Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

V.Govindankutty vs The Southern Railway
2021 Latest Caselaw 6808 Ker

Citation : 2021 Latest Caselaw 6808 Ker
Judgement Date : 26 February, 2021

Kerala High Court
V.Govindankutty vs The Southern Railway on 26 February, 2021
                IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                PRESENT

                  THE HONOURABLE MR.JUSTICE N.NAGARESH

        FRIDAY, THE 26TH DAY OF FEBRUARY 2021/7TH PHALGUNA, 1942

                       WP(C).No.18640 OF 2019(D)


PETITIONERS:

               V.GOVINDANKUTTY, S/O.RAMAN NAIR,
               AGED 69 YEARS, GOVERNMENT CONTRACTOR,
               VELLAMKANDATH HOUSE, ENKAKAD P.O.,
               THRISSUR DISTRICT - 680 589.

               BY ADV. SRI.BINOY VASUDEVAN

RESPONDENTS:

         1     THE SOUTHERN RAILWAY,
               REPRESENTED BY ITS GENERAL MANAGER,
               SOUTHERN RAILWAY HEADQUARTERS,
               CHENNAI - 600 003.

         2     THE CHIEF ENGINEER, CONSTRUCTION,
               SOUTHERN RAILWAY, ERNAKULAM - 682 016.

         3     THE DEPUTY CHIEF ENGINEER, CONSTRUCTION,
               SOUTHERN RAILWAY, ERNAKULAM - 682 016.

ADDL.    4     THE PRINCIPAL SECRETARY TO THE GOVERNMENT,
               PUBLIC WORKS DEPARTMENT, GOVERNMENT SECRETARIAT,
               THIRUVANANTHAPURAM- 695 001.

ADDL.    5     THE CHIEF ENGINEER, PWD/ROADS AND BRIDGES,
               THIRUVANANTHAPURAM-695 033.

               ADDITIONAL R4 AND R5 ARE IMPLEADED AS PER ORDER DATED
               26.11.2019 IN IA NO.1/2019.

               R1-R3 BY SRI.N.K.SUBRAMANIAN, SC, RAILWAYS
               R4-R5 BY GOVERNMENT PLEADER SMT. DEEPA NARAYANAN

     THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD          ON
26.02.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 WP(C)No.18640/2019

                                     2




                              JUDGMENT

Dated this the 26th day of February, 2021

The petitioner, a Government Contractor, has

approached this Court seeking to command respondents 1

to 3 to release the final bill payable to the petitioner as

approved in Ext.P4 along with the security deposit payable

to the petitioner pursuant to the subject matter contract as

expeditiously as possible.

2. The petitioner states that he executed an

agreement with the 3rd respondent-Deputy Chief Engineer,

Construction, Southern Railway, for construction of a

Railway Over Bridge at Wadakkancherry. It was a deposit

work entrusted by the Public Works Department,

Government of Kerala. According to the petitioner, the

delay in disbursal of requisite amount by the PWD resulted

in delay in completion of the work.

WP(C)No.18640/2019

3. The petitioner would contend that it is an

admitted fact that there was no default on the part of the

petitioner to complete the work. However, the agreement

with the petitioner was foreclosed by respondents 1 to 3 and

the remaining work was later awarded to another

Contractor. The amount due to the petitioner for the work

he has completed, has not been paid so far.

4. The learned Standing Counsel for respondents 1

to 3 would state that this was a deposit work undertaken on

behalf of the Public Works Department. There were

material deviations from the original proposal. For

executing the work, the amount under sanction has been

exceeded and hence a revised completion estimate was

sent to PWD. However, PWD did not reply to the proposal.

Therefore, the Railway is unable to process the bill of the

petitioner and to close the file.

5. The learned Standing Counsel for respondents 1

to 3 pointed out that in the original contract it is clearly WP(C)No.18640/2019

mentioned that any deviation from the original estimate shall

be accepted by the Depositing Authority and hence the

responsibility to clear the completion estimate is also with

the Depositing Authority. But unfortunately, PWD has not

taken any steps even after giving completion estimate.

6. The learned Government Pleader on the other

hand submitted that the construction work was deposited for

an amount of `2,42,23,000/- as per sanctioned estimate.

