore have to be held as highly arbitrary and

illegal.

24. In the circumstances, Exts.P13 and P15 orders

passed by the respondents are set aside. The respondents

ought to have arrived at revised estimates in consultation WPC No.14903/2020

with the petitioner. Ext.P12 revised estimate was drawn

unilaterally. Therefore, respondents 1 to 3 are directed to

reconsider Ext.P12 revised estimate in consultation with the

petitioner at the earliest and take decision afresh in that

manner. The petitioner shall be given reasonable time for

completion of work, if necessary after getting supplemental

agreements executed by the petitioner.

The writ petition is allowed as above.

Sd/-

N. NAGARESH, JUDGE aks/28.12.2020 WPC No.14903/2020

APPENDIX PETITIONER'S EXHIBITS:

EXHIBIT P1 TRUE COPY OF THE NOTICE INVITING TENDER ISSUED BY THE 1ST RESPONDENT.

EXHIBIT P2 TRUE COPY OF THE GENERAL TENDER CONDITION ISSUED BY THE 1ST RESPONDENT.

EXHIBIT P3 TRUE COPY OF THE BOQ OBTAINED FROM THE WEBSITE OF THE 1ST RESPONDENT.

EXHIBIT P4 TRUE COPY OF THE AGREEMENT ENTERED INTO BETWEEN THE PETITIONER AND THE 1ST RESPONDENT.

EXHIBIT P5 TRUE COPY OF THE SELECTION NOTICE/WORK ORDER ISSUED BY THE 1ST RESPONDENT TO THE PETITIONER.

EXHIBIT P6 TRUE COPY OF THE PROGRESS CHART PREPARED BY THE PETITIONER.

EXHIBIT P7 TRUE COPY OF THE LETTER ISSUED BY THE PETITIONER TO THE 1ST RESPONDENT.

EXHIBIT P8 TRUE COPY OF THE LETTER ISSUED BY THE 3RD RESPONDENT TO THE PETITIONER.

EXHIBIT P9 TRUE COPY OF THE REPLY GIVEN BY THE PETITIONER TO THE 3RD RESPONDENT.

EXHIBIT P10 TRUE COPY OF THE LETTER ISSUED BY THE 1ST RESPONDENT TO THE PETITIONER.

EXHIBIT P11 TRUE COPY OF THE LETTER ISSUED BY THE 3RD RESPONDENT TO THE PETITIONER.

EXHIBIT P12 TRUE COPY OF THE REVISED ESTIMATE SENT BY THE 3RD RESPONDENT TO THE PETITIONER.

 WPC No.14903/2020



EXHIBIT P13     TRUE COPY OF         THE   TERMINATION NOTICE
                ISSUED BY THE        2ND   RESPONDENT TO THE
                PETITIONER.

EXHIBIT P14     TRUE COPY OF THE REPRESENTATION SUBMITTED
                BY   THE   PETITIONER  BEFORE   THE   1ST
                RESPONDENT.

EXHIBIT P15     TRUE COPY OF THE TERMINATION ORDER ISSUED
                BY THE 2ND RESPONDENT TO THE PETITIONER.

EXHIBIT P16     TRUE COPY OF        THE E-MAIL    COMMUNICATION
                SENT BY THE          PETITIONER   TO THE 3RD
                RESPONDENT.
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter