Citation : 2021 Latest Caselaw 6907 Ker
Judgement Date : 26 February, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE SHAJI P.CHALY
FRIDAY, THE 26TH DAY OF FEBRUARY 2021 / 7TH PHALGUNA, 1942
Con.Case(C).No.1104 OF 2019 IN WP(C). 3526/2019
AGAINST THEJUDGMENT IN WP(C) 3526/2019(M) OF HIGH COURT OF KERALA
PETITIONER:
MUTHUPANDI
AGED 59 YEARS
S/O KASHIPANDI THEVAR, KUNNEL HOUSE, PULLIKKANAM P.O
PUTHUKADU DIV. IDUKKI DISTRICT
BY ADV. SRI.K.R.SUNIL
RESPONDENTS:
JAFAR KHAN
FATHER'S NAME AND AGE NO KNOWN, EXECUTIVE ENGINEER,
PUBLIC WORKS DEPARTMENT (ROAD DIVISION),
IDUKKI - 685 602
BY SENIOR GOVERNMENT PLEADER SRI.SURIN GEORGE IPE
THIS CONTEMPT OF COURT CASE (CIVIL) HAVING COME UP FOR
ADMISSION ON 26.02.2021, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
Con.Case(C).No.1104 OF 2019 2
IN WP(C). 3526/2019
JUDGMENT
Dated this the 26th day of February 2021
This contempt case is filed complaining that the directives
contained in the judgment dated 22.3.2019 in W.P.(C) No.3526/2019 are
not complied with. The directions issued by this Court reads thus:
"4. Learned Counsel for the petitioner submitted that situation
would suffice if a direction is issued WP(C).No. 3526 of 2019 3 to
complete the work as is stated in the statement.
5. Having heard learned Counsel for the petitioner as well as
learned Government Pleader this writ petition is disposed of,
recording that the Government have already taken steps to complete
the construction activities on or before 31.05.2019 and there will be a
direction accordingly. The writ petition is disposed of, accordingly."
2. Today when the matter is taken up, learned Senior Government
Pleader has produced a statement filed in the contempt petition. Paragraph 3
of the said statement would be worthwhile to record in order to understand
the actual factual situation and to avoid any complexity in the future, which is
extracted hereunder:
IN WP(C). 3526/2019
"3. The administrative sanction have accorded for Rs.1,05,00,000/-
for 4 works at Kanjar - Pullikkanam Road and administrative sanction
was accorded for Rs.1,70,00,000/- for 7 works at Moolamattom -
Pullikkanam road and all the works were completed. The details of the
said works are as follows:
Kanjar- Pullikkana road
1. 2019-20 Providing 20 mm bit CC in Kanjar-Pullikkanam Road Ch.15/550 to 16/600 (AS- Rs.25,00,000/-) The work is completed.
2. 2019-20 Providing 20mm bit CC in Kanjar-Pullikkanam road.Ch.16/650 to 17/700 (AS-Rs.25,00,000/-) The work is completed.
3. 2019-20 Providing 20mm bit CC in Kanjar- Pullikkanam road Ch.14/450 to 15/500 (AS- Rs.25,00,000/-) The work is completed.
4. B/W 2017-18 Improvements to Kanjar-Pullikkanam road Ch.00/000 to 03/000(Kanjar-Koovappilly Road (AS-Rs,30,00,000/-) The work is completed.
5. In addition to this some portions of the road is damaged as only bit Chipping Carpet done in the previous year. Hence additional works were arranged in the damaged portions as;
1) 20mm Bit CC to Kanjar- Pulllikkanam road between Ch.09/200 to 11/400.
2). 20mm Bit CC to Kanjar - Pullikkanam road between Ch.04/500 to 06/700.
Tendering process of these two works are in progress.
IN WP(C). 3526/2019
4. Moolamattom-Pullikkanam Road
1. 2018-19 Urgent Maintenance and patch repairs to Moolamattom - Pullikkanam Road Km 4,000 to 6/000 (AS -Rs.20,00,000/-) The work is completed.
2. 2019-20 Providing 20mm bit CC in Moolamattom -Pullikkanam Road Ch.12/000 to 14/200(AS-Rs.20,00,000/-) The work is completed.
3. 2019-20 Providing 20mm bit CC in Moolamattom -Pullikkanam Road Ch.14/300 to 15/458 (AS-Rs.20,00,000/-) The work is completed
4. 2019-20 Providing 20mm bit CC in Moolamattom-Pullikkanam Road Ch.06/000 to 08/500 (AS- Rs. 25,00,000/-). The work is completed.
5. 2019-20 Proving 20mm bit CC in Moolamattom- Pullikkanam road Ch. 10/000 to 11/100 (AS -Rs. 25,00,000/-). The work is completed.
6. B/W 2018-19 Improvements to Manappady- Elappilly- Edadu Road (Mollamattom- Pullikkanam road Km 01/800 to 3/500) (ASRs.30,00,000/-) . The work is completed.
Now the road is fully traffic worthy. As some minor repairs are required for 1.5 Km. Of this road between Ch.10/000 to 12/000, one work is arranged in this chainage."
3. It is also clear from the statement that what remains to be
completed is only 1.5 Kms of road between ch.10/0000 to 12/000 and
according to the learned Senior Government Pleader, every effort is made
by the respondent to complete the road in that extent also.
4. In that view of the matter, I am of the considered opinion that
substantially the judgment rendered by this Court was complied with and
IN WP(C). 3526/2019
two major roads were completed by the respondent and what remains to
be completed is only 1.5 Kms road. Therefore, the contempt petition is
closed, however, I observe that all steps shall be taken to finalaise the
completion of the road in regard to 1.5 Kms.
Sd/-
SHAJI P.CHALY
smv JUDGE
IN WP(C). 3526/2019
APPENDIX
PETITIONER'S ANNEUXRES:
ANNEXURE THE CERTIFIED COPY OF THE JUDGMENT OF
THIS HON'BLE COURT DATED 22.03.2019
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!