The work was completed in the year 2012 and the ROB was

opened to public. Till 25.07.2019, no extra claim was made

by the Railway. On 25.07.2019, the Deputy Chief Engineer

II/Construction, Ernakulam intimated the additional 4th

respondent that the completion estimate was drawn for a

value of `3,31,84,476/- against the already approved

sanctioned estimate value of `2,42,22,729/- and an amount

of `91,86,819/- has been included towards anticipated

further outlay. This is evident from Ext.R4(a) of the 3 rd

respondent. In Ext.R4(a), the 3rd respondent stated that an WP(C)No.18640/2019

amount of `2,42,23,000/- had been deposited by the PWD

for the work and based on completion report, a balance

amount of `89,61,475/- has to be deposited to Railway for

closing the account. The 3rd respondent has also stated that

an amount of `10,87,191/- is pending to be paid to the

petitioner.

7. I have heard the learned counsel for the

petitioner, learned Standing Counsel for respondents 1 to 3

and the learned Government Pleader appearing for

additional respondents 4 and 5.

8. The work of construction of ROB was a deposit

work entrusted by the PWD to respondents 1 to 3.

Therefore respondents 4 and 5 are bound to honour any

demand made by respondents 1 to 3 in accordance with the

contract entered into between them on completion of work.

Additional respondents 4 and 5 would submit that such

payment is not contemplated under the terms of the

agreement and additional respondents are not bound to pay WP(C)No.18640/2019

the amount which was belatedly made.

9. Respondents 1 to 3 do not dispute the

completion of the work by the petitioner, for which bills have

been raised. The defence of respondents 1 to 3 is that this

being a deposit work, without receiving the amount from

respondents 4 and 5, payment cannot be made to the

petitioner.

10. This Court finds that the said statement made by

respondents 1 to 3 cannot stand the scrutiny of law. As long

as agreement between the petitioner and respondents 1 to

3 does not state that the amounts will be paid to the

petitioner only as and when additional respondents 4 and 5

provide funds for the deposit work, respondents 1 to 3

cannot deny amount legitimately due to the petitioner. The

dispute between respondents 1 to 3 on the one part and

additional respondents 4 and 5 on the other part, cannot be

a justifiable reason for respondents 1 to 3 for non-payment

of dues to the petitioner.

WP(C)No.18640/2019

In the circumstances, the writ petition is allowed and

respondents 1 to 3 are directed to make the payment of the

admitted outstanding dues to the petitioner within a period

of three months. It is made clear that this judgment shall

not in any manner be treated as deciding any issues

between respondents 1 to 3 and additional respondents 4

and 5, in respect of the agreement between them.

Sd/-

N. NAGARESH JUDGE ncd/26.02.2021 WP(C)No.18640/2019

APPENDIX PETITIONERS' EXHIBITS:

EXHIBIT P1 TRUE COPY OF THE AGREEMENT EXECUTED BY THE PETITIONER WITH THE RESPONDENT.

EXHIBIT P2 TRUE COPY OF THE REQUEST SUBMITTED BY THE PETITIONER BEFORE THE 2ND RESPONDENT DATED 25/01/2017.

EXHIBIT P3 TRUE COPY OF THE REQUEST SUBMITTED BY THE PETITIONER BEFORE THE 2ND RESPONDENT DATED 01/03/2018.

EXHIBIT P4 TRUE COPY OF THE FINAL BILL EXECUTED BY THE 3RD RESPONDENT.

EXHIBIT P5 TRUE COPY OF THE RIDER AGREEMENT DATED 27/12/2018 EXECUTED BY THE PETITIONER WITH THE 3RD RESPONDENT.

EXHIBIT P6 TRUE COPY OF THE REMINDER SUBMITTED BY THE PETITIONER BEFORE THE 3RD RESPONDENT ON 24/05/2019.

RESPONDENTS' EXHIBITS:

EXHIBIT R3(a) COPY OF LETTER DATED 26.7.2019 ISSUED BY 3RD RESPONDENT TO THE PETITIONER.

EXHIBIT R3(b)        COPY OF LETTER DATED 25.7.2019 ISSUED
                     BY   3RD   RESPONDENT    TO   THE  CHIEF
                     ENGINEER, PUBLIC WORKS DEPARTMENT.
EXHIBIT R4(a)        TRUE    COPY   OF    THE    LETTER   NO.
                     148/CN/MVPA/25 DATED 25.7.2019.
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter