Citation : 2021 Latest Caselaw 3856 Ker
Judgement Date : 3 February, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
WEDNESDAY, THE 03RD DAY OF FEBRUARY 2021/14TH MAGHA,1942
WP(C).No.9671 OF 2020(H)
PETITIONER:
KERALA GOVERNMENT ELECTRICAL CONTRACTORS
ASSOCIATION,REPRESENTED BY ITS
WORKING PRESIDENT-P.VELAPPAN NAIR,
REGISTER NO.T/529/1995, P.W.D ELECTRICAL
DIVISION OFFICE, PMG JN, PATTOM P.O.,
THIRUVANANTHAPURAM-04.
BY ADVS.
SHRI.AJITH KRISHNAN
SRI.G.SHRIKUMAR (SR.)
RESPONDENTS:
1 STATE OF KERALA REPRESENTED BY
THE CHIEF SECRETARY,
GOVERNMENT OF KERALA,
GOVERNMENT SECRETARIAT,
THIRUVANANTHAPURAM-695 001.
2 ADDITIONAL CHIEF SECRETARY,
STATE OF KERALA,
PUBLIC WORKS DEPARTMENT,
GOVERNMENT SECRETARIAT,
THIRUVANANTHAPURAM-695 001.
3 THE CHIEF ENGINEER,
PUBLIC WORKS DEPARTMENT-BUILDINGS,
PUBLIC OFFICE,
THIRUVANANTHAPURAM-695 033.
WP(C) No.9671/2020
:2 :
4 THE CHIEF ELECTRICAL ENGINEER,
PUBLIC WORKS DEPARTMENT(ELECTRICAL WING),
PUBLIC OFFICE, THIRUVANANTHAPURAM-695 033.
R1-R4 BY GOVERNMENT PLEADER SRI. K.V.MANOJ KUMAR
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD
ON 03-02-2021 THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
WP(C) No.9671/2020
:3 :
JUDGMENT
~~~~~~~~~
Dated this the 3rd day of February, 2021
The petitioner is Kerala Government Electrical
Contractors Association. The members of the petitioner-
Association are engaged in installing, maintaining and
undertaking electrical contract works in the buildings
constructed by the State Government and various Public
Sector Undertakings. The petitioner has approached this
Court aggrieved by the proposal of the 1 st respondent-State of
Kerala to implement a composite tender system in the building
wings for all building construction tenders.
2. Electrical and civil contracts are normally tendered
separately by the respondents as the need for electrical works
arises and proper assessment thereof can be made only after
completion of the structure of the building. The Electrical
Wing of PWD used to invite tenders for carrying out electrical WP(C) No.9671/2020
work, only when the structure of the building is about to be
completed. The electrical works were being carried out by the
registered Electrical Contractors under the Public Works
Department who hold a licence granted by the Electrical
Inspectorate of the State Government. Licence is granted
only to those Electrical Contractors having sufficient
experience and prescribed qualifications.
3. While the scheme was of first awarding civil
contracts in respect of a building and then inviting tenders
from Electrical Contractors, the Government attempted to
change the system by introducing a composite tender system
for simultaneous execution of civil and electrical works. The
Government on 20.04.2008 issued Ext.P2 Circular which
stated that all civil works and electrical works should be
tendered simultaneously and electrical works carried along
with the civil works. By Ext.P3 letter dated 24.07.2009, the
Chief Engineer informed the Principal Secretary to
Government that if a composite tender system is adopted,
only a limited number of Electrical Contractors will be involved WP(C) No.9671/2020
and therefore requested that the Government may decide
whether to follow composite tendering of civil and electrical
works and to consider whether to follow the present separate
tender procedure for civil and electrical works under the
co-ordination of the concerned engineers of buildings and
electrical wings.
4. The petitioner approached this Court filing W.P.(C)
No.30556/2009, aggrieved by the proposal of composite
tender system. This Court held that none of the concerns of
the petitioner has been answered by the Government. This
Court by Ext.P4 judgment held that the system of inviting
tender only through the civil contractors will effectively deny
opportunities to the electrical contractors. It will result in
absence of any competition. This Court found that it would
violate the concept of level playing field resulting in violation of
Article 19(1)(g) of the Constitution of India. This Court further
held that Article 14 will be attracted while testing the validity of
the Government Policy. This Court accordingly quashed the
orders impugned in the writ petition and directed the WP(C) No.9671/2020
Government to reconsider the matter in the light of the
findings rendered in the judgment.
5. Pursuant to Ext.P4 judgment, the Government
issued Ext.P5 order dated 13.01.2011 directing that the
component tender document should have two separate
schedules of works, Part A for civil works and Part B for
electrical works. The Government ordered that only
contractors with electrical registration with PWD will be
awarded electrical works. In 2015, when the Executive
Engineer, Electronic Division issued a composite tender, the
petitioner filed W.P.(C) No.2618/2015, which was allowed by
this Court as per Ext.P6 judgment dated 31.03.2015.
6. But, to the surprise and detriment of the members
of the petitioner-Association, the Government has now issued
Ext.P1 order dated 26.02.2020 according sanction to
implement composite tender system. As per Ext.P1, if the
major component is civil, the existing civil contractors may
also be permitted to take part in composite tender upto their
tendering limits provided that existing civil contractor will have WP(C) No.9671/2020
to submit an undertaking that they will obtain valid
electrical/electronic licence or associate with an agency
having valid electrical/electronic licence. If the major
component is electrical work, the existing electrical contractors
may also be permitted to take part in composite tender upto
their tendering limits, provided they will give an undertaking
that they will obtain a valid civil licence/electronic licence or
associate with an agency having civil/electronic licence.
7. Ext.P1 does not provide a level playing field for the
Electrical Contractors and put them at the mercy of big civil
contracting Companies/Firms for survival. It will enhance
costs of construction thereby substantially affecting public
exchequer. Ext.P1 offends the fundamental rights guaranteed
to the members of the petitioner-Association under Articles 14
and 19(1)(g) of the Constitution of India, contends the
petitioner.
8. The 2nd respondent defended the writ petition filing
counter affidavit. The 2nd respondent stated that there were
complaints among various Departments that the civil and WP(C) No.9671/2020
electrical works are not arranged simultaneously and this has
led to splitting and cutting open of walls already plastered and
drilled and wiring activities carried out to the building. This
tendency causes damage to the building and delays the
functional use of the building even for years. Composite
tender system was accepted for timely completion of building
projects and to get quality output. The Government have
adopted the process followed by Central Public Works
Department.
9. There is no discrimination shown to electrical
contractors. On the other hand, they are given
encouragement and facility to come over to the new process.
The electrical contractors and civil contractors individually or
as joint ventures are permitted to quote in the tender, till they
attain experience in composite category. The 2 nd respondent
emphatically denied the statement that electrical requirements
can be assessed only after the structural work. There will not
be delay in executing electrical work under the composite
tendering system resulting in escalation of cost because the WP(C) No.9671/2020
completion time is fixed between 12 to 24 months.
10. In the initial stages, bidders from major component
category are allowed. If a proper category of composite
contractors is formed as soon as possible, wherein both
eligible civil as well as electrical contractors are enlisted, the
question of uneven advantage to civil category will not arise.
The objective of composite tender is to have better
co-ordination among different components of works. The
electrical part of the work in the composite tender can be
carried out only with the association of electrical contractors
and hence the role of electrical contractors is inevitable,
contended the 2nd respondent.
11. The major issue involved in adopting composite
tender was that of extending level playing field for different
categories of contractors. The Department has addressed the
issue. The new scheme will create a new category of
composite contractors. The existing civil contractors and
existing electrical contractors can very well come over to the
new category. In fact, the Government have provided ample WP(C) No.9671/2020
opportunities to them for that purpose. A civil contractor will
not be able to bid and complete the work without partnering
with registered electrical contractors, unless the civil
contractor himself is a registered electrical contractor. Under
the existing scheme of things, projects used to take 5 to 6
years for completion. Under the new scheme, maximum
completion period of major works will be from 12 months to 24
months. This time target cannot be achieved if tendering of
electrical work is done after completion of civil structural work
of a building. The fear expressed by the petitioner-
Association is therefore baseless. The writ petition is liable to
be dismissed, contended the 2nd respondent.
12. Learned Senior Counsel Sri. G. Sreekumar,
assisted by Sri. Ajith Krishnan, appearing for the petitioner
argued that if the present composite tender system is
implemented, at the time of acceptance of tender, authorities
will have no idea about the execution of electrical works which
usually can be commenced only after the execution of major
part of civil works. By efflux of time taken for execution of civil WP(C) No.9671/2020
work, the cost of electrical work will go up and there will be
change in technology and user of electrical appliances also.
The new system therefore will not produce the desired result.
13. The learned Senior Counsel pointed out that as of
now, registration is required for all components of work. Civil
work will be carried out by civil contractors and electrical work
by electrical contractors. Committing civil contractors to
undertake electrical work after obtaining an undertaking that
he will obtain electrical registration or associate with another
electrical contractor, is not a reasonable classification.
Electrical work in a building contract being a comparatively
minor component work, the category of electrical contractors
will be practically ousted from all bidding processes, since
works where electrical component is major would be very few.
Practically, the electrical contractors will be left to the mercy of
big civil contractors.
14. Placing reliance on the judgment of the Apex Court
in Natural Resources Allocation, In re, Special Reference
No.1 of 2012 [(2012) 10 SCC 1], the learned Senior Counsel WP(C) No.9671/2020
argued that the mandate contained in Article 39 of the
Constitution requires that material resources of the community
should be so distributed as best to subserve the common
good and the Composite Tender System will cause
accumulation of wealth in the hands of a few Civil Corporate
Contractors. The system will only create powerful
monopolies, violating the law laid down by the Apex Court in
Rashbihari Panda v. State of Orissa [(1969) 1 SCC 414].
Relying on the judgment of the Apex Court in Jespar I. Slong
v. State of Meghalaya and others [(2004) 11 SCC 485], the
learned Senior Counsel pointed out that exclusion of
competition in public contracts was always frowned upon by
the Apex Court.
15. The learned Senior Counsel further pointed out that
the new composite tender system will in effect curb
competition. Experts in respective components will be ousted.
Ext.P1 would prevent qualified electrical contractors from
participating in the tender proceedings. Ext.P1 therefore would
offend right of the members of the petitioner-Association WP(C) No.9671/2020
under Article 19(1)(g). The learned Senior Counsel further
argued that Ext.P1 has been issued with malafide motives and
to circumvent the directions of this Court contained in Ext.P4
judgment. By Ext.P5 Government Order, it was decided that a
composite tender must be divided into two parts and
contractors with registration in the PWD alone can participate
in the tender proceedings for execution of electrical works.
But, by Ext.P1, participation of electrical contractors in tender
proceedings is completely eliminated.
16. Ext.P1 would result in fewer participation in tender
proceedings, contended the learned Senior Counsel. Only a
favoured lot will be awarded contracts. A cartel who
monopolise the field would be formed which will takeover the
entire works. As the contractors are given freedom to
determine the estimate rate, huge loss will be caused to the
public exchequer. There will be no transparency in the tender
system. As the new system would take away the opportunity
of the members of the petitioner-Association to bid for
contracts, they will lose their livelihood offending Article 21 of WP(C) No.9671/2020
the Constitution of India. Ext.P1 is therefore liable to be set
aside, argued the Senior Counsel. Placing reliance on the
judgment of the Apex Court in Reliance Energy Limited and
another v. Maharashtra State Road Development
Corporation Limited and others [(2007) 8 SCC 1], the
counsel urged that lack of level playing field under the
proposed tender system, would make it unreasonable.
Departure from the standard of eligibility followed until now,
would make the State action unsustainable, contended the
counsel placing reliance on Ramana Dayaram Shetty v.
International Airport Authority of India and others [(1979)
3 SCC 489].
17. Sri. K.V. Manoj Kumar, learned Senior Government
Pleader, argued that composite tender system is proven to be
the best system of awarding public works now. The Central
Government, the CPWD, Central Public Sector Undertakings
and State PSUs, all follow the composite tender system, which
is more advantageous to the public exchequer. There will not
be exclusion of electrical contractors from bidding. On the WP(C) No.9671/2020
other hand, both existing civil and electrical contractors are
given opportunity to come over to the new system and
become composite contractors.
18. The learned Senior Government Pleader placed
reliance on the judgments of the Apex Court in Shri Sitaram
Sugar Company Limited and another v. Union of India and
others [(1990) 3 SCC 223] and Jal Mahal Resorts Private
Limited v. K.P. Sharma and others [(2014) 8 SCC 804] to
urge that this Court should not venture a judicial review in the
matter which is essentially a policy issue best left to the
executive. Test of reasonableness cannot be applied in these
issues, as held by the Apex Court in G.B. Mahajan v.
Jalgaon Municipal Council and others [(1991) 3 SCC 91],
contended the learned Government Pleader. No person can
claim a fundamental right to carry on business with the
Government, urged the Senior Government Pleader.
19. In fact, the present system will be more beneficial to
the electrical contractors, argued the learned Government
Pleader. Once the Electrical Contractors join a composite WP(C) No.9671/2020
project and complete the work, the entire value of both civil
and electrical component of that work will go to the credit of
the electrical contractors also. Civil contractors as well as
electrical contractors are permitted to undertake works as a
consortium. The fear expressed by the petitioner is therefore
feigned, contended the learned Government Pleader.
20. Heard.
21. The prime ground of challenge against Ext.P1 is
discrimination. A reading of Ext.P1 would show that once
Ext.P1 composite tender scheme is implemented, existing civil
contractors who do not have electrical contract registration will
not be able to bid for the bids, unless they give an undertaking
that they will associate with an electrical contractor having
valid registration. Similarly, an existing electrical contractor
also will have to undertake, unless he has a civil contract
registration, that he will associate with a registered civil
contractor. Therefore, it cannot be said that there is
discrimination between civil contractors and electrical
contractors.
WP(C) No.9671/2020
22. The argument of the petitioners is that since work
where electrical component is major, would be few and far
between, electrical contractors will be excluded from bidding in
majority of the contracts where civil work will be the major
component. This will be so, though to a lesser extent, to civil
contractors also. When electrical work is the major
component of a project, civil contractors will be put to a
comparatively disadvantageous position.
23. To ensure that contractors of minor components will
have opportunities in all public works, the Government have
taken a decision that a major contractor who has been
awarded work will have to undertake that he will associate
with minor component contractors to do minor component
works, unless the major component contractor himself is a
registered contractor for minor component work also. To
compensate such loss of opportunities to registered
contractors in the field, the Government have taken care to
design the composite tender scheme in such a manner that all
the contractors get a fair chance to be part of all contract WP(C) No.9671/2020
works and can gradually migrate to the category of composite
contractors.
24. Learned Senior Counsel for the petitioner heavily
relied on Ext.P4 judgment of this Court, which found that the
competitive tender system introduced as per Ext.P1 Circular
dated 20.04.2008 therein is unsustainable. At the outset, it is
to be noted that the system sought to be introduced as per the
said Circular dated 20.04.2008 and the system introduced as
per Ext.P1 Government Order in this writ petition are different.
25. The learned Single Judge of this Court found
Ext.P1 Circular mentioned in Ext.P4 judgment unsustainable
for the following reasons:-
(1) The additional counter affidavit of the respondents does not answer the various contentions raised by the petitioners that the electrical contractors will be totally excluded from the scene and there will be a monopoly of civil contracts.
(2) Para 20.5.1 of the PWD manual provides that the electrification works in Government buildings should be arranged only through licensed electrical contractors registered in the Department. No amendments to the PWD manual have been WP(C) No.9671/2020
made so far.
(3) Ext.P1 Circular therein does not provide for level playing field for any electrical contractors. The system introduced through Ext.P1 therein will result in absence of any competition from among electrical contractors. It will offend Article 19(1)(g) of the Constitution of India.
26. On a perusal of Ext.P1 Government Order, I find
that it cannot be said that electrical contractors will be
excluded from bidding exclusively and whenever electrical
component is the major work of a project, registered electrical
contractor can make their bid. In the case of works where the
electrical component is not the major component, the
electrical contractors can bid for the work as joint ventures/
consortium or can be a part of the project through agreements
or understanding with the successful bidder.
27. It has to be noted that if electrical component or
electronic component is the major component of any work, in
those cases the civil contractors can also participate only
through a joint venture/consortium or through an agreement or
understanding with the successful bidder. Therefore, it cannot WP(C) No.9671/2020
be said that there is a discrimination as against electrical
contractors.
28. It may be true that majority of works awarded by
Kerala Public Works Department will be having civil work as
the major component and therefore electrical contractors will
be at a disadvantageous position. But then, the 1 st
respondent has devised a scheme by which the electrical
contractors also can participate in all works where civil work is
the major component, by mandating that wherever a
registered civil contractor who himself is not a contractor
having electrical contract registration, such civil contractor will
have to undertake that he will carry out the work in association
with a registered electrical contractor. The electrical
contractors are provided with the opportunity of bidding in
works through joint venture/consortium method also.
Therefore, there will not be substantial reduction of
opportunities to the electrical contractors to participate in
Government works.
WP(C) No.9671/2020
29. In the matter of formulating conditions of a tender,
greater latitude is required to be conceded to State Authorities
unless the action is found to be malicious and misuse of
powers. If the State acts reasonably, fairly and in public
interest, interference by Courts is very restrictive. It has been
so held by the Hon'ble Apex Court in Michigan Rubber
(India) Ltd. v. State of Karnataka and others [(2012) 8 SCC
216].
30. As regards non-amendment of PWD manual, the
said ground relied on in Ext.P4 judgment is not available in the
present writ petition as Ext.P1 Government Order itself
envisages that necessary amendments will be done in the
PWD manual. As regards the lesser competition that may be
resultant of implementing Ext.P1 Government Order, it is to be
noted that Ext.P1 is the result of a policy decision of the
Government. Such decisions are taken by the Government
taking into consideration and after analysing and studying
data collected by the Government and after being convinced
that the policy decision will be more beneficial to the public at WP(C) No.9671/2020
large.
31. In the fast evolving economic, trade and industrial
scenario in the world, there would always be an element of
unpredictability on the efficacy of any policy decision. But,
considering its past experience, the State may have to resort
to and implement such decisions boldly. As long as such
policy decisions do not contravene any of the provisions of
Part III of the Constitution of India and as long as such
decisions are not found to be devoid of any reasons or
unconstitutional, courts of law shall not intervene. Such
decisions are best left to the Executive Authorities.
32. The learned Senior Counsel emphasised on Ext.P7
communication of the Additional Chief Secretary of Finance
Department addressed to the Chief Engineer, PWD
(Buildings), wherein the Additional Chief Secretary informed
that for all building works, the Public Works Department
should mandatorily move for simultaneous tenders for civil and
electrical works to be awarded simultaneously to separate
contractors. The contention of the petitioner is that when the WP(C) No.9671/2020
Finance Department represented by no less than an
Additional Chief Secretary has given a mandatory direction,
the Public Works Department cannot ignore the same and go
for composite tender system as envisaged in Ext.P1. Ext.P7
communication can be only taken as an interdepartmental
communication wherein one Department has communicated
its view on the aspect to another Department. The
Government have to weigh the views and opinions of all
Departments concerned and arrive at a final decision. Ext.P1
order signed by the Governor appears to be culmination of
such a process made by the Government. Ext.P1 therefore
cannot be settled on the basis of Ext.P7.
