Citation : 2021 Latest Caselaw 4274 Ker
Judgement Date : 5 February, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE A.M.SHAFFIQUE
&
THE HONOURABLE MR. JUSTICE GOPINATH P.
FRIDAY, THE 05TH DAY OF FEBRUARY 2021 / 16TH MAGHA,1942
WA.No.138 OF 2021
AGAINST THE JUDGMENT DATED 25.6.2018 IN WP(C) 23761/2007(D) OF
HIGH COURT OF KERALA
APPELLANTS/RESPONDENTS NO.1 TO 3:
1 THE ASSISTANT ENGINEER
KSEBL, ELECTRICAL SECTION, NOORANAD.
2 THE DEPUTY CHIEF ENGINEER
ANTI POWER THEFT SQUAD (HQ), KSEBL, VIGILANCE WING,
VYDYUTHI BHVAN, PATTOM, P O, THIRUVANANTHAPURAM.
3 KERALA STATE ELECTRICITY BOARD
REPRESENTED BY ITS SECRETARY, VYDYUTHI BHAVAN,
PATTOM P O, TRIVANDRUM.
BY ADV. SRI.SUDHEER GANESH KUMAR.R.
RESPONDENT/PETITIONER/RESPONDENT:
DR.JOSE KOSHY GEORGE
MANAGING DIRECTOR,
M/S JOSCO HOSPITAL(P) LIMITED, EDAPPOM, PANDALAM-
R1 BY ADV. SRI.R.BINDU (SASTHAMANGALAM)
THIS WRIT APPEAL HAVING COME UP FOR ADMISSION ON 05.02.2021, THE
COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
W.A.No.138/2021 2
JUDGMENT
Dated this the 5th day of February 2021
Gopinath, J.
This writ appeal has been filed by the Assistant Engineer,
Kerala State Electricity Board, Electrical Section, Nooranad and
others challenging the judgment of a learned single Judge of this
Court in W.P.(C)No.23761/2007. The respondent/writ petitioner
had approached this Court challenging Ext.P6 order of the Deputy
Chief Engineer, KSEB, by which a penalty was imposed on the
respondent/writ petitioner for 'unauthorised extension'.
2. The respondent/writ petitioner contended that he was
the Managing Director of Josco Hospital (P) Ltd., and that he had
applied for providing a connection to a new building constructed
across the road from the existing hospital building and that the
Board had negligently kept the application pending as a result of
which after obtaining sanction from the PWD authorities, a line was
drawn to the building across the road for conducting the X-ray unit
of the Hospital.
3. On a consideration of the matter, the learned single
Judge found that the fact of 'unauthorised extension' is established
as the respondent/writ petitioner had no legal right to undertake
such 'extension' without permission of the Board. The learned
Single Judge had also taken note of the contention of the appellant
Board that since the building is on the opposite side of the road, only
fresh service connection can be granted and no 'extension' can be
permitted. The contention of the respondent/writ petitioner that
the respondent/writ petitioner cannot be penalised under clause 42
(d) of Conditions of Supply of Electrical Energy was also rejected by
the learned single Judge. However, the learned single Judge found
that the respondent/writ petitioner can be penalised only for
additional connected load, which was caused on account of
'unauthorised extension' and thus found that the respondent/writ
petitioner can be penalised only for an additional load of 32kw. This
was on the specific finding that the authorised connected load of the
respondent/writ petitioner was 31kw and he was found consuming
energy at a connected load of 63kw. The learned single Judge also
reduced the penalty to one time in the place of two times penalty
imposed by the Deputy Chief Engineer in the impugned order.
4. The learned counsel for the appellant Board would
contend that the Board itself had shown some leniency in as much as
the Deputy Chief Engineer had reduced the penalty to two times the
rate applicable to the respective tariff when the statutory provisions
(the then prevailing Conditions of Supply of Electrical Energy,
1990), provided that penalty would be at three times the applicable
tariff.
5. As already noticed, in the peculiar facts and
circumstances of the case, the learned single Judge reduced the
penalty to one time in the place of two times penalty imposed by the
Deputy Chief Engineer in the impugned order. The judgment of the
learned single Judge was on 25.6.2018. The appeal was filed with a
delay of 862 days. We have condoned the delay after noticing the
circumstances which led to the delay in filing the appeal.
6. The learned counsel for the Board would contend that
when the Statute had prescribed the penalty to be three times the
applicable tariff, the learned single Judge ought not to have reduced
the penalty to one time especially considering the fact that the
Deputy Chief Engineer had himself reduced the penalty to two times
instead of statutorily fixed three times.
7. The learned counsel for the respondent/writ petitioner
would contend that the circumstances which led to the Deputy Chief
Engineer finding that the penalty should be imposed only at two
times applicable tariff are particularly that there was some
negligence on the part of the Board also in not considering the
application submitted by the respondent/writ petitioner for
connection at the proper time which, according to us, they should
have done essentially considering the fact that the respondent/writ
petitioner was running a Hospital and the extension requested for
was to operate the X-ray unit attached to the Hospital. Even
otherwise, when a consumer makes an application for extending his
electric connection, the Board should have taken a decision within a
reasonable time. In the totality of the facts and circumstances of the
case, we feel that it would be appropriate to fix the penalty at 1.5
times instead of one time as fixed by the learned single Judge,
especially considering the fact that the learned single Judge had on
merits found that the contentions raised by the respondent/writ
petitioner against the action taken by the Board cannot be sustained.
8. The learned counsel for the respondent/writ petitioner
would however contend that his client should not be penalized for
the period during which there was a delay in filing this writ appeal.
We feel that the contention of the respondent/writ petitioner is well-
founded.
9. We, accordingly, hold that no surcharge shall be levied
on the respondent/writ petitioner for the period from 25.6.2018 till
11.1.2021. However, we hold that the Board will be entitled to
recover penalty at the rate of 1.5 times instead of one time as fixed
by the learned single Judge. Therefore, we direct the appellants to
issue a revised calculation raising the demand on the
respondent/writ petitioner by fixing penalty at 1.5 times the
applicable tariff for the excess load of 32kw as found by the learned
single Judge and by not levying any surcharge for the period from
25.6.2018 till 11.1.2021. It is made clear that the demand will be for
a total period of days reckoned by the Deputy Chief Engineer in
Ext.P.6 and at the applicable rate. On such demand being raised, the
respondent/writ petitioner shall be given a reasonable time to remit
such demand.
The writ appeal will stand disposed of accordingly.
Sd/-
A.M.SHAFFIQUE
JUDGE
Sd/-
GOPINATH P.
JUDGE
acd
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!