Citation : 2021 Latest Caselaw 6543 Ker
Judgement Date : 24 February, 2021
W.A. No. 386/2021 :1:
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE THE CHIEF JUSTICE MR.S.MANIKUMAR
&
THE HONOURABLE MR. JUSTICE SHAJI P.CHALY
WEDNESDAY, THE 24TH DAY OF FEBRUARY 2021 / 5TH PHALGUNA, 1942
WA.No.386 OF 2021
AGAINST THE JUDGMENT DATED 17.02.2021 IN WP(C) 24907/2020(K) OF HIGH
COURT OF KERALA
APPELLANT/PETITIONER IN W.P.(C):
M/S. ALECTRONA ENERGY PVT LTD.,
REPRESENTED BY ITS MANAGING DIRECTOR,
MR. ROHIT RABINDERNATH, S/O. LATE MR. RABINDERNATH,
AGED 42 YEARS HAVING ITS REGISTERED OFFICE
AT 3RD FLOOR, BLOCK A, BANNARI AMMAN TOWERS, NO.29,
DR. RADHAKRISHNAN ROAD, MYLAPORE, CHENNAI - 600 004.
BY ADVS.
SRI.M.R.HARIRAJ
SMT.THANUJA ROSHAN
SHRI.VISWAJITH C.K
SMT.GANGA A.SANKAR
SHRI.CHACKOCHEN VITHAYATHIL
SMT.GISHA G. RAJ
SHRI.REJIVUE
SRI.AKHIL BHANSALI
RESPONDENTS/RESPONDENTS IN W.P.(C):
1. KERALA STATE ELECTRICITY BOARD LTD.,
A GOVT. OF KERALA UNDERTAKING, REPRESENTED BY ITS CHIEF
ENGINEER, 9TH FLOOR VYDYUTHI BHAVANAM, PATTOM,
THIRUVANANTHAPURAM - 695 001.
2 STATE OF KERALA, REPRESENTED BY THE SECRETARY TO
GOVERNMENT OF KERALA, DEPARTMENT OF ELECTRICITY,
THIRUVANANTHAPURAM - 695 001.
3 DCB BANK LTD., HAVING ITS CENTRAL OFFICE AT 601 & 602,
PENINSULA BUSINESS PARK, 6TH FLOOR, TOWER A, SENAPATHI
W.A. No. 386/2021 :2:
BAPAT MARG, LOWER PAREL, MUMBAI - 400 013, REPRESENTED
BY ITS MANAGER, NUNGAMBAKKAM BRANCH
R1 BY SRI.SUDHEER GANESH KUMAR, SC FOR R1,
R2 BY SRI. ARAVIND KUMAR BABU, SR. GOVERNMENT PLEADER
THIS WRIT APPEAL HAVING COME UP FOR ADMISSION ON 24.02.2021, THE
COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
W.A. No. 386/2021 :3:
Dated this the 24th day of February, 2021.
JUDGMENT
SHAJI P. CHALY, J.
The above appeal is preferred by the petitioner in W.P.(C) No.
24907 of 2020, whereby the following relief sought for by the
appellant was declined.
"To issue a writ of certiorari or mandamus or any other appropriate writ
or order or direction to call for the records of the first respondent culminated in Ext. P19 and to quash the same and to direct the respondent to allow the petitioner to complete the execution of the agreement."
2. Brief material facts for the disposal of the appeal are as
follows:
The appellant is a company registered under the Indian
Companies Act engaged in the manufacturing and installation of the
solar photo-voltaic modules, electronic controls, solar inverters and
solar water pumps. The appellant was awarded with a tender by the
Kerala State Electricity Board for the erection of a 1.0 MW solar power
plant at Mylatty, Kasargod District and issued with Ext. P2 work order
on 07.12.2017. The main grievance highlighted by the appellant was in
regard to Ext. P19 order of the KSEB Limited dated 12.11.2020,
whereby the bank guarantee offered by the appellant amounting to Rs
58,20,000/- was sought to be invoked and directed the Bank to credit
the amount to the accounts of the Secretary, KSEB Limited, since the
work was allegedly delayed, in spite of extension of time on several
occasions .
3. The case projected by the appellant was that there were
certain issues relating to the tax structure and its implications on the
price and the said issue delayed the execution of the agreement.
Anyhow, as per Ext. P3 agreement dated 01.03.2018 executed by and
between the parties, the terms and conditions were agreed upon.
According to the appellant, there was no delay or laches on the part of
the appellant in the execution of the agreement, though Ext. P2 work
order was issued on 07.12.2017.
4. The sum and substance of the contentions advanced by the
appellant was that the KSEB Ltd. was not legally right in revoking the
bank guarantee, since there is no breach of contract on the part of the
appellant and further that the bank guarantee offered by the appellant
was against the guarantee of the work executed and therefore, there
was no power vested with the authorities on the basis of the
agreement executed, to invoke the bank guarantee for delay of work
as alleged .
5. The KSEB Ltd. has filed a detailed counter affidavit disputing
the allegations raised by the appellant and justifying the stand adopted
by it in regard to the bank guarantee. The KSEB has also produced
Ext. R1A Performance Bank Guarantee executed by and between the
parties to substantiate that whenever there was violation of the
agreement conditions and the work order, the KSEB was entitled to
invoke the bank guarantee. According to it, the appellant furnished
two bank guarantees, one for Rs.20,00,000/- and another for
Rs.38,28,000/- as performance security guarantee. Even though no
termination notice has been issued by the KSEB, by virtue of the
covenants of the performance guarantees extended by the appellant,
the KSEB directed to invoke the Bank guarantees and for the purpose
of invoking the Bank guarantees, the termination of the contract was
not mandatory. It was also submitted that the appellant, as per letter
dated 19.12.2017, e-mail dated 05.01.2018 and another letter dated
05.02.2018, had requested time for executing the agreement pointing
out various reasons, which is produced by the Board as Ext. R1B
series. Therefore, according to the Board, the cause of delay in
executing the agreement was attributable only to the appellant.
6. It was also submitted that in spite of the execution of the
agreement on 01.03.2018, the site was taken over by the appellant
only on 14.08.2018 i.e., more than 5 months after the date of
execution of the agreement. Again, it was submitted that a meeting
was conducted on 22.11.2018 by the KSEB to review the progress of
the work and in the said meeting, the appellant assured to complete
the work in time. That apart, though the project should have been
completed on 13.02.2019, the progress of the project was virtually nil.
Anyhow, at the request of the appellant, a meeting was conducted on
21.02.2019 and in the meeting the appellant informed about the
dispute by and between the shareholders of the company which
crippled their operations throughout the year 2018 and it was, assured
that the project would be completed within 15.05.2019 from the
aforesaid date and requested to grant extension till such date. Even
though KSEB Limited imposed penalty due to the liquidated damages,
the appellant expressed its willingness to continue with the project, if
time extension was granted and further informed that they are not
much concerned about the profit through the execution of the project,
but are only concerned with the valuable experience achieved through
executing the project and maintaining the good terms with the KSEB
Ltd. Anyway, time extension for the completion of the project was
granted for a period of three months from 01.06.2019 to 31.08.2019
without any financial obligations to KSEB Ltd. as per letter dated
23.05.2019, however based on certain conditions like, a fresh realistic
implementation schedule/chart showing activities from 01.06.2019 to
31.08.2019.
7. According to the KSEB, there was no progress of work and the
appellant has failed to comply with the contractual obligations and
therefore, as per Ext. P7 letter dated 02.07.2019, the board was
constrained to proceed with the termination of the project. On receipt
of the said letter, appellant approached this Court by filing W.P.(C) No.
2009 of 2019. However, the said writ petition was dismissed holding
that Ext. P7 was only a communication issued by the Board and
therefore, no interference is possible under Article 226 of the
Constitution of India.
8. Whatever that be, the Board has constituted a Dispute
Resolution Committee in accordance with Article XII of Ext. P3
agreement, evident from Ext. R1C and the committee meeting held on
04.02.2020 decided to extend the time by 4 months, and as per Ext.
R1D, the time was extended from 01.04.2020 to 31.07.2020 and the
same was communicated to the appellant as per Ext. R1E letter dated
01.04.2020. According to the Board, in spite of due diligence shown by
the Board, there was no concerted and dedicated efforts from the side
of the appellant to complete the work and the Board had no other
option than to invoke the Bank guarantee.
9. The appellant had filed a reply refuting the allegations and
producing certain documents to justify the stand adopted by the
appellant.
10. Anyhow, the learned single Judge, after considering the
issues raised by the parties elaborately, justified the stand adopted by
the Board and found that there was delay and laches on the part of the
appellant in executing the work in spite of the extension of time period
by the Board on several occasions and accordingly, dismissed the writ
petition.
11. We have heard Sri. Akhil Bhansali, learned counsel
representing the learned counsel for the appellant and Sri. G. Pramod
representing the learned Standing Counsel for the KSEB Ltd., and
perused the pleadings and materials on record.
12. The sole question emerges for consideration is whether any
manner of interference is required to the judgment of the learned
single Judge. The paramount contention advanced by the learned
counsel for the appellant was that the learned single Judge did not
consider or appreciate the legal issues involved in the writ petition and
failed to consider whether the encashment of the bank guarantee
without the termination of the agreement or without any show cause
notice was a legalistic approach on the part of the KSEB Ltd. It was
also submitted that since the legal circumstances with respect to the
invocation of the bank guarantee was raised vis-a-vis the agreement
executed, the learned single Judge egregiously failed by dismissing the
writ petition on the ground of delay and holding that the appellant
alone was attributable for the same. It was also submitted that there
was no justifiable reasons for not permitting the appellant to proceed
with the contract, especially taking into account the final extended
time period as per the decision of the Dispute Resolution Board due to
the lock down restrictions of the pandemic Covid-19 and therefore,
there was no possibility for executing the work, and taking into
account the said unavoidable situation, the KSEB ought to have made
a pragmatic approach and should have provided with sufficient time for
the execution of the work.
13. That apart, it was predominantly contended that the bank
guarantee was a performance guarantee intended for the purpose of
compelling the Contractor to honour all the conditions stipulated in the
original agreement and therefore, the intention of the parties was to
bind the appellant to the original agreement and the performance
guarantee stipulated in the agreement was for post commissioning
obligations and not prior to the commissioning of the project.
14. The learned Standing Counsel for the KSEB, on the other
hand, has taken us through the work order, the agreement and the
performance guarantee and submitted that the action of the KSEB was
in terms of the agreements executed by and between the parties and
the rest of the aspects are disputed factual circumstances, which could
not be deciphered in a proceeding under Article 226 of the Constitution
of India.
15. We have appreciated the rival submissions made across the
Bar. The factual circumstances with respect to the award of the
contract, execution of the agreements, taking over of the site, grant of
extended period etc. are all undisputed facts. It is also an undisputed
fact that consequent to the time lag in completing the contract, a
dispute arose and consequent to which the dispute was referred to the
Dispute Resolution Committee constituted by the KSEB in terms of
Article XII of Ext. P3 agreement. From Ext. P11 Minutes of the Dispute
Resolution Committee, it is clear that the appellant and his Advocate
participated in the meeting and the Dispute Resolution Committee has
taken note of the delay in execution of the work. However, it agreed to
the request of the Contractor for extension of time, subject to the
condition that the Contractor shall pay the Board an amount equal to
the generation loss (deemed) during the period of such extension. The
amount equal to generation loss per year was calculated to
Rs.50,57,500/- and the generation loss amount was agreed to be
deducted by calculating the loss from the date of issue of letter by the
Board to the Contractor and to the date on which the Contractor
completes his work.
16. It was also agreed that if the project is not successfully
completed and handed over to the Board as agreed, the said
generation loss will be deducted from the bank guarantee executed in
favour of the Board by the Contractor along with the other dues and
amounts borne out of the contract in terms of the agreement already
executed by and between the parties. The appellant was also asked to
extend the validity period of the Bank guarantee in order to enable the
Board to extend the further time as proposed by the Contractor. It is
relevant to note that the proceedings of the conciliation meeting is
dated 04.02.2020, which was prior to the lock-down restrictions. The
proceedings of the conciliation committee is accepted by the appellant,
since it is not under challenge. Therefore, the factual circumstances
arrived at by the learned single Judge to dismiss the writ petition, thus
declining the relief for protection of the bank guarantee, cannot be
said to be bad on factual aspects, since the appellant failed to adhere
to the commitment made before the Dispute resolution committee and
even within in the period up to the invocation of the Bank Guarantee.
However, the appellant has raised a contention that the bank
guarantee can be invoked only under the circumstances made in
Article XIII of Ext. P3 agreement and in order to appreciate the said
contention, it is extracted hereunder:
"ARTICLE XIIl - PERFORMANCE SECURITY DEPOSIT GUARANTEE:
During the performance security deposit guarantee period of 5 years from the date of commissioning, the Contractor shall repair free of charge, any defect noticed in the works and /or any damage or defects or functional failure noticed in any accessory transported or installed by the Contractor which falls or proves unsatisfactory under normal operations due to his faulty material handling or workmanship.
However, during the guarantee period, if the Contractor fails to rectify the defects, if any, in reasonable time, the Board shall arrange to make good the defects in works, accessories etc. and the amount incurred by the Board on this account will be recovered together with 21% of the expenses from the amounts payable to the Contractor.
On the expiry of the guarantee period, the amount kept for ensuring performance security deposit guarantee will be released after deducting the amount as above, if any."
17. On an analysis of the said covenant, we find that the
guarantee period of 5 years is from the date of commissioning and the
appellant Contractor is liable to repair free of charge, any defect
noticed in the works and/or any damage or defects or functional
failure noticed in any accessory transported or installed by the
Contractor, which fails or proves unsatisfactory under normal
operations due to his faulty material handling or workmanship.
However, if during the guarantee period, if the Contractor fails to
rectify the defects, if any, within a reasonable time, the Board shall
arrange to make good the defects in works, accessories etc. and the
amount incurred by the Board as agreed to be recovered with 21% of
the expenses from the amount payable to the Contractor. It was
agreed by and between the parties to realise 5% of the contract
amount in the performance security deposit and the bank guarantee
will be released on proving the specified capacity of the plant within
one year of commission and the remaining 5% of the contract amount
in the performance guarantee furnished by the contractor will be
released only after 5 years from the date of commissioning of the
project and by appropriate certification by the agreement authority.
But, it is also significant to note that Article X of the agreement
dealing with 'breach of contract', stipulates that if the Contractor
commits breach of all or any of the terms or conditions of contract,
the KSEBL shall be entitled to recover from the Contractor all the
damages it might suffer thereby and the amount thus due could be
recovered from the Contractor in any manner the KSEBL chooses,
including recovery by Revenue Recovery Proceedings.
18. Therefore, in our considered opinion, though the
performance security deposit guarantee dealt with under Ext. P3
agreement has its own features and consequences, when read
together with Article X, it is clear that the Board was vested with
powers to proceed with to recover the damages suffered by the Board
in any manner the Board chooses. It is an admitted fact that the work
was not completed within the agreed or extended period which is an
essential condition agreed upon by the parties to meet up with the
requirements of the board to generate power. That apart, the issue is
guided also by Ext. R1A performance guarantee agreement executed
by and between the parties having guarantee cover from 03.02.2018
to 31.01.2020 for an amount of Rs.38,20,000/- in accordance with the
terms and conditions of the letter of award/ work order dated
07.12.2017. As per the performance guarantee, the appellant
unconditionally and irrevocably undertook to pay to the purchaser, on
an immediate basis, upon receipt of first written demand from the said
purchaser and without any cavil or argument or delaying tactics or
reference by the Contractor and without any need for the purchaser to
convey to the Contractor any reasons for invocation of the bank
guarantee OR to prove the failure to perform on the part of the
supplier/Contractor(s) OR to show grounds OR reasons for the demand
OR the sum specified therein, the entire sum or sums within the limits
of Rs.38,20,000/-.
19. A reading of the said unconditional undertaking under clause
(b) of the performance agreement along with clause (f) of the said
guarantee agreeing unconditionally and irrevocably to pay to the KSEB
any amounts so demanded not exceeding Rs.38,20,000/-,
notwithstanding any dispute or disputes raised by the supplier or
anyone else in any suit or proceedings etc., would make it clear that
there was sufficient authority vested with the Board on the basis of the
terms and conditions executed by and between the parties to invoke
the bank guarantee. Therefore, the question raised with respect to the
authority of the KSEB to invoke the bank guarantee, in our view,
cannot be sustained under law, being a part of the Contract executed
by and between the parties.
20. Moreover, whatever documents executed, letters issued and
the agreements executed by and between the parties cannot be read
in isolation and they will have to be read together for the purpose of
understanding the situations that arose consequent to the contract
entered into by and between the appellant and the KSEB Limited.
Moreover, it is very well settled in law that whenever there are clear
terms and conditions in the contract executed by and between the
parties in regard to the performance of the parties and the action to be
taken, the parties are not at liberty to resile from the contract and
canvass for any other proposition to suit their convenience. Though
learned counsel for the appellant relied upon the Judgment of the Apex
court in Hindustan Construction Co Ltd. Vs State of Bihar [(1999)
8 SCC 436], a judgment rendered in an appeal from a suit proceeding
in regard to invocation of a Bank Guarantee, we feel, it may not be
suitable to be applied as a binding precedent in a writ proceeding,
since the facts raised by the appellant are stoutly disputed by the
respondent board in the instant writ petition .
21. That apart, the discussion of facts, and the disputes raised
by the appellant would clearly show that the entire aspects were
centered around various factual disputes and therefore, it could not be
resolved in a proceeding under Article 226 of the Constitution of India.
Moreover, the appellant has not established any case of mala fides or
illegality or unfairness so perverse on the part of the KSEB Limited in
regard to the invocation of the bank guarantee, to exercise the power
of judicial review conferred on a writ court; but on the contrary we find
that the KSEB Ltd. was cooperating with the agreement executed, and
the time was extended for the completion of the work on various
occasions at the request of the appellant as an attempt to protect the
interest of both parties. Thus, what we intend to convey is that there
was no palpable or grave circumstances justifying interference of a
writ court in a contractual matter, which is a well settled legal position.
The factual and legal circumstances so discussed persuade us to think
that the appellant was not entitled to get any relief and further that
the appellant has not made out any case for interference with the
judgment of the learned single Judge in an intra court appeal preferred
under Section 5 of the Kerala High Court Act, 1958, there being no
jurisdictional error or other legal infirmities .
Needless to say, appeal fails and accordingly, it is dismissed.
sd/-
S. MANIKUMAR, CHIEF JUSTICE.
sd/-
SHAJI P. CHALY, JUDGE.
Rv
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!