For all the aforesaid reasons, this Court finds that
there is no justifiable reason to interfere with Ext.P1
Government Order on any of the grounds raised by the
petitioner. The writ petition is therefore dismissed.
Sd/-
N. NAGARESH, JUDGE
aks/25.01.2021 WP(C) No.9671/2020
APPENDIX PETITIONER'S EXHIBITS:
EXHIBIT P1 TRUE COPY OF THE GOVERNMENT ORDER GO(MS) NO.27/2020/PWD DATED 26.02.2020 ISSUED BY THE 2ND RESPONDENT.
EXHIBIT P2 TRUE COPY OF THE CIRCULAR DATED 20.04.2008 ISSUED BY THE 1ST RESPONDENT.
EXHIBIT P3 TRUE COPY OF THE LETTER DATED 24.07.2009 ISSUED BY THE 3RD RESPONDENT.
EXHIBIT P4 TRUE COPY OF THE JUDGMENT DATED 19.11.2010 IN WP(C) NO. 30556/2009.
EXHIBIT P5 TRUE COPY OF THE GOVT.ORDER G.O(RT) NO.65/2011/PWD DATED 13.01.2011 ISSUED BY THE 2ND RESPONDENT.
EXHIBIT P6 TRUE COPY OF THE JUDGMENT DATED 31.03.2015 IN WP(C) NO. 2618/2015.
EXHIBIT P7 TRUE COPY OF THE LETTER DATED 11/10/2019 ISSUED BY THE ADDITIONAL CHIEF SECRETARY FINANCE TO THE 3RD RESPONDENT.
EXHIBIT P8 TRUE COPY OF THE AGREEMENT
NO.SE(K)57/2016/17 DATED 30/01/2017 IN
RELATION TO WORK OF CONSTRUCTION OF GOVT.
MEDICAL COLLEGE, PALAKKAD.
EXHIBIT P9 TRUE COPY OF THE LETTER NO.S.J.E.03/2015,
DATED 7/7/2015, ISSUED BY THE
SUPERINTENDENT, SUB JAIL, ERNAKULAM
EXHIBIT P10 TRUE COPY OF THE RELEVANT PAGES OF WORK
SCHEDULE ISSUED TO THE CONTRACTOR.
EXHIBIT P11 TRUE COPY OF THE RELEVANT PAGE OF WORK
SCHEDULE ISSUED TO THE CONTRACTOR.
EXHIBIT P12 TRUE COPY OF THE LETTER NO.F2/510/2013
DTD.29/06/2013, ISSUED BY THE
SUPERINTENDING ENGINEER, KOZHIKODE.
WP(C) No.9671/2020
EXHIBIT P13 TRUE COPY OF THE ORDER NO.B3-6/2003/CT
DATED 02/02/2018 ISSUED BY THE PRINCIPAL SECRETARY, TAX DEPARTMENT.
EXHIBIT P14 TRUE COPY OF THE GOVERNMENT ORDER G.O.(RT) NO.902/2015/PWD DATED 29/6/2015, ISSUED BY THE 2ND RESPONDENT.
EXHIBIT P15 TRUE COPY OF THE LETTER DATED 16/10/2015, ISSUED BY THE 3RD RESPONDENT PURSUANT TO EXHIBIT P14.
EXHIBIT P16 TRUE COPY OF THE GOVERNMENT ORDER G.O.(RT) NO.1384/2018/PWD DATED 7-9/2018, ISSUED BY THE 2ND RESPONDENT.
ncd
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!