Citation : 2021 Latest Caselaw 6822 Ker
Judgement Date : 26 February, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE SMT. JUSTICE P.V.ASHA
FRIDAY, THE 26TH DAY OF FEBRUARY 2021 / 7TH PHALGUNA, 1942
WP(C).No.1190 OF 2021(W)
PETITIONER:
J. ABDUL VAHID,
AGED 59 YEARS
S/O. JAMALUDEEN KUNJU, E. J . CONSTRUCTIONS,
KURUNDANTAYYATHU HOUSE, KADATHOOR P. O., THAZHAVA,
KOLLAM.
BY ADVS.
SRI.R.SUNIL KUMAR
SMT.A.SALINI LAL
SHRI.ARUN KRISHNA
RESPONDENTS:
1 THE MANAGING DIRECTOR
KERALA STATE TRANSPORT CORPORATION, TRANSPORT BHAVAN,
FORT, THIRUVANANTHAPURAM - 695023.
2 THE CHIEF ENGINEER (P AND CW)
KERALA STATE TRANSPORT CORPORATION, TRANSPORT BHAVAN,
FORT, THIRUVANANTHAPURAM - 695023.
3 THE EXECUTIVE ENGINEER
KERALA STATE TRANSPORT CORPORATION, TRANSPORT BHAVAN,
FORT, THIRUVANANTHAPURAM - 695023.
4 THE ASSISTANT ENGINEER
KERALA STATE TRANSPORT CORPORATION OFFICE, ERNAKULAM
- 682011.
5 DIVISIONAL ACCOUNTS OFFICER
KERALA STATE TRANSPORT CORPORATION, TRANSPORT BHAVAN,
FORT, THIRUVANANTHAPURAM - 695023.
R1-5 BY ADV. SRI.P.C.CHACKO(PARATHANAM)
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
26.02.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C).No.1190 OF 2021(W)
2
JUDGMENT
Dated this the 26th day of February 2021
The writ petition is filed seeking the
following reliefs:-
"i) To issue a writ of mandamus or any other appropriate writ, order or direction directing the respondents to pay an amount of Rs.22,030,771/- with interest at the rate of 12% forthwith.
ii) Pass such other orders as this Hon'ble court deems fit and proper in the facts and circumstances of the case."
2. On the basis of notice inviting tender,
the petitioner had submitted e-tender on
26.09.2014 and 24.11.2014. Based on Ext.P1
selection notice issued on 09.01.2015, the
petitioner executed Ext.P2 agreement on 25.06.2015
and carried out the construction of KSRTC bus
terminal cum shopping complex at Haripad. The
petitioner submits that the work was completed on
29.09.2018 and payment towards the final bill was
made on 18.05.2020. According to the petitioner WP(C).No.1190 OF 2021(W)
the defect liability period as per Ext.P2
agreement is only one year and therefore, the
petitioner is entitled to refund of the security
amount.
3. The writ petition is filed seeking a
direction to make the paymentof a sum of
Rs.2,20,30,771/- which according to the petitioner
is the balance amount.
4. The respondents have filed a counter
affidavit stating that, as per Ext.R1(a) letter,
the KSRTC has addressed the Deputy General
Manager, HLL Life Care Limited for assessment of
structural stability and quality of the
constructions under KSRTC. Serial No.1 in the said
letter relates to the work carried out by the
petitioner. It is stated that as per Ext.R1(b)
letter, the Government has agreed that Central
PSUs ie, M/s.HLL Life Care Limited and M/s.
Hindustan Pre Fab Limited shall be the project
management consultant for existing and future work
of KSRTC.
WP(C).No.1190 OF 2021(W)
5. The contention of the learned counsel for
the petitioner is that Ext.R1(b) letter can not
relate to the work of the petitioner as the said
work was already completed well before 19.10.2020.
6. Even though, the petitioner has, in
paragraph No.5 of the writ petition stated that
the defect liability period in respect of the work
under taken by the petitioner is over as it was
completed on 29.09.2018, the counter affidavit
filed by the respondents does not dispute the
same. They have only stated that the payment can
be made only after evaluation of structural
stability by the project management consultant.
As the petitioner's contention remains undisputed
with respect to the date of completion of the work
as well as with respect to the defect liability
period, the respondents can not delay further
payment due to the petitioner, awaiting the report
from the Project consultant, for which steps are
taken in the year 2020 and consent is given by
government on 06.11.2020 in Ext.R1(b) letter. As WP(C).No.1190 OF 2021(W)
rightly contended by the learned Counsel for the
petitioner, a work which was completed in 2018,
can not be said to be a work which was existing as
on 06.11.2020 when Ext R1(b) letter was issued or
as on 19.10.2020, when Ext.R1(a)letter was issued
or because the respondents included the work
carried out by the petitioner in Ext R1(a)
letter.
7. As the learned Counsel for the
respondents submitted that KSRTC is facing serious
financial crunch, there shall be a direction to
the respondents to see that the balance payment
due to the petitioner under various heads is made
within a period of six months, provided 50% of the
same is paid within three months.
The writ petition is disposed of accordingly.
Sd/-
P.V.ASHA JUDGE DM WP(C).No.1190 OF 2021(W)
APPENDIX PETITIONER'S EXHIBITS:
EXHIBIT P1 COPY OF THE LETTER ISSUED BY THE 2ND RESPONDENT DATED 9.1.2015.
EXHIBIT P2 COPY OF THE AGREEMENT DATED 25.06.2015 BETWEEN PETITIONER AND 2ND RESPONDENT.
EXHIBIT P3 COPY OF THE LETTER RECEIVED UNDER THE RIGHT TO INFORMATION ACT DATED 01.12.2020.
EXHIBIT P4 COPY OF THE FINAL BILL ISSUED BY THE RESPONDENTS TO THE PETITIONER WITH BILL NO.6/19.
EXHIBIT P5 COPY OF THE REVENUE RECOVERY NOTICE DATED 6.1.21 ISSUED BY THE KFC TO THE PETITIONER.
RESPONDENTS' EXHIBITS:
EXHIBIT R1(a) TRUE COPY OF THE ORDER DATED 19.10.2020 ISSUED BY THE 1ST RESPONDENT.
EXHIBIT R1(b) TRUE COPY OF THE ORDER DATED 06.11.2020 ISSUED BY THE GOVERNMENT OF KERALA.
//TRUE COPY//
PA TO JUDGE
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!