Citation : 2021 Latest Caselaw 4038 Ker
Judgement Date : 4 February, 2021
WP(C).No.527 OF 2021(M)
1
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE SMT. JUSTICE P.V.ASHA
THURSDAY, THE 04TH DAY OF FEBRUARY 2021 / 15TH MAGHA,1942
WP(C).No.527 OF 2021(M)
PETITIONER/S:
K.ABDUL REHIMAN
AGED 62 YEARS
THOTTARIKIL PURAYIDOM, KALANJOOR P.O.,
PATHANAMTHITTA
BY ADVS.
SRI.R.JAIKRISHNA
KUM.NARAYANI HARIKRISHNAN
RESPONDENT/S:
1 THE STATE FARMING CORPORATION OF KERALA LIMITED,
VETTITHITTA P.O., ALIMUKKU,PUNALUR, KOLLAM, KERALA-
689 696, REPRESENTED BY ITS MANAGING DIRECTOR
2 THE COMMERCIAL OFFICER,
THE STATE FARMING CORPORATION OF KERALA LIMITED,
VETTITHITTA P.O., ALIMUKKU,PUNALUR, KOLLAM, KERALA-
689 696
3 STAR PLYWOOD,
ODAKKALI, ASAMANOOR P.O., PERUMBAVOOR-683 549,
REPRESENTED BY ITS MANAGING PARTNER-ANTHRU P.A.
4 PIUS ASSOCIATES,
PILLATTU BUILDING, VARANDARAPPILLY P.O., THRISSUR-
680 303, REPRESENTED BY ITS PROPRIETOR- PIUS P.M.
5 ASHRAF OMMER RAWTHER,
VII/128,KARIYARA P.O., PUNALOOR, KOLLAM-691 332
6 AMA TRADERS,
9/344,APPADATHU, PANIPRA ROAD, PANIPRA,
KOTHAMANGALAM P.O.,-686 691, REPRESENTED BY ITS
PROPRIETOR- ABDUL JABBAR
7 VARAMBEL ENTERPRISES,
PPXII/432, KADASSERY, OPP VISHNU TEMPLE, KADASSERY
WP(C).No.527 OF 2021(M)
2
POONKULANJI P.O., PUNNALA,KOLLAM-689 695,
REPRESENTED BY ITS PROPRIETOR- VISHNU P.S
R1-2 BY ADV. SRI.DENIZEN KOMATH
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON
01.02.2021, THE COURT ON 04.02.2021 DELIVERED THE FOLLOWING:
WP(C).No.527 OF 2021(M)
3
P.V.ASHA, J.
------------------------------------------
W.P.(C) No.527 of 2021
------------------------------------------- Dated this the 4th day of February, 2021
JUDGMENT.
This Writ Petition is filed seeking a direction to the
1st respondent to reject the tenders submitted by the
respondents 3 to 7 on the ground that they have not
submitted the requisite documents along with the tender; he
seeks a further direction to award the sale of trees in his
favour.
2. The State Farming Corporation- 1st respondent issued
Ext.P1 notice inviting tender on 25.11.2020 for sale of
36306 numbers of Rubber Trees available at Chithalvetti,
Mullumala and Cherupittakavu estates (19 blocks) with the
tender conditions Ext.P2. Petitioner who is a B-Class
Contractor participated in the tender in respect of 1802,
2001 and 1783 numbers of trees in block no.E,F and K of
Chithalvetti estate and in respect of 2271 and 2428 numbers
of trees in block no.17 and 18 of Cherupittakavu as per
Ext.P3 series of price schedule. It is stated that the
petitioner was the bidder who quoted highest price for
block no.F of Chithalvetti estate and block no.17 and 18 of
Cherupittakavu estate. However it is stated that when the WP(C).No.527 OF 2021(M)
bid was submitted on account of technical glitch in the
webportal the particular column was not showing the total
price of trees. It is stated that petitioner had quoted a
sum of Rs.1,755/- as base rate and for the total number of
trees (1802) the total price should have been auto
populated as Rs.13,62,510/- (1802x 1755); but it was
showing only Rs.1,755/- which was the base rate. It is
stated that the 1st respondent awarded the trees of Block
No.E of Chithalvetti to the 3rd respondent and Block K was
awarded to another person. It is stated that in block no.F
of Chithalvetty Estate and Block no.17 and 18 of
Cherupitakavu Estate, though petitioner was the bidder who
quoted the highest price as per Exts.P4 series available in
the e-tender portal, the 1st respondent decided to cancel
the tender and initiated steps for retender. It is stated
that on coming to know about the same, petitioner submitted
Exts.P5 and P6 letters to the 1 st respondent on 14.12.2020
and 22.12.2020 pointing out the fulfillment of all tender
conditions by him and the technical glitches occurred in
the portal. It is stated that 1st respondent did not respond
to his representations. On 21.12.2020, the 1st respondent
issued Ext.P7 notice for re-tender of the Rubber Trees at
Block 7 of Chithalvetti Estate and Block 17 and 18 of WP(C).No.527 OF 2021(M)
Cherupittakavu estate along with trees in other 4 blocks.
Petitioner claims that as there was paucity of time for
challenging the re-tender process he participated in the
re-tender. It is stated that clause 3 directing to quote
the price on block basis, was included in Ext.P8 re-tender
conditions since the 1st respondent had taken note of the
technical glitch occurred in the e-portal; at the same time
out of the 19 blocks, 1st respondent chose to hold re-
tender only in 7 blocks and that in three blocks out of
those 7 which were re-tendered, petitioner was the bidder
who quoted highest price. It is stated that pursuant to the
re-tender notification, petitioner submitted his bid in 6
blocks including the three blocks in which he was the
highest bidder. It is stated that there were three bidders
in each of the 7 blocks in which he participated and in
these blocks respondent no.3 and 6 were the highest bidders
after re-tender. It is stated that Ext.P9 series of the
schedule of price quoted by the bidders for the said 7
blocks would show that the 6th respondent turned out as the
highest bidder in block no.A, D and F of Chithalvetti and
the 3rd respondent turned out to be highest bidder in block
no.17 and 18 of Cherupittakavu and also in Mullumala.
According to the petitioner bids submitted by respondents 3 WP(C).No.527 OF 2021(M)
to 7 were not liable to be considered since their bids were
defective and they had not uploaded the requisite
documents. The following are the infirmities pointed out by
the petitioner:
In the case of the 3rd respondent-Star Plywood:
1. All pages of the tender conditions are not signed.
2. Credit worthiness certificate from the bank is not submitted.
3. Aadhar card not submitted.
4. GST registration certificate not submitted.
5. PAN card not submitted.
In the case of 4th respondent -Pius Associates:
1. Credit worthiness certificate from the bank is not submitted
2. Aadhar card not submitted
3. GST registration certificate not submitted
4. PAN card not submitted In the case of 5th respondent - Ashraf Ommer Rawther:
1. All pages of the tender conditions are not signed
2. Credit worthiness certificate from the bank is not submitted
3. Aadhar card not submitted
4. GST registration certificate not submitted
5. PAN card not submitted In the case of 6th respondent -AMA Traders:
1. Credit worthiness certificate from the bank is not submitted In the case of 7th respondent -Varambel Enterprises it is
stated that:
1. Credit worthiness certificate from the bank is not submitted
2. Aadhar card not submitted WP(C).No.527 OF 2021(M)
3. GST registration certificate not submitted
4. PAN card not submitted.
3. Petitioner claims that the action of 1st respondent
in accepting the tenders of the respondents 3 to 7, who did
not submit/upload the requisite documents along with their
tender is in violation of clause 18B and C of Ext.P8 re-
tender conditions which insists that the bidders shall
submit signed copy of the proof of identity either as
permanent resident certificate issued by the Village
Officer or Election ID card/Passport/Aadhar and in case the
same is not uploaded they would not be considered. The
credit worthiness certificate is another document which is
to be produced apart from Pancard and GST registration
certificate. It is stated that though the petitioner
submitted Ext.P11 representation pointing out the
infirmities in the tenders submitted by respondents 3 to 7
and illegality in accepting their bid, the 1st respondent
did not take any action. The petitioner therefore filed
this Writ Petition seeking a direction to the 1st respondent
to reject the tenders submitted by respondents 3 to 7 and
to award the trees to the petitioner treating him as H1.
4. The 1st respondent has filed a counter affidavit
refuting the contentions of the petitioner. It is stated WP(C).No.527 OF 2021(M)
that as per clause 11 and 19 of Exts.P2 and P8 tender
conditions the Corporation reserves full rights to accept
or reject any or all tenders without assigning any reason.
It is stated that clause 14 of Ext.P2 conditions provided
that the trees would only be sold in block. But the
petitioner committed a mistake by not offering the price in
accordance with clause 14 of Ext.P2 tender conditions for
the entire block. According to the respondent there was no
technical glitch of any kind and all other participants
have given the rate for the block. It is stated that the IT
mission server submits the comparison statement through
online e-tender portal from which the Corporation is to
consider highest rate offered by each tender for each
Block. Out of the 19 blocks notified in the original tender
the highest offer in 12 blocks was accepted and
confirmation order was issued to the tenderers who quoted
the highest rate. Producing Ext.R1(a), (b) and (c) BOQ
summaries, the respondent has stated that the contention
of petitioner with respect to the original tender are
baseless. It is stated that the 1st respondent had
considered the representation submitted by the petitioner
and that the decision to re-tender for certain blocks
including Chithalvetti and Cherupitakavu estates was taken, WP(C).No.527 OF 2021(M)
based on the recommendation of the Sales Committee. It is
stated that he had submitted Ext.P6 representation raising
claims on 1st tender after participating in the 2nd tender.
It is stated that the original tender was opened on
10.12.2020. Based on the decision for re-tender, notice for
re-tender was issued on 21.12.2020 giving due opportunity
for the contesting parties. It is stated that a 2 nd tender
became necessary in view of the low rates offered by the
contestants and in order to see that the contestants like
petitioner are not committing repeated glitches while
quoting tenders through IT Portals, that it became
necessary to incorporate clause 3 in the notice inviting
re-tender. The respondent doubted the bonafides of the
petitioner pointing out that the price he quoted in the re-
tender is far less than in the first tender. Regarding the
infirmities pointed out by the petitioner with respect to
the party respondents it is stated that signature in all
the pages of the tender is not necessary when it is
digitally signed. Regarding the other contentions with
respect to the non submission of ID card, Pancard, GST
registration, etc it is stated that the participants had
already submitted those details in the previous occasion
pursuant to Ext.P1 tender. It is further stated that as per WP(C).No.527 OF 2021(M)
clause 12 of Ext.P8 tender the 1st respondent has the
authority to accept or reject any re-tender on any reason.
It is stated that the 3rd respondent is already having
Ext.R1(e) GST registration. It is stated that the
petitioner who quoted rates far below does not have any
right to claim that the trees covered by the re-tender
shall be awarded to him. According to the 1 st respondent
any delay in finalisation of the re-tender would cause
irreparable financial loss to the Corporation which is
already running on loss.
5. Heard Sri.Jaikrishna the learned Counsel for the
petitioner and Sri.Renjith Thampan learned senior counsel
appearing for the 1st respondent.
6. While Sri.Jaikrishna asserted that the violation of
tender conditions are sufficient reason for rejection of
the bids submitted by respondents 3 to 7, Sri.Renjith
Thampan, the learned Senior Counsel argued that the
circumstances of the case do not warrant any intervention
by this court and any delay in removal and replantation of
trees would affect the Corporation adversely. Relying on
the judgments of the Division Bench in TBAS Construction
Supreme Infrastructure India Ltd. (M/s.) vs. Union of India
and others : 2018 (4) KHC 865, Pushkarraj Constructions WP(C).No.527 OF 2021(M)
Pvt. Ltd. (M/s.) and others v. Silppi Constructions and
Contractors and others : 2019 (3) KHC 566 and Abdul Majeed
K.S. And another vs. Beeru P.K. and others : 2013 (3) KHC
805 (para 11), Indian Railway Catering & Tourism
Corporation Ltd. (M/s.) and another vs. Doshion Veolia
Water Solutions (P) Ltd. (M/s.) and others : 2010 KHC 4740
it was argued that intervention of the court in matters of
contract should be limited to cases where the decision made
by the authority is malafide or intended to favour somebody
or where the process adopted is so arbitrary. It was argued
that the Corporation has taken its decision in public
interest and it has got every right to take such a decision
in the interest of the Corporation and interference at the
instance of petitioner who quoted a very low rate is not
called for.
7. I have considered the rival contentions. The
contention of the petitioner regarding the 1st tender is
that he was the highest tenderer in respect of 4 blocks
while admitting that he could provide only the rate per
tree and not per block, alleging technical glitches in the
portal. Ext.R1(d) minutes of the sales committee would
show that his complaint was considered while confirming the
tenders. The minutes would also show that there were WP(C).No.527 OF 2021(M)
several other participants who had quoted the rate per
block and did not face any such technical glitches as
alleged by the petitioner. Ext.R1(d) would also show that
the decision for re-tendering was taken in the interest of
the Corporation. At any rate petitioner has not challenged
the said decision and has not sought any relief based on
the tender he submitted pursuant to Ext.P1 tender
notification. On the other hand he has participated in the
re-tender that too quoting rate far lower than which he
quoted in the original tender. Petitioner does not have a
case that he is the highest bidder in the re-tender. He is
claiming his chance pointing out the infirmities in respect
of other tenderers who quoted higher price, referring to
clause 13 and 18B and C of Ext.P8 tender conditions.
Regarding the absence of signature in all pages, learned
Counsel for the petitioner has withdrawn the contention,
agreeing that digital signature is sufficient. The other
infirmities pointed out are non production of Pancard, GST
registration, Adhaar card, credit worthiness certificate
received from the Bank, etc. If the 1st respondent found
that those conditions can be relaxed and those are all
matters which could be ensured otherwise, it cannot be said
that their tenders have to be rejected when the amount WP(C).No.527 OF 2021(M)
quoted by them are at a higher rate and that the rejection
of their tenders would defeat the interest of the
Corporation. Therefore, an intervention at the instance of
petitioner who has quoted a very low price, would not be
just or fair. Even if there is violation of clause 18 those
infirmities were found to be curable on production of the
relevant documents. When the tendering authority has found
it proper to accept the tenders from the party respondents
in the interest of the institution this Court is not
expected to interfere with such a decision.
8. It is settled law that in respect of contracts
entered into on behalf of the State or the undertakings
under it, the court can examine only the infirmity if any
in the 'decision-making process' whether it was
unreasonable, irrational, arbitrary and violative of
Article 14 of the Constitution; and not the decision
itself. As held by the Apex Court in Tata Cellular v. Union
of India: (1994) 6 SCC 651, wherein the scope of judicial
review in contractual matters was explained the terms of
the invitation to tender cannot be open to judicial
scrutiny because the invitation to tender is in the realm
of contract; such decisions are made qualitatively by
experts; the court does not sit as a court of appeal but WP(C).No.527 OF 2021(M)
merely reviews the manner in which the decision was made;
the court does not have the expertise to correct the
administrative action; Government must have freedom of
contract; a fair play in the joints is a necessary
concomitant for an administrative body functioning in an
administrative sphere or quasi-administrative sphere.
However, the decision must not only be tested by the
application of Wednesbury principle of reasonableness; but
must be free from arbitrariness not affected by bias or
actuated by malafides; quashing decisions may impose heavy
administrative burden on the administration and lead to
increased and unbudgeted expenditure. The aforesaid
judgment is reiterated and followed in a series of
judgments. As held in Jagdish Mandal v. State of Orissa:
(2007) 14 SCC 517 so long as a decision relating to award
of contract is bonafide and is in the public interest,
courts are not supposed to interfere by exercising power of
judicial review even if a procedural aberration or error in
assessment or prejudice to a tenderer is made out.
9. In Raunaq International Ltd. v. I.V.R. Construction
Ltd.: 1999 (1) SCC 492 the Apex Court held that there
should not be any interference under Article 226 in a
dispute between rival tenderers unless substantial amount WP(C).No.527 OF 2021(M)
of public interest was involved or in case the transaction
was vitiated by malafides. In B.S.N. Joshi & Sons Ltd. v.
Nair Coal Services Ltd.: 2006 (11) SCC 548 it was held that
when a decision is taken by the appropriate authority upon
due consideration of the tender document submitted by all
the tenderers on their own merits, the Courts have to
exercise judicial restraint once it was found that the
decision of the authority was taken purely in public
interest. In Afcons Infrastructure Ltd. v. Nagpur Metro
Rail Corpn. Ltd.: (2016) 16 SCC 818 it was held that the
employer of a project who authored the tender documents, is
the best person to understand and appreciate its
requirements and interpret its documents. It was held as
follows:
"The constitutional courts must defer to this understanding and appreciation of the tender documents, unless there is mala fide or perversity in the understanding or appreciation or in the application of the terms of the tender conditions. It is possible that the owner or employer of a project may give an interpretation to the tender documents that is not acceptable to the constitutional courts but that by itself is not a reason for interfering with the interpretation given.xxxxx
13. In other words, a mere disagreement with the decision-making process or the decision of the administrative authority is no reason for a constitutional court to interfere. The threshold of mala fides, intention to favour someone or arbitrariness, irrationality or perversity must be met before the constitutional court interferes with the decision-making process or the decision."
10. In Municipal Corpn., Ujjain v. BVG India Ltd.: (2018) 5 WP(C).No.527 OF 2021(M)
SCC 462 , the Apex Court was considering a case where tenders
were invited for door-to-door collection and transportation of
municipal solid waste. After analysing various judgments with
respect to the scope of judicial review on contractual matters,
the 3 Judge Bench reiterated that the purpose of judicial review
of administrative action is to check whether the choice or
decision is made lawfully and not to check whether the choice or
decision is sound. If the process adopted or decision made by
the authority is not malafide and not intended to favour
someone, if the process adopted or decision made is neither so
arbitrary nor irrational and if the public interest is not
affected, there should be no interference under Article 226. In
paragraph 45 it was held as follows:
45. Evaluating tenders and awarding contracts are essentially commercial transactions/contracts. If the decision relating to award of contract is in public interest, the courts will not, in exercise of the power of judicial review, interfere even if a procedural aberration or error in awarding the contract is made out. The power of judicial review will not be permitted to be invoked to protect private interest by ignoring public interest. Attempts by unsuccessful bidders with an artificial grievance and to get the purpose defeated by approaching the court on some technical and procedural lapses, should be handled by courts with firmness. The exercise of the power of judicial review should be avoided if there is no irrationality or arbitrariness. In the matter on hand, we do not find any illegality, arbitrariness, irrationality or unreasonableness on the part of the expert body while in action. So also, we do not find any bias or malafides either on the part of the corporation or on the part of the technical expert while taking the decision. Moreover, the decision is taken keeping in mind the public interest and the work experience of the successful bidder."
11. After analysing almost all the judgments of the
Apex Court, the Division Bench of this court in the WP(C).No.527 OF 2021(M)
judgments in TBAS Construction Supreme Infrastructure India
Ltd. (M/s.) and in Pushkarraj Constructions Pvt. Ltd.
(M/s.)'s case held that interference with the decisions of
tendering authority must be only in exceptional cases and
while examining the rationality of a decision the court
should look at the matter in the point of view of the
tendering authority and even in cases where there is
procedural lacuna court should refrain from interference if
the decision is for public interest.
12. All the infirmities alleged by the petitioner are
those which the Corporation has considered and found that
the tenderers have already produced it. 1st respondent
cannot be found fault with on the said decision when the
party respondents have quoted a higher amount. There is no
bonafides in the contention of the petitioner that the re-
tender has caused quoting of higher amount by other
tenderers on coming to know about the amount quoted by him.
Petitioner did not even quote either the same amount as he
had quoted in the previous tender or even any higher
amount. The contention that the respondents happened to
quote higher amount on coming to know about the rate quoted
by the petitioner in the previous tender is unsustainable.
It is also pertinent to note that there were altogether 10 WP(C).No.527 OF 2021(M)
blocks for which re-tender was notified. In the light of
the judgments of the apex court that the power of judicial
review in matters of contract are limited and it is for the
tendering authority to decide whether a tender can be
accepted or not in the interest of public, this Court is
not expected to interfere with the re-tender. There is no
allegation of malafides or that the 1st respondent is
favouring anybody.
Accordingly the Writ Petition is dismissed.
Sd/-
P.V.ASHA
rkc JUDGE
WP(C).No.527 OF 2021(M)
APPENDIX
PETITIONER'S/S EXHIBITS:
EXHIBIT P1 TRUE COPY OF THE NOTICE INVITING TENDER
ISSUED BY THE 1ST RESPONDENT
EXHIBIT P2 TRUE COPY THE TENDER CONDITIONS ISSUED BY
THE 1ST RESPONDENT FROM THE WEBSITE
5.12.2020
EXHIBIT P3 TRUE COPY OF THE PRICE SCHEDULE WITH
RESPECT TO THE BID SUBMITTED BY THE
PETITIONER FOR BLOCK E OF CHITHALVETTY ESTATE
EXHIBIT P3A TRUE COPY OF THE PRICE SCHEDULE WITH RESPECT TO THE BID SUBMITTED BY THE PETITIONER FOR BLOCK F OF CHITHALVETTY ESTATE
EXHIBIT P3B TRUE COPY OF THE PRICE SCHEDULE WITH RESPECT TO THE BID SUBMITTED BY THE PETITIONER FOR BLOCK K OF CHITHALVETTY ESTATE
EXHIBIT P3C TRUE COPY OF THE PRICE SCHEDULE WITH RESPECT TO THE BID SUBMITTED BY THE PETITIONER FOR BLOCK 17 OF CHERPPITTAKAVU ESTATE
EXHIBIT P3D TRUE COPY OF THE PRICE SCHEDULE WITH RESPECT TO THE BID SUBMITTED BY THE PETITIONER FOR BLOCK 18 OF CHERUPPITTAKAVU ESTATE
EXHIBIT P4 TRUE COPY OF THE PRICE SCHEDULE WITH RESPECT TO THE BID SUBMITTED BY THE PETITIONER FOR BLOCK- F OF CHITHALVETTY ESTATE
EXHIBIT P4A TRUE COPY OF THE PRICE SCHEDULE WITH RESPECT TO THE BID SUBMITTED BY THE PETITIONER FOR BLOCK- 17 OF CHERUPPITTAKAVU ESTATE
EXHIBIT P4B TRUE COPY OF THE PRICE SCHEDULE WITH RESPECT TO THE BID SUBMITTED BY THE PETITIONER FOR BLOCK- 18 OF CHERUPPITTAKAVU ESTATE WP(C).No.527 OF 2021(M)
EXHIBIT P5 TRUE COPY OF THE LETTER SUBMITTED BY THE PETITIONER TO THE 1ST RESPONDENT
EXHIBIT P6 TRUE COPY OF THE LETTER SUBMITTED BY THE PETITIONER TO THE 1ST RESPONDENT
EXHIBIT P7 TRUE COPY OF THE NOTICE ISSUED BY THE 2ND RESPONDENT
EXHIBIT P8 TRUE COPY OF THE RE-TENDER CONDITIONS ISSUED BY THE 1ST RESPONDENT FORM THE WEBSITE
EXHIBIT P9 TRUE COPY OF THE SCHEDULE OF PRICE QUOTED BY THE BIDDERS FOR BLOCK A OF CHITHALVETTY ESTATE
EXHIBIT P9A TRUE COPY OF THE SCHEDULE OF PRICE QUOTED BY THE BIDDERS FOR BLOCK D OF CHITHALVETTY ESTATE
EXHIBIT P9B TRUE COPY OF THE SCHEDULE OF PRICE QUOTED BY THE BIDDERS FOR BLOCK F OF CHITHALVETTY ESTATE
EXHIBIT P9C TRUE COPY OF THE SCHEDULE OF PRICE QUOTED BY THE BIDDERS FOR BLOCK 17 OF CHERUPPITTAKAVU ESTATE
EXHIBIT P9D TRUE COPY OF THE SCHEDULE OF PRICE QUOTED BY THE BIDDERS FOR BLOCK 18 OF CHERUPPITTAKAVU ESTATE
EXHIBIT P9E TRUE COPY OF THE SCHEDULE OF PRICE QUOTED BY THE BIDDERS FOR BLOCK 7B OF MULLUMALA ESTATE
EXHIBIT P10 TRUE COPY OF THE SAMPLE TENDER DOCUMENT SUBMITTED BY 3RD RESPONDENT
EXHIBIT P10A TRUE COPY OF THE SAMPLE TENDER DOCUMENT SUBMITTED BY 4TH RESPONDENT
EXHIBIT P10B TRUE COPY OF THE SAMPLE TENDER DOCUMENT SUBMITTED BY 5TH RESPONDENT
EXHIBIT P10C TRUE COPY OF THE SAMPLE TENDER DOCUMENT SUBMITTED BY 6TH RESPONDENT
EXHIBIT P10D TRUE COPY OF THE SAMPLE TENDER DOCUMENT SUBMITTED BY 7TH RESPONDENT WP(C).No.527 OF 2021(M)
EXHIBIT P11 TRUE COPY OF THE LETTER SUBMITTED BY THE PETITIONER BEFORE THE 1ST RESPONDENT
RESPONDENT'S/S EXHIBITS:
EXHIBIT R1(a) TRUE PHOTOCOPY OF THE BOQ SUMMARY OF THE PETITIONER AND THAT OF THE HIGHEST BIDDER REGARDING CHITHALVETTY ESTATE BLOCK CY F IN THE FIRST TENDER.
EXHIBIT R1(b) TRUE PHOTOCOPIES OF THE BOQ SUMMARY OF THE PETITIONER AND THAT OF THE HIGHEST BIDDER REGARDING CHERUPPITTAKAAVU ESTATE BLOCK 17 IN THE FIRST TENDER.
EXHIBIT R1(c) TRUE PHOTOCOPIES OF THE BOQ SUMMARY OF THE PETITIONER AND THAT OF THE HIGHEST BIDDER REGARDING CHERUPPITTAKAAVU ESTATE BLOCK 18 IN THE FIRST TENDER.
EXHIBIT R1(d) TRUE PHOTOCOPY OF THE DETAILS AND MINUTES OF THE FIRST TENDER COUNTER SIGNED BY THE 1ST RESPONDENT MANAGING DIRECTOR ON 22.12.2020.
EXHIBIT R1(e) TRUE PHOTOCOPY OF THE GST REGISTRATION CERTIFICATE OF THE 3RD RESPONDENT STAR PLYWOOD INDUSTRIES.
EXHIBIT R1(f) TRUE PHOTOCOPY OF THE DETAILS AND MINUTES OF THE FIRST TENDER COUNTER-SIGNED BY THE 1ST RESPONDENT MANAGING DIRECTOR ON 5.1.2021.